Crushed surfacing base course unit price, Washington
Low bidders on WSDOT contracts carried a median of $55.00 per CY for crushed surfacing base course, from 16 JAN 2002 to 23 MAR 2022, across 57 low bids. Half of all 209 bids fell between $35.00 and $100.00.
- Owner
- Washington State DOT
- Item
- No code published
- Unit
- CY
- Latest letting
- 23 MAR 2022
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2002 | 2 | 2 | $36.00 | 11 | $40.00 |
| 2003 | 1 | 1 | $22.00 | 5 | $17.50 |
| 2004 | 1 | 1 | $18.00 | 4 | $19.00 |
| 2005 | 4 | 4 | $31.00 | 14 | $35.50 |
| 2006 | 2 | 2 | $66.00 | 5 | $80.00 |
| 2007 | 1 | 1 | $50.00 | 3 | $50.00 |
| 2009 | 2 | 2 | $190.00 | 10 | $165.00 |
| 2010 | 4 | 4 | $45.00 | 18 | $28.85 |
| 2011 | 2 | 2 | $49.10 | 12 | $60.00 |
| 2012 | 3 | 3 | $35.00 | 14 | $60.00 |
| 2013 | 3 | 3 | $32.00 | 16 | $32.50 |
| 2014 | 2 | 2 | $42.50 | 7 | $39.00 |
| 2015 | 4 | 4 | $69.50 | 14 | $78.50 |
| 2016 | 4 | 4 | $92.31 | 12 | $98.25 |
| 2017 | 4 | 4 | $74.50 | 11 | $110.00 |
| 2018 | 7 | 7 | $100.00 | 17 | $75.00 |
| 2019 | 7 | 7 | $55.00 | 21 | $100.00 |
| 2020 | 2 | 2 | $97.50 | 6 | $107.50 |
| 2021 | 1 | 1 | $26.00 | 2 | $27.00 |
| 2022 | 1 | 1 | $78.00 | 7 | $243.00 |
Bid prices as published, not adjusted for inflation.
By region
| Region | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| ER region | 16 | $52.50 | 57 | $60.00 |
| NCR region | 13 | $33.20 | 55 | $39.00 |
| NWR region | 14 | $76.00 | 54 | $92.50 |
| SCR region | 8 | $47.00 | 25 | $88.13 |
| SWR region | 4 | $67.50 | 12 | $67.50 |
Regions with at least three low bids, over all lettings.
By quantity
| Quantity (CY) | Low bids | Low-bid median |
|---|---|---|
| 2 to 20 | 14 | $98.25 |
| 20 to 77 | 14 | $60.00 |
| 80 to 687 | 14 | $65.00 |
| 700 to 4,992.10 | 15 | $33.20 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | Region | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 23 MAR 2022 | 009783 | NWR region | 8 | $78.00 | $243.00 | $200.00 | 7 | INTERWEST CONSTRUCTION, INC. | WSDOT |
| 25 FEB 2021 | 009655 | ER region | 50 | $26.00 | $27.00 | $100.00 | 2 | ROB'S DEMOLITION, INC. | WSDOT |
| 15 APR 2020 | 009547 | NWR region | 20 | $100.00 | $200.00 | $250.00 | 2 | NORTHEAST ELECTRIC, LLC | WSDOT |
| 11 MAR 2020 | 009526 | ER region | 97 | $95.00 | $105.00 | $125.00 | 4 | CENTRAL WASHINGTON ASPHALT, IN | WSDOT |
| 24 APR 2019 | 009426 | ER region | 2,557 | $50.00 | $82.90 | $45.00 | 4 | N.A. DEGERSTROM, INC. | WSDOT |
| 17 APR 2019 | 009418 | SCR region | 1,200 | $44.00 | $67.00 | $80.00 | 3 | ASCORP, INC. DBA DEBCO | WSDOT |
| 20 MAR 2019 | 009407 | ER region | 687 | $55.00 | $91.00 | $80.00 | 3 | CENTRAL WASHINGTON ASPHALT, IN | WSDOT |
| 20 MAR 2019 | 009404 | ER region | 30 | $200.00 | $225.00 | $40.00 | 2 | DIRT AND AGGREGATE INTERCHANGE | WSDOT |
| 13 MAR 2019 | 009396 | SCR region | 202 | $120.00 | $120.00 | $110.00 | 3 | SELLAND CONSTRUCTION, INC. | WSDOT |
| 27 FEB 2019 | 009394 | SWR region | 2 | $1,000.00 | $587.50 | $150.00 | 2 | GRANITE CONSTRUCTION COMPANY | WSDOT |
| 09 JAN 2019 | 009359 | SCR region | 2,387 | $43.50 | $113.35 | $50.00 | 4 | FRANK GURNEY, INC. | WSDOT |
| 24 APR 2018 | 009257 | SCR region | 215 | $35.00 | $40.00 | $65.00 | 3 | INTERSTATE CONCRETE & ASPHALT | WSDOT |
| 21 MAR 2018 | 009222 | SWR region | 340 | $75.00 | $75.00 | $80.00 | 3 | LAKESIDE INDUSTRIES, INC. | WSDOT |
| 07 MAR 2018 | 009216 | NWR region | 11 | $170.00 | $170.00 | $75.00 | 1 | LAKESIDE INDUSTRIES, INC. | WSDOT |
| 22 FEB 2018 | 009210 | ER region | 310 | $50.00 | $50.00 | $100.00 | 3 | N.A. DEGERSTROM, INC. | WSDOT |
Filter this item by your own quantity, region and period, or check your price against it, in the WSDOT explorer.
How these prices were read
WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are WSDOT's own: this item is compared with WSDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.