WisDOT contract 20250114007 bid tabulation
C of Sun Prairie, N. Thompson Road; CTH C to West Main Street (LOC STR, Dane County City of Sun Prairie, N. Thompson Road). Let by Wisconsin DOT on January 14, 2025, Dane. 5 bids received; low bid $2,786,338 by Payne and Dolan, Inc.
- Owner
- Wisconsin DOT
- Letting
- 14 JAN 2025
- Pay items
- 107
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Payne and Dolan, Inc | $2,786,338 | Low |
| 2 | Rock Road Companies, Inc. | $3,070,995 | +10% |
| 3 | Tri-County Paving, Inc. | $3,078,577 | +10% |
| 4 | Lalonde Contractors Incorporated | $3,174,146 | +14% |
| 5 | Zignego Company, Inc. | $3,284,844 | +18% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Payne and Dolan, Inc | 2. Rock Road Companies, Inc. | 3. Tri-County Paving, Inc. | 4. Lalonde Contractors Incorporated | 5. Zignego Company, Inc. |
|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete pavement (204.0100) | SY | 168 | $16.80 | $19.00 | $16.80 | $13.89 | $20.00 |
| 2 | Removing asphaltic surface (204.0110) | SY | 51,650 | $1.89 | $0.50 | $3.44 | $3.78 | $1.89 |
| 3 | Removing gutter (204.0140) | LF | 300 | $5.00 | $6.00 | $5.00 | $6.26 | $20.00 |
| 4 | Removing curb & gutter (204.0150) | LF | 10,990 | $3.30 | $7.50 | $3.30 | $6.26 | $10.00 |
| 5 | Removing concrete sidewalk (204.0155) | SY | 1,595 | $16.80 | $10.00 | $16.80 | $10.90 | $10.00 |
| 6 | Removing manholes (204.0210) | EACH | 1 | $1,341.00 | $750.00 | $1,341.00 | $1,200.00 | $750.00 |
| 7 | Removing inlets (204.0220) | EACH | 22 | $835.00 | $750.00 | $835.00 | $950.00 | $500.00 |
| 8 | Removing storm sewer (size) 01. 12-inch (204.0245) | LF | 455 | $57.80 | $32.00 | $57.80 | $45.00 | $20.00 |
| 9 | Removing storm sewer (size) 02. 15-inch (204.0245) | LF | 67 | $57.80 | $34.00 | $57.80 | $53.00 | $20.00 |
| 10 | Removing storm sewer (size) 03. 18-inch (204.0245) | LF | 72 | $57.80 | $36.00 | $57.80 | $55.00 | $20.00 |
| 11 | Sealing pipes (204.0280) | EACH | 1 | $610.00 | $500.00 | $610.00 | $550.00 | $750.00 |
| 12 | Excavation common (205.0100) | CY | 1,790 | $31.00 | $20.00 | $27.25 | $30.00 | $30.00 |
| 13 | Prepare foundation for asphaltic paving (project) 01. 3996-00-31 (211.0101) | EACH | 1 | $79,200 | $125,000 | $85,000 | $25,475 | $1.00 |
| 14 | Finishing roadway (project) 01. 3996-00-31 (213.0100) | EACH | 1 | $1,500.00 | $7,502.06 | $40,000 | $3,008.00 | $1,000.00 |
| 15 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 3,700 | $19.30 | $23.00 | $23.90 | $23.68 | $30.00 |
| 16 | Select crushed material (312.0110) | TON | 1,130 | $18.70 | $20.00 | $25.40 | $19.83 | $30.00 |
| 17 | Drilled tie bars (416.0610) | EACH | 228 | $10.59 | $10.59 | $10.59 | $13.88 | $30.00 |
| 18 | Tack coat (455.0605) | GAL | 2,354 | $0.01 | $3.00 | $2.75 | $0.01 | $0.01 |
| 19 | Incentive density HMA pavement (460.2000) | DOL | 8,450 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 20 | HMA pavement 3 MT 58-28 S (460.6223) | TON | 7,910 | $65.00 | $75.87 | $68.50 | $65.00 | $65.00 |
| 21 | HMA pavement 4 MT 58-28 S (460.6224) | TON | 5,280 | $68.20 | $79.87 | $72.75 | $68.20 | $68.20 |
| 22 | Asphaltic surface (465.0105) | TON | 300 | $80.00 | $115.00 | $89.60 | $80.00 | $80.00 |
