WisDOT contract 20250114018 bid tabulation
2225-00-73. Let by Wisconsin DOT on January 14, 2025, Milwaukee. 6 bids received; low bid $4,946,007 by Stark Pavement Corporation.
- Owner
- Wisconsin DOT
- Letting
- 14 JAN 2025
- Pay items
- 176
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Stark Pavement Corporation | $4,946,007 | Low |
| 2 | Zignego Company, Inc. | $4,986,103 | +1.0% |
| 3 | Vinton Construction Company | $5,121,805 | +4.0% |
| 4 | Rock Road Companies, Inc. | $5,214,706 | +5.0% |
| 5 | Lalonde Contractors Incorporated | $5,396,679 | +9.0% |
| 6 | Payne and Dolan, Inc | $5,898,747 | +19% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Stark Pavement Corporation | 2. Zignego Company, Inc. | 3. Vinton Construction Company | 4. Rock Road Companies, Inc. | 5. Lalonde Contractors Incorporated | 6. Payne and Dolan, Inc |
|---|---|---|---|---|---|---|---|---|---|
| 1 | CPM progress schedule (108.4400) | EACH | 1 | $6,000.00 | $1,000.00 | $4,000.00 | $0.01 | $4,940.00 | $5,335.00 |
| 2 | Grubbing (201.0205) | STA | 9 | $249.00 | $249.00 | $249.00 | $320.00 | $249.00 | $268.92 |
| 3 | Grubbing (201.0220) | ID | 28 | $11.95 | $11.95 | $11.95 | $10.00 | $11.95 | $12.91 |
| 4 | Removing small pipe culverts (203.0100) | EACH | 5 | $400.00 | $350.00 | $166.00 | $166.00 | $400.00 | $179.28 |
| 5 | Removing concrete pavement (204.0100) | SY | 1,653 | $12.00 | $1.00 | $0.01 | $0.01 | $15.46 | $1.00 |
| 6 | Removing asphaltic surface butt joints (204.0115) | SY | 653 | $11.00 | $11.00 | $4.80 | $4.80 | $11.00 | $33.56 |
| 7 | Removing asphaltic surface milling (204.0120) | SY | 49,576 | $3.98 | $3.98 | $1.00 | $1.00 | $3.98 | $4.25 |
| 8 | Removing curb & gutter (204.0150) | LF | 4 | $125.00 | $100.00 | $20.00 | $20.00 | $41.92 | $21.60 |
| 9 | Removing concrete sidewalk (204.0155) | SY | 121 | $26.50 | $20.00 | $27.00 | $27.00 | $15.95 | $29.16 |
| 10 | Removing masonry (204.0185) | CY | 86 | $60.00 | $30.00 | $125.00 | $125.00 | $92.94 | $135.00 |
| 11 | Removing concrete bases (204.0195) | EACH | 1 | $500.00 | $1,000.00 | $1,000.00 | $1,000.00 | $929.67 | $1,080.00 |
| 12 | Removing manholes (204.0210) | EACH | 6 | $500.00 | $400.00 | $341.00 | $341.00 | $500.00 | $368.28 |
| 13 | Removing inlets (204.0220) | EACH | 18 | $450.00 | $405.00 | $217.50 | $217.50 | $450.00 | $234.90 |
| 14 | Removing storm sewer (size) 01. 10-inch (204.0245) | LF | 167 | $15.00 | $10.00 | $13.00 | $13.00 | $15.00 | $14.04 |
| 15 | Removing storm sewer (size) 02. 12-inch (204.0245) | LF | 664 | $15.00 | $11.00 | $13.25 | $13.25 | $15.00 | $14.31 |
| 16 | Removing storm sewer (size) 03. 15-inch (204.0245) | LF | 74 | $15.00 | $12.00 | $13.50 | $13.50 | $15.00 | $14.58 |
| 17 | Removing storm sewer (size) 04. 18-inch (204.0245) | LF | 128 | $15.00 | $13.00 | $18.25 | $18.25 | $15.00 | $19.71 |
| 18 | Removing storm sewer (size) 05. 21-inch (204.0245) | LF | 147 | $15.00 | $14.00 | $19.00 | $19.00 | $15.00 | $20.52 |
| 19 | Removing storm sewer (size) 06. 24-inch (204.0245) | LF | 83 | $15.00 | $15.00 | $23.75 | $23.75 | $15.00 | $25.65 |
| 20 | Removing storm sewer (size) 07. 30-inch (204.0245) | LF | 45 | $15.00 | $16.00 | $26.00 | $26.00 | $15.00 | $28.08 |
| 21 | Removing (item description) 01. removing decorative headwalls (204.9060.S) | EACH | 18 | $500.00 | $50.00 | $100.00 | $100.00 | $500.00 | $108.00 |
| 22 | Excavation common (205.0100) | CY | 2,459 | $25.00 | $29.00 | $49.97 | $49.97 | $45.20 | $53.97 |
| 23 | Backfill granular grade 1 (209.1100) | CY | 180 | $30.00 | $50.00 | $25.00 | $25.00 | $66.70 | $27.00 |
| 24 | Prepare foundation for asphaltic paving (project) 01. 2225-00-73 (211.0101) | EACH | 1 | $4,000.00 | $4,000.00 | $64,807 | $73,933 | $4,000.00 | $92,500 |
| 25 | Finishing roadway (project) 01. 2225-00-73 (213.0100) | EACH | 1 | $2,000.00 | $1,000.00 | $5,000.00 | $15,721 | $3,808.00 | $4,000.00 |
| 26 | Base aggregate dense 3/4-inch (305.0110) | TON | 2,002 | $24.00 | $0.01 | $42.50 | $42.50 | $33.28 | $45.90 |
| 27 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 1,051 | $27.00 | $20.00 | $35.30 | $35.30 | $24.23 | $45.00 |
| 28 | Shaping shoulders (305.0500) | STA | 277 | $15.00 | $150.00 | $57.00 | $26.33 | $92.63 | $100.00 |
| 29 | Base aggregate open-graded (310.0110) | TON | 915 | $41.00 | $52.00 | $40.25 | $40.25 | $40.10 | $43.47 |
| 30 | Breaker run (311.0110) | TON | 2,070 | $24.00 | $11.00 | $31.20 | $31.20 | $24.03 | $33.70 |
| 31 | Tack coat (455.0605) | GAL | 9,078 | $3.00 | $3.00 | $3.52 | $3.52 | $3.00 | $2.30 |
| 32 | Incentive density HMA pavement (460.2000) | DOL | 15,024 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 33 | HMA pavement 3 LT 58-28 S (460.5223) | TON | 8,527 | $78.60 | $78.60 | $77.92 | $77.92 | $78.60 | $94.25 |
| 34 | HMA pavement 4 LT 58-28 S (460.5224) | TON | 5,869 | $78.60 | $78.60 | $83.92 | $83.92 | $78.60 | $91.25 |
| 35 | Asphaltic surface (465.0105) | TON | 81 | $136.40 | $136.40 | $231.29 | $231.29 | $136.40 | $345.00 |
| 36 | Asphaltic surface driveways and field entrances (465.0120) | TON | 130 | $136.40 | $136.40 | $184.78 | $184.78 | $136.40 | $345.00 |
| 37 | Concrete collars for pipe (520.8000) | EACH | 32 | $500.00 | $750.00 | $462.50 | $462.50 | $500.00 | $499.50 |
| 38 | Apron endwalls for culvert pipe reinforced concrete 18-inch (522.1018) | EACH | 1 | $1,100.00 | $1,500.00 | $1,078.00 | $1,078.00 | $1,100.00 | $1,164.24 |
| 39 | Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 29X45-inch (522.2629) | EACH | 1 | $2,000.00 | $2,000.00 | $1,797.00 | $1,797.00 | $2,000.00 | $1,940.76 |
| 40 | Concrete curb type D (601.0110) | LF | 76 | $45.00 | $100.00 | $50.00 | $49.53 | $59.59 | $54.00 |
| 41 | Concrete curb & gutter 30-inch type D (601.0411) | LF | 176 | $45.00 | $75.00 | $50.00 | $29.44 | $56.50 | $54.00 |
| 42 | Concrete sidewalk 5-inch (602.0410) | SF | 5,749 | $12.00 | $13.00 | $9.00 | $6.70 | $10.32 | $9.72 |
| 43 | Curb ramp detectable warning field natural patina (602.0515) | SF | 468 | $53.00 | $50.00 | $45.00 | $49.06 | $41.98 | $48.60 |
| 44 | Curb ramp detectable warning field radial natural patina (602.0615) | SF | 301 | $62.00 | $75.00 | $55.00 | $61.62 | $54.46 | $59.40 |
| 45 | Riprap medium (606.0200) | CY | 6 | $120.00 | $300.00 | $250.00 | $250.00 | $280.60 | $270.00 |
