Controlled density fill unit price, Washington
Low bidders on WSDOT contracts carried a median of $253.00 per CY for controlled density fill, over the 24 months to 07 OCT 2026, across 1 low bids. Half of all 5 bids fell between $290.38 and $315.00.
- Owner
- Washington State DOT
- Item
- No code published
- Unit
- CY
- Latest letting
- 15 JUL 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2001 | 2 | 2 | $80.00 | 13 | $100.00 |
| 2002 | 3 | 3 | $82.00 | 15 | $90.00 |
| 2003 | 1 | 1 | $150.00 | 4 | $137.50 |
| 2004 | 3 | 3 | $100.00 | 20 | $100.00 |
| 2005 | 1 | 1 | $74.00 | 3 | $95.00 |
| 2006 | 1 | 1 | $155.00 | 2 | $152.50 |
| 2008 | 4 | 4 | $142.50 | 14 | $162.50 |
| 2009 | 2 | 2 | $119.81 | 20 | $118.50 |
| 2010 | 3 | 3 | $120.00 | 14 | $120.00 |
| 2011 | 1 | 1 | $85.00 | 10 | $95.53 |
| 2012 | 1 | 1 | $120.00 | 8 | $118.00 |
| 2013 | 1 | 1 | $105.00 | 9 | $200.00 |
| 2014 | 2 | 2 | $207.50 | 19 | $165.00 |
| 2015 | 1 | 1 | $140.00 | 6 | $145.00 |
| 2016 | 4 | 4 | $250.00 | 30 | $200.00 |
| 2017 | 2 | 2 | $572.00 | 15 | $145.00 |
| 2018 | 2 | 2 | $625.00 | 5 | $250.00 |
| 2019 | 2 | 2 | $4,100.00 | 6 | $460.00 |
| 2020 | 1 | 1 | $233.00 | 4 | $185.00 |
| 2021 | 2 | 2 | $690.00 | 9 | $300.00 |
| 2023 | 1 | 1 | $135.00 | 5 | $250.00 |
| 2026 | 1 | 1 | $253.00 | 5 | $300.00 |
Bid prices as published, not adjusted for inflation.
By region
| Region | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| NWR region | 15 | $110.00 | 91 | $135.00 |
| OR region | 9 | $200.00 | 57 | $150.00 |
| SWR region | 5 | $135.00 | 31 | $195.00 |
| ER region | 4 | $206.50 | 20 | $138.50 |
| SCR region | 3 | $145.00 | 15 | $150.00 |
Regions with at least three low bids, over all lettings.
By quantity
| Quantity (CY) | Low bids | Low-bid median |
|---|---|---|
| 0.30 to 5 | 10 | $325.00 |
| 5 to 13 | 10 | $177.50 |
| 21 to 120 | 10 | $112.50 |
| 139 to 581 | 11 | $110.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | Region | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 15 JUL 2026 | XE3755 | SCR region | 120 | $253.00 | $300.00 | $150.00 | 5 | INTERWEST CONSTRUCTION, INC. | WSDOT |
| 01 FEB 2023 | 009930 | SWR region | 12 | $135.00 | $250.00 | $165.00 | 5 | SELBY BRIDGE COMPANY, INC. | WSDOT |
| 15 DEC 2021 | 009742 | NWR region | 0.50 | $1,200.00 | $1,225.00 | $1,000.00 | 4 | GRANITE CONSTRUCTION COMPANY | WSDOT |
| 13 JAN 2021 | 009623 | ER region | 5 | $180.00 | $200.00 | $200.00 | 5 | MAX J. KUNEY COMPANY | WSDOT |
| 23 JAN 2020 | 009509 | ER region | 91 | $233.00 | $185.00 | $200.00 | 4 | GARCO CONSTRUCTION, INC. | WSDOT |
| 13 MAR 2019 | 009384 | OR region | 8 | $200.00 | $200.00 | $400.00 | 3 | GRANITE CONSTRUCTION COMPANY | WSDOT |
| 30 JAN 2019 | 009375 | ER region | 1 | $8,000.00 | $8,000.00 | $1,000.00 | 3 | CPM DEVELOPMENT CORPORATION | WSDOT |
| 18 APR 2018 | 009233 | NWR region | 0.30 | $1,000.00 | $1,100.00 | $200.00 | 2 | A-1 LANDSCAPING AND CONSTRUCTI | WSDOT |
| 04 APR 2018 | 009238 | SWR region | 281.20 | $250.00 | $230.00 | $160.00 | 3 | ROGNLIN'S, INC. | WSDOT |
| 23 FEB 2017 | 009021 | OR region | 6 | $1,000.00 | $484.40 | $400.00 | 4 | TUCCI & SONS, INC. | WSDOT |
| 11 JAN 2017 | 009002 | NWR region | 267 | $144.00 | $144.00 | $100.00 | 11 | RAM CONSTRUCTION GENERAL | WSDOT |
| 21 DEC 2016 | 008993 | OR region | 1 | $800.00 | $800.00 | $100.00 | 9 | SCARSELLA BROS., INC. | WSDOT |
| 23 MAR 2016 | 008859 | OR region | 21 | $300.00 | $227.50 | $207.00 | 4 | NORDLAND CONSTRUCTION | WSDOT |
| 23 MAR 2016 | 008861 | OR region | 13 | $200.00 | $150.00 | $121.00 | 7 | SCARSELLA BROS., INC. | WSDOT |
| 13 JAN 2016 | 008831 | NWR region | 87 | $84.01 | $142.50 | $160.00 | 10 | FABER CONSTRUCTION CORP. | WSDOT |
Filter this item by your own quantity, region and period, or check your price against it, in the WSDOT explorer.
How these prices were read
WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are WSDOT's own: this item is compared with WSDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.