| 23 | Concrete collars for pipe (520.8000) | EACH | 2 | $660.00 | $500.00 | $660.00 | $800.00 | $1,000.00 |
| 24 | Concrete curb & gutter 18-inch type D (601.0407) | LF | 70 | $44.96 | $44.96 | $44.96 | $51.94 | $70.00 |
| 25 | Concrete curb & gutter 30-inch type A (601.0409) | LF | 32 | $58.90 | $58.90 | $58.90 | $53.80 | $70.00 |
| 26 | Concrete curb & gutter 30-inch type D (601.0411) | LF | 9,445 | $23.47 | $23.47 | $23.47 | $30.44 | $47.00 |
| 27 | Concrete curb pedestrian (601.0600) | LF | 38 | $57.31 | $57.31 | $57.31 | $52.22 | $70.00 |
| 28 | Concrete sidewalk 4-inch (602.0405) | SF | 1,040 | $4.07 | $4.07 | $4.07 | $8.09 | $8.50 |
| 29 | Concrete sidewalk 6-inch (602.0415) | SF | 25,635 | $6.56 | $6.56 | $6.56 | $9.35 | $10.21 |
| 30 | Curb ramp detectable warning field natural patina (602.0515) | SF | 1,090 | $49.06 | $49.06 | $49.06 | $40.59 | $50.00 |
| 31 | Curb ramp detectable warning field radial natural patina (602.0615) | SF | 432.39 | $58.95 | $58.95 | $58.95 | $56.18 | $75.00 |
| 32 | Concrete driveway 6-inch (602.0810) | SY | 259 | $59.04 | $59.04 | $59.04 | $83.95 | $100.00 |
| 33 | Storm sewer pipe reinforced concrete class IV 12-inch (608.0412) | LF | 310 | $135.60 | $70.00 | $135.60 | $140.00 | $141.00 |
| 34 | Storm sewer pipe reinforced concrete class IV 15-inch (608.0415) | LF | 26 | $160.00 | $80.00 | $160.00 | $139.00 | $146.00 |
| 35 | Storm sewer pipe reinforced concrete class IV 18-inch (608.0418) | LF | 35 | $175.90 | $90.00 | $175.90 | $146.00 | $154.00 |
| 36 | Storm sewer pipe reinforced concrete class IV 30-inch (608.0430) | LF | 26 | $234.00 | $140.00 | $234.00 | $226.00 | $196.00 |
| 37 | Manhole covers type J (611.0530) | EACH | 3 | $1,170.00 | $1,000.00 | $1,170.00 | $770.00 | $801.00 |
| 38 | Catch basins 4-FT diameter (611.1004) | EACH | 5 | $3,370.00 | $3,100.00 | $3,370.00 | $4,286.00 | $4,900.00 |
| 39 | Catch basins 6-FT diameter (611.1006) | EACH | 2 | $7,500.00 | $7,000.00 | $7,500.00 | $8,576.00 | $8,000.00 |
| 40 | Manholes 4-FT diameter (611.2004) | EACH | 3 | $3,370.00 | $3,100.00 | $3,370.00 | $4,130.00 | $4,800.00 |
| 41 | Inlets 2.5X3-FT (611.3253) | EACH | 19 | $2,925.00 | $3,200.00 | $2,925.00 | $3,798.00 | $4,200.00 |
| 42 | Adjusting manhole covers (611.8110) | EACH | 54 | $575.00 | $950.00 | $575.00 | $841.00 | $850.00 |
| 43 | Adjusting inlet covers (611.8115) | EACH | 35 | $535.00 | $1,400.00 | $535.00 | $841.00 | $850.00 |
| 44 | Insulation board polystyrene (inch) 01. 2-inch (612.0902.S) | SY | 8 | $84.40 | $50.00 | $84.40 | $46.00 | $50.00 |
| 45 | Mobilization (619.1000) | EACH | 1 | $63,000 | $160,221 | $110,000 | $162,974 | $144,000 |
| 46 | Water (624.0100) | MGAL | 40 | $0.01 | $300.00 | $70.00 | $54.40 | $50.00 |
| 47 | Topsoil (625.0100) | SY | 6,420 | $9.80 | $10.00 | $9.40 | $11.35 | $8.00 |
| 48 | Mobilizations erosion control (628.1905) | EACH | 6 | $100.00 | $100.00 | $1.00 | $225.00 | $225.00 |
| 49 | Mobilizations emergency erosion control (628.1910) | EACH | 3 | $100.00 | $100.00 | $1.00 | $225.00 | $225.00 |
| 50 | Erosion mat class I type A (628.2002) | SY | 5,840 | $4.00 | $4.00 | $3.00 | $1.08 | $1.08 |
| 51 | Inlet protection type C (628.7015) | EACH | 100 | $65.00 | $65.00 | $60.00 | $58.00 | $58.00 |
| 52 | Fertilizer type B (629.0210) | CWT | 4 | $250.00 | $250.00 | $150.00 | $85.00 | $85.00 |
| 53 | Seeding mixture no. 40 (630.0140) | LB | 107 | $30.00 | $30.00 | $15.00 | $12.75 | $12.75 |
| 54 | Seed water (630.0500) | MGAL | 34 | $100.00 | $100.00 | $50.00 | $50.00 | $50.00 |
| 55 | Posts tubular steel 2X2-inch X 14- FT (634.0814) | EACH | 56 | $180.00 | $180.00 | $210.00 | $215.00 | $215.00 |
| 56 | Posts tubular steel 2X2-inch X 16- FT (634.0816) | EACH | 4 | $200.00 | $200.00 | $215.00 | $220.00 | $220.00 |
| 57 | Signs type II reflective H (637.2210) | SF | 284.50 | $19.50 | $19.50 | $28.00 | $20.00 | $20.00 |
| 58 | Signs type II reflective F (637.2230) | SF | 27.25 | $21.00 | $21.00 | $30.00 | $23.00 | $23.00 |
| 59 | Moving signs type II (638.2102) | EACH | 77 | $100.00 | $100.00 | $100.00 | $95.00 | $95.00 |
| 60 | Removing signs type II (638.2602) | EACH | 12 | $35.00 | $35.00 | $50.00 | $28.00 | $28.00 |
| 61 | Removing small sign supports (638.3000) | EACH | 12 | $35.00 | $35.00 | $50.00 | $28.00 | $28.00 |
| 62 | Moving small sign supports (638.4000) | EACH | 32 | $100.00 | $100.00 | $50.00 | $80.00 | $80.00 |
| 63 | Field office type C (642.5201) | EACH | 1 | $3,500.00 | $12,000 | $20,000 | $15,968 | $10,000 |
| 64 | Traffic control drums (643.0300) | DAY | 4,815 | $0.20 | $0.20 | $0.20 | $0.20 | $0.20 |
| 65 | Traffic control barricades type III (643.0420) | DAY | 7,853 | $0.25 | $0.35 | $0.25 | $0.35 | $0.35 |
| 66 | Traffic control warning lights type A (643.0705) | DAY | 13,849 | $0.06 | $0.09 | $0.06 | $0.09 | $0.09 |
| 67 | Traffic control arrow boards (643.0800) | DAY | 5 | $40.00 | $100.00 | $40.00 | $100.00 | $100.00 |
| 68 | Traffic control signs (643.0900) | DAY | 13,607 | $0.21 | $0.25 | $0.21 | $0.25 | $0.25 |
| 69 | Traffic control covering signs type II (643.0920) | EACH | 6 | $112.00 | $30.00 | $112.00 | $30.00 | $30.00 |
| 70 | Traffic control signs fixed message (643.1000) | SF | 26.50 | $15.50 | $16.00 | $15.50 | $16.00 | $16.00 |
| 71 | Traffic control signs PCMS (643.1050) | DAY | 42 | $45.00 | $69.00 | $45.00 | $69.00 | $69.00 |
| 72 | Temporary marking removable mask out tape 12-inch (643.3990) | LF | 300 | $7.00 | $5.00 | $7.00 | $5.00 | $5.00 |
| 73 | Traffic control (643.5000) | EACH | 1 | $14,585 | $5,500.00 | $20,585 | $5,500.00 | $5,500.00 |
| 74 | Marking line epoxy 4-inch (646.1020) | LF | 45,310 | $0.40 | $0.40 | $0.40 | $0.65 | $0.65 |
| 75 | Marking line epoxy 8-inch (646.3020) | LF | 435 | $1.00 | $1.00 | $1.00 | $1.30 | $1.30 |
| 76 | Marking arrow epoxy (646.5020) | EACH | 96 | $172.25 | $172.25 | $172.25 | $200.00 | $200.00 |
| 77 | Marking symbol epoxy (646.5220) | EACH | 95 | $161.15 | $161.15 | $161.15 | $230.00 | $230.00 |
| 78 | Marking stop line epoxy 18-inch (646.6120) | LF | 735 | $14.00 | $14.00 | $14.00 | $13.00 | $13.00 |
| 79 | Marking yield line epoxy 18-inch (646.6220) | EACH | 71 | $32.95 | $32.95 | $32.95 | $60.00 | $60.00 |
| 80 | Marking diagonal epoxy 12-inch (646.7120) | LF | 150 | $13.45 | $13.45 | $13.45 | $9.00 | $9.00 |
| 81 | Marking crosswalk epoxy transverse line 6-inch (646.7420) | LF | 1,845 | $13.00 | $13.00 | $13.00 | $10.00 | $10.00 |
| 82 | Marking curb epoxy (646.8120) | LF | 40 | $6.60 | $6.60 | $6.60 | $8.00 | $8.00 |
| 83 | Marking island nose epoxy (646.8220) | EACH | 3 | $259.50 | $259.50 | $259.50 | $250.00 | $250.00 |
| 84 | Construction staking storm sewer (650.4000) | EACH | 30 | $215.00 | $215.00 | $215.00 | $215.00 | $150.00 |
| 85 | Construction staking base (650.5000) | LF | 9,270 | $0.85 | $0.85 | $0.85 | $0.85 | $0.75 |
| 86 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 11,385 | $0.82 | $0.82 | $0.82 | $0.82 | $1.50 |
| 87 | Construction staking resurfacing reference (650.8000) | LF | 9,270 | $0.18 | $0.18 | $0.18 | $0.18 | $0.10 |
| 88 | Construction staking curb ramps (650.9000) | EACH | 98 | $215.00 | $215.00 | $215.00 | $215.00 | $200.00 |
| 89 | Construction staking sidewalk (project) 01. 3996-00-31 (650.9500) | EACH | 1 | $2,300.00 | $2,300.00 | $2,300.00 | $2,300.00 | $2,000.00 |
| 90 | Construction staking supplemental control (project) 01. 3996-00-31 (650.9911) | EACH | 1 | $1,800.00 | $1,800.00 | $1,800.00 | $1,800.00 | $4,000.00 |
| 91 | Sawing asphalt (690.0150) | LF | 2,405 | $1.15 | $1.39 | $1.75 | $1.15 | $1.39 |
| 92 | Sawing concrete (690.0250) | LF | 1,445 | $2.25 | $2.25 | $2.35 | $2.25 | $2.00 |
| 93 | Incentive compressive strength concrete pavement (715.0720) | DOL | 1,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 94 | Incentive iri ride (740.0440) | DOL | 7,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 95 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 2,000 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 |
| 96 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 1,320 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 |
| 97 | Special 01. reconnect storm sewer laterals (SPV.0060) | EACH | 1 | $1,684.00 | $1,500.00 | $1,684.00 | $2,983.00 | $1,000.00 |
| 98 | Special 02. adjusting water valve boxes (SPV.0060) | EACH | 30 | $340.00 | $250.00 | $340.00 | $396.30 | $800.00 |
| 99 | Special 03. inlet covers type D (SPV.0060) | EACH | 26 | $1,795.00 | $1,500.00 | $1,795.00 | $995.00 | $920.00 |
| 100 | Special 04. dynamic speed display sign assembly solar powered (SPV.0060) | EACH | 4 | $5,000.00 | $5,000.00 | $5,580.00 | $5,000.00 | $5,000.00 |
| 101 | Special 05. rectangular rapid flashing beacon (RRFB) single light bar system (SPV.0060) | EACH | 8 | $8,000.00 | $8,000.00 | $9,951.00 | $8,000.00 | $8,000.00 |
| 102 | Special 06. rectangular rapid flashing beacon (RRFB) double light bar system (SPV.0060) | EACH | 4 | $8,500.00 | $8,500.00 | $10,890 | $8,500.00 | $8,500.00 |
| 103 | Special 07. rectangular rapid flashing beacon (RRFB) trombone system (SPV.0060) | EACH | 2 | $17,500 | $17,500 | $16,465 | $17,500 | $17,500 |
| 104 | Special 08. marked raised crosswalk epoxy (SPV.0060) | EACH | 4 | $318.25 | $318.25 | $318.25 | $500.00 | $500.00 |
| 105 | Special 01. concrete curb & gutter 36-inch special (SPV.0090) | LF | 1,800 | $35.58 | $35.58 | $35.58 | $47.07 | $50.00 |
| 106 | Special 02. marking crosswalk epoxy block style 18-inch (SPV.0090) | LF | 1,495 | $22.75 | $22.75 | $22.75 | $12.50 | $12.50 |
| 107 | Special 01. raised concrete crosswalk (SPV.0180) | SY | 161 | $105.24 | $105.24 | $105.24 | $221.15 | $161.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of January 14, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.