| 46 | Storm sewer pipe reinforced concrete class III 12-inch (608.0312) | LF | 753 | $90.00 | $105.00 | $78.00 | $78.00 | $90.00 | $84.24 |
| 47 | Storm sewer pipe reinforced concrete class III 15-inch (608.0315) | LF | 468 | $95.00 | $110.00 | $84.00 | $84.00 | $95.00 | $90.72 |
| 48 | Storm sewer pipe reinforced concrete class III 18-inch (608.0318) | LF | 92 | $110.00 | $120.00 | $86.50 | $86.50 | $110.00 | $93.42 |
| 49 | Storm sewer pipe reinforced concrete class III 21-inch (608.0321) | LF | 60 | $130.00 | $135.00 | $104.00 | $104.00 | $130.00 | $112.32 |
| 50 | Storm sewer pipe reinforced concrete class III 24-inch (608.0324) | LF | 17 | $170.00 | $150.00 | $109.50 | $109.50 | $170.00 | $118.26 |
| 51 | Storm sewer pipe reinforced concrete class IV 12-inch (608.0412) | LF | 249 | $90.00 | $105.00 | $78.00 | $78.00 | $90.00 | $84.24 |
| 52 | Storm sewer pipe reinforced concrete class IV 15-inch (608.0415) | LF | 107 | $95.00 | $120.00 | $84.00 | $84.00 | $95.00 | $90.72 |
| 53 | Storm sewer pipe reinforced concrete class IV 21-inch (608.0421) | LF | 108 | $130.00 | $100.00 | $105.00 | $105.00 | $130.00 | $113.40 |
| 54 | Storm sewer pipe reinforced concrete horizontal elliptical class HE-III 29X45-inch (608.2329) | LF | 35 | $240.00 | $350.00 | $250.00 | $250.00 | $240.00 | $270.00 |
| 55 | Storm sewer pipe reinforced concrete horizontal elliptical class HE-IV 24X38-inch (608.2424) | LF | 301 | $190.00 | $305.00 | $213.00 | $213.00 | $190.00 | $230.04 |
| 56 | Storm sewer pipe reinforced concrete horizontal elliptical class HE-IV 29X45-inch (608.2429) | LF | 100 | $240.00 | $325.00 | $275.00 | $275.00 | $240.00 | $297.00 |
| 57 | Manhole covers type J (611.0530) | EACH | 3 | $750.00 | $450.00 | $496.00 | $496.00 | $750.00 | $535.68 |
| 58 | Manhole covers type J-special (611.0535) | EACH | 5 | $1,500.00 | $450.00 | $535.00 | $535.00 | $1,500.00 | $577.80 |
| 59 | Inlet covers type C (611.0612) | EACH | 3 | $760.00 | $449.00 | $516.00 | $516.00 | $760.00 | $557.28 |
| 60 | Inlet covers type MS (611.0642) | EACH | 30 | $700.00 | $485.00 | $505.00 | $505.00 | $700.00 | $545.40 |
| 61 | Manholes 4-FT diameter (611.2004) | EACH | 10 | $2,700.00 | $2,100.00 | $3,474.00 | $3,474.00 | $2,700.00 | $3,751.92 |
| 62 | Manholes 5-FT diameter (611.2005) | EACH | 1 | $4,650.00 | $2,200.00 | $5,396.00 | $5,396.00 | $4,650.00 | $5,827.68 |
| 63 | Manholes 6-FT diameter (611.2006) | EACH | 5 | $6,200.00 | $2,400.00 | $6,290.00 | $6,290.00 | $6,200.00 | $6,793.20 |
| 64 | Manholes 7-FT diameter (611.2007) | EACH | 2 | $8,500.00 | $3,000.00 | $7,440.00 | $7,440.00 | $8,500.00 | $8,035.20 |
| 65 | Manholes 5X5-FT (611.2055) | EACH | 1 | $4,750.00 | $10,500 | $6,597.50 | $6,597.50 | $4,750.00 | $7,125.30 |
| 66 | Inlets 4-FT diameter (611.3004) | EACH | 3 | $2,700.00 | $2,500.00 | $2,900.00 | $2,900.00 | $2,700.00 | $3,132.00 |
| 67 | Inlets median 1 grate (611.3901) | EACH | 18 | $2,800.00 | $2,600.00 | $3,193.00 | $3,193.00 | $2,800.00 | $3,448.44 |
| 68 | Inlets median 2 grate (611.3902) | EACH | 11 | $3,000.00 | $2,900.00 | $3,730.50 | $3,730.50 | $3,000.00 | $4,028.94 |
| 69 | Pipe underdrain 6-inch (612.0106) | LF | 3,282 | $2.80 | $14.50 | $3.65 | $3.65 | $25.00 | $3.94 |
