Clearing and grubbing unit price, Washington

Low bidders on WSDOT contracts carried a median of $9,302.50 per ACRE for clearing and grubbing, over the 24 months to 07 OCT 2026, across 2 low bids. Half of all 9 bids fell between $6,600.00 and $25,000.

Owner
Washington State DOT
Item
No code published
Unit
ACRE
Latest letting
15 JUL 2026
$9,302.50Low bidder's median, per ACRE
$20,000Median of all bids, per ACRE
2Contracts in the window
$35,000Engineer's estimate, median per ACRE

By year of letting

Clearing and grubbing, WSDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
200033$3,700.0018$4,070.00
200133$5,300.0020$5,872.50
200243$5,000.0021$5,000.00
200333$3,000.0020$5,000.00
20041414$5,000.0082$7,500.00
20051414$4,321.7573$5,000.00
200699$6,500.0049$6,160.00
20071816$6,535.2093$8,000.00
20081312$5,900.00103$9,000.00
20091716$4,394.50126$5,967.09
20102119$3,700.00178$4,975.00
20111515$5,800.00112$6,440.00
20121313$24,00093$8,000.00
20131110$4,180.0059$8,000.00
20141010$10,00064$10,000
201588$6,375.0051$12,000
20161414$13,95091$18,000
201799$16,00048$15,350
20181010$11,00037$14,000
20191010$14,66347$20,000
202033$30,00011$24,780
20211212$18,50060$20,900
202266$20,00022$26,890
202388$27,75034$64,850
202622$9,302.509$20,000
Clearing and grubbing, WSDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By region

Clearing and grubbing, WSDOT: unit prices by region, all lettings
RegionLow bidsLow-bid medianAll bidsMedian, all bids
NWR region126$10,000824$10,000
OR region33$10,000223$10,146
SWR region27$5,000.00184$5,500.00
ER region21$5,000.0099$5,000.00
NCR region17$3,500.0090$3,000.00
SCR region14$3,700.0073$3,500.00
Clearing and grubbing, WSDOT: unit prices by region, all lettings

Regions with at least three low bids, over all lettings.

By quantity

Clearing and grubbing, WSDOT: low bidder's median by quantity band
Quantity (ACRE)Low bidsLow-bid median
0.02 to 0.3760$23,500
0.40 to 1.3061$8,000.00
1.31 to 5.1060$6,535.20
5.20 to 142.5061$2,860.00
Clearing and grubbing, WSDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest WSDOT contracts carrying Clearing and grubbing
LetContractRegionQuantityLow bidder's priceMedianEstimateBidsLow bidderSource
15 JUL 2026XE3755SCR region1.60$2,605.00$20,000$15,0005INTERWEST CONSTRUCTION, INC.WSDOT
08 JUL 2026XE3751SCR region0.14$16,000$20,500$55,0004TAPANI, INC.WSDOT
08 MAR 2023009937NWR region0.90$84,035$84,035$18,8743INTERWEST CONSTRUCTION, INC.WSDOT
01 MAR 2023009935NWR region0.30$30,582$50,000$25,0005FABER CONSTRUCTION CORP.WSDOT
23 FEB 2023009932NWR region0.30$17,803$70,000$11,0004FABER CONSTRUCTION CORP.WSDOT
23 FEB 2023009925ER region8.50$3,500.00$21,750$5,000.002MAX J. KUNEY COMPANYWSDOT
01 FEB 2023009928OR region1.31$25,500$24,000$24,0004TUCCI & SONS, INC.WSDOT
01 FEB 2023009924NWR region0.16$100,000$100,000$14,0007INTERWEST CONSTRUCTION, INC.WSDOT
11 JAN 2023009908NWR region0.20$30,000$75,000$40,0005KONNERUP CONSTRUCTION, INC.WSDOT
11 JAN 2023009909SWR region0.56$9,900.00$56,500$35,0004THOMPSON BROS. EXCAVATING, INCWSDOT
16 MAR 2022009794OR region0.36$20,000$80,000$30,0005SCARSELLA BROS., INC.WSDOT
09 MAR 2022009774OR region1.70$20,000$22,500$20,0002KRAEMER NORTH AMERICA, LLC.WSDOT
24 FEB 2022009769NWR region2.10$35,600$29,070$20,0004GRANITE CONSTRUCTION COMPANYWSDOT
09 FEB 2022009763OR region6.10$20,000$20,000$12,1007KRAEMER NORTH AMERICA, LLC.WSDOT
20 JAN 2022009754NWR region0.40$19,000$28,780$25,0003GRANITE CONSTRUCTION COMPANYWSDOT
Latest WSDOT contracts carrying Clearing and grubbing

Filter this item by your own quantity, region and period, or check your price against it, in the WSDOT explorer.

How these prices were read

WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are WSDOT's own: this item is compared with WSDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy