Construction geotextile for underground drainage unit price, Washington
Low bidders on WSDOT contracts carried a median of $2.50 per SY for construction geotextile for underground drainage, from 29 MAR 2000 to 19 JAN 2023, across 106 low bids. Half of all 665 bids fell between $1.50 and $4.00.
- Owner
- Washington State DOT
- Item
- No code published
- Unit
- SY
- Latest letting
- 19 JAN 2023
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2000 | 1 | 1 | $15.00 | 3 | $15.00 |
| 2002 | 3 | 3 | $2.50 | 16 | $2.00 |
| 2003 | 5 | 5 | $2.00 | 30 | $2.00 |
| 2004 | 5 | 5 | $2.00 | 35 | $2.00 |
| 2005 | 5 | 5 | $2.30 | 37 | $2.25 |
| 2006 | 4 | 4 | $2.00 | 25 | $2.50 |
| 2007 | 9 | 9 | $2.50 | 51 | $2.70 |
| 2008 | 5 | 5 | $2.00 | 40 | $1.96 |
| 2009 | 6 | 6 | $2.02 | 49 | $2.00 |
| 2010 | 11 | 11 | $1.50 | 93 | $1.65 |
| 2011 | 10 | 10 | $3.25 | 70 | $2.50 |
| 2012 | 2 | 2 | $1.62 | 21 | $1.70 |
| 2013 | 3 | 3 | $8.00 | 21 | $3.00 |
| 2014 | 2 | 2 | $1.77 | 15 | $2.00 |
| 2015 | 5 | 5 | $4.00 | 22 | $3.11 |
| 2016 | 3 | 3 | $1.00 | 12 | $4.75 |
| 2017 | 6 | 6 | $3.00 | 31 | $3.00 |
| 2018 | 2 | 2 | $2.25 | 3 | $2.00 |
| 2019 | 5 | 5 | $4.00 | 21 | $4.00 |
| 2020 | 4 | 4 | $2.62 | 22 | $3.25 |
| 2021 | 5 | 5 | $3.00 | 24 | $5.50 |
| 2022 | 3 | 3 | $5.50 | 13 | $6.00 |
| 2023 | 2 | 2 | $4.00 | 11 | $5.00 |
Bid prices as published, not adjusted for inflation.
By region
| Region | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| NWR region | 58 | $2.00 | 402 | $2.00 |
| OR region | 16 | $5.00 | 89 | $5.00 |
| SWR region | 9 | $2.00 | 61 | $2.00 |
| SCR region | 11 | $1.55 | 50 | $2.00 |
| NCR region | 7 | $5.00 | 37 | $3.00 |
| ER region | 4 | $2.88 | 23 | $3.00 |
Regions with at least three low bids, over all lettings.
By quantity
| Quantity (SY) | Low bids | Low-bid median |
|---|---|---|
| 10 to 142 | 26 | $5.00 |
| 150 to 508 | 27 | $3.25 |
| 530 to 1,650 | 26 | $2.00 |
| 1,660 to 32,740 | 27 | $1.50 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | Region | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 19 JAN 2023 | 009891 | OR region | 56 | $5.00 | $10.00 | $12.00 | 7 | CECCANTI, INC. | WSDOT |
| 11 JAN 2023 | 009909 | SWR region | 534 | $3.00 | $3.50 | $4.00 | 4 | THOMPSON BROS. EXCAVATING, INC | WSDOT |
| 06 APR 2022 | 009789 | OR region | 30 | $21.00 | $21.00 | $8.00 | 3 | INTERWEST CONSTRUCTION, INC. | WSDOT |
| 02 MAR 2022 | 009762 | NWR region | 590 | $5.50 | $3.00 | $5.00 | 3 | MIDMOUNTAIN CONTRACTORS, INC. | WSDOT |
| 09 FEB 2022 | 009763 | OR region | 170 | $5.00 | $6.00 | $5.00 | 7 | KRAEMER NORTH AMERICA, LLC. | WSDOT |
| 15 DEC 2021 | 009742 | NWR region | 70 | $2.50 | $7.50 | $4.00 | 4 | GRANITE CONSTRUCTION COMPANY | WSDOT |
| 21 APR 2021 | 009662 | NWR region | 370 | $6.00 | $3.00 | $2.00 | 4 | SCARSELLA BROS., INC. | WSDOT |
| 10 FEB 2021 | 009643 | NWR region | 177 | $2.00 | $5.75 | $3.00 | 8 | STRIDER CONSTRUCTION CO., INC. | WSDOT |
| 03 FEB 2021 | 009646 | NWR region | 110 | $3.00 | $6.00 | $3.00 | 5 | OCEANSIDE CONSTRUCTION, INC. | WSDOT |
| 21 JAN 2021 | 009637 | NCR region | 438 | $5.00 | $5.00 | $4.00 | 3 | NORTHEAST ELECTRIC, LLC | WSDOT |
| 08 APR 2020 | 009535 | OR region | 103 | $5.00 | $5.00 | $8.00 | 5 | ROGNLIN'S, INC. | WSDOT |
| 20 FEB 2020 | 009516 | OR region | 1,556 | $2.00 | $2.85 | $3.25 | 8 | INTERWEST CONSTRUCTION, INC. | WSDOT |
| 05 FEB 2020 | 009501 | NWR region | 4,080 | $2.00 | $2.00 | $20.00 | 5 | TITAN EARTHWORK LLC | WSDOT |
| 23 JAN 2020 | 009509 | ER region | 150 | $3.25 | $3.62 | $7.00 | 4 | GARCO CONSTRUCTION, INC. | WSDOT |
| 17 APR 2019 | 009418 | SCR region | 800 | $3.00 | $3.00 | $2.00 | 3 | ASCORP, INC. DBA DEBCO | WSDOT |
Filter this item by your own quantity, region and period, or check your price against it, in the WSDOT explorer.
How these prices were read
WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are WSDOT's own: this item is compared with WSDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.