| 70 | Pipe underdrain unperforated 6- inch (612.0206) | LF | 172 | $8.00 | $50.00 | $12.65 | $12.65 | $25.00 | $13.66 |
| 71 | Underdrain trench (612.0600) | LF | 172 | $30.00 | $50.00 | $0.01 | $0.01 | $25.00 | $0.01 |
| 72 | Apron endwalls for underdrain reinforced concrete 6-inch (612.0806) | EACH | 20 | $185.00 | $1,000.00 | $156.25 | $156.25 | $220.00 | $168.75 |
| 73 | Fence safety (616.0700.S) | LF | 600 | $1.00 | $1.00 | $1.00 | $3.90 | $1.00 | $1.08 |
| 74 | Maintenance and repair of haul roads (project) 01. 2225-00-73 (618.0100) | EACH | 1 | $1,000.00 | $1.00 | $0.01 | $0.01 | $1.00 | $1,500.00 |
| 75 | Mobilization (619.1000) | EACH | 1 | $132,000 | $679,000 | $370,000 | $393,938 | $409,162 | $287,000 |
| 76 | Dust control surface treatment (623.0200) | SY | 7,085 | $0.20 | $0.01 | $0.01 | $0.10 | $0.01 | $0.25 |
| 77 | Water (624.0100) | MGAL | 42 | $20.00 | $50.00 | $0.01 | $0.01 | $54.40 | $0.01 |
| 78 | Topsoil (625.0100) | SY | 9,226 | $4.49 | $4.49 | $4.49 | $10.50 | $4.49 | $4.85 |
| 79 | Mulching (627.0200) | SY | 9,226 | $0.01 | $0.01 | $0.01 | $0.32 | $0.01 | $0.01 |
| 80 | Erosion bales (628.1104) | EACH | 41 | $0.50 | $0.50 | $0.50 | $11.50 | $0.50 | $0.54 |
| 81 | Silt fence (628.1504) | LF | 1,113 | $2.15 | $2.15 | $2.15 | $1.75 | $2.15 | $2.32 |
| 82 | Silt fence maintenance (628.1520) | LF | 1,113 | $0.10 | $0.10 | $0.10 | $0.04 | $0.10 | $0.11 |
| 83 | Mobilizations erosion control (628.1905) | EACH | 4 | $100.00 | $100.00 | $100.00 | $200.00 | $100.00 | $108.00 |
| 84 | Mobilizations emergency erosion control (628.1910) | EACH | 4 | $1.00 | $1.00 | $1.00 | $75.00 | $1.00 | $1.08 |
| 85 | Erosion mat urban class I type B (628.2008) | SY | 9,226 | $1.99 | $1.99 | $1.99 | $1.98 | $1.99 | $2.15 |
| 86 | Inlet protection type A (628.7005) | EACH | 24 | $1.00 | $1.00 | $1.00 | $77.50 | $1.00 | $1.08 |
| 87 | Inlet protection type B (628.7010) | EACH | 119 | $70.00 | $70.00 | $70.00 | $39.50 | $70.00 | $75.60 |
| 88 | Temporary ditch checks (628.7504) | LF | 214 | $9.00 | $9.00 | $9.00 | $11.50 | $9.00 | $9.72 |
| 89 | Culvert pipe checks (628.7555) | EACH | 436 | $0.10 | $0.10 | $0.10 | $18.00 | $0.10 | $0.11 |
| 90 | Rock bags (628.7570) | EACH | 100 | $1.00 | $1.00 | $1.00 | $11.50 | $1.00 | $1.08 |
| 91 | Fertilizer type B (629.0210) | CWT | 11 | $80.00 | $80.00 | $80.00 | $77.90 | $80.00 | $86.40 |
| 92 | Seeding mixture no. 40 (630.0140) | LB | 172 | $12.85 | $12.85 | $12.85 | $8.75 | $12.85 | $13.88 |
| 93 | Seeding temporary (630.0200) | LB | 68 | $3.00 | $3.00 | $3.00 | $7.00 | $3.00 | $3.24 |
| 94 | Seed water (630.0500) | MGAL | 59 | $30.00 | $30.00 | $30.00 | $10.00 | $30.00 | $32.40 |
| 95 | Posts wood 4X6-inch X 18-FT (634.0618) | EACH | 6 | $140.00 | $140.00 | $140.00 | $115.00 | $140.00 | $151.20 |
| 96 | Posts tubular steel 2X2-inch X 18- FT (634.0818) | EACH | 74 | $240.00 | $240.00 | $240.00 | $245.00 | $240.00 | $259.20 |
| 97 | Signs type II reflective H (637.2210) | SF | 380.27 | $21.00 | $21.00 | $21.00 | $20.99 | $21.00 | $22.68 |
| 98 | Signs type II reflective F (637.2230) | SF | 390.86 | $23.00 | $23.00 | $23.00 | $24.50 | $23.00 | $24.84 |
| 99 | Moving signs type II (638.2102) | EACH | 7 | $59.00 | $59.00 | $59.00 | $95.00 | $59.00 | $63.72 |
| 100 | Removing signs type II (638.2602) | EACH | 71 | $20.00 | $20.00 | $20.00 | $20.50 | $20.00 | $21.60 |
| 101 | Removing small sign supports (638.3000) | EACH | 71 | $20.00 | $20.00 | $20.00 | $21.00 | $20.00 | $21.60 |
| 102 | Field office type B (642.5001) | EACH | 1 | $13,500 | $20,000 | $15,000 | $22,500 | $16,068 | $30,000 |
| 103 | Traffic control drums (643.0300) | DAY | 87,334 | $0.12 | $0.12 | $0.12 | $0.12 | $0.12 | $0.22 |
| 104 | Traffic control barricades type III (643.0420) | DAY | 9,587 | $0.60 | $0.60 | $0.60 | $0.60 | $0.60 | $0.76 |
| 105 | Traffic control warning lights type A (643.0705) | DAY | 19,173 | $0.10 | $0.10 | $0.10 | $0.10 | $0.10 | $0.11 |
| 106 | Traffic control signs (643.0900) | DAY | 36,840 | $0.40 | $0.40 | $0.40 | $0.40 | $0.40 | $0.38 |
| 107 | Traffic control covering signs type II (643.0920) | EACH | 10 | $50.00 | $50.00 | $50.00 | $50.00 | $50.00 | $43.20 |
| 108 | Traffic control signs fixed message (643.1000) | SF | 257 | $18.50 | $18.50 | $18.50 | $18.50 | $18.50 | $21.60 |
| 109 | Traffic control signs PCMS (643.1050) | DAY | 28 | $30.00 | $30.00 | $30.00 | $30.00 | $30.00 | $32.40 |
| 110 | Traffic control (643.5000) | EACH | 1 | $23,369 | $23,369 | $23,369 | $23,369 | $23,369 | $42,784 |
| 111 | Geotextile type DF schedule A (645.0111) | SY | 4,365 | $1.60 | $4.00 | $2.00 | $2.00 | $5.00 | $2.16 |
| 112 | Geotextile type HR (645.0120) | SY | 33 | $5.00 | $10.00 | $10.00 | $10.00 | $11.62 | $10.80 |
| 113 | Geogrid type SR (645.0220) | SY | 850 | $3.20 | $5.00 | $3.00 | $3.00 | $2.97 | $3.24 |
| 114 | Marking line epoxy 4-inch (646.1020) | LF | 36,244 | $0.65 | $0.65 | $0.65 | $0.65 | $0.65 | $0.70 |
| 115 | Marking line epoxy 8-inch (646.3020) | LF | 1,039 | $1.30 | $1.30 | $1.30 | $1.30 | $1.30 | $1.40 |
| 116 | Marking arrow epoxy (646.5020) | EACH | 15 | $220.00 | $220.00 | $220.00 | $220.00 | $220.00 | $237.60 |
| 117 | Marking outfall epoxy (646.5520) | EACH | 22 | $65.00 | $65.00 | $65.00 | $65.00 | $65.00 | $70.20 |
| 118 | Marking stop line epoxy 18-inch (646.6120) | LF | 622 | $13.00 | $13.00 | $13.00 | $13.00 | $13.00 | $14.04 |
| 119 | Marking diagonal epoxy 12-inch (646.7120) | LF | 851 | $9.50 | $9.50 | $9.50 | $9.50 | $9.50 | $10.26 |
| 120 | Marking crosswalk epoxy transverse line 6-inch (646.7420) | LF | 656 | $10.50 | $10.50 | $10.50 | $10.50 | $10.50 | $11.34 |
| 121 | Marking crosswalk epoxy block style 24-inch (646.7520) | LF | 798 | $17.50 | $17.50 | $17.50 | $17.50 | $17.50 | $18.90 |
| 122 | Construction staking storm sewer (650.4000) | EACH | 48 | $115.00 | $115.00 | $115.00 | $115.00 | $115.00 | $124.20 |
| 123 | Construction staking subgrade (650.4500) | LF | 3,337 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 |
| 124 | Construction staking base (650.5000) | LF | 3,337 | $0.01 | $1.25 | $1.25 | $0.01 | $0.01 | $1.35 |
| 125 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 251 | $1.25 | $1.25 | $1.25 | $1.25 | $1.25 | $1.35 |
| 126 | Construction staking resurfacing reference (650.8000) | LF | 13,817 | $0.15 | $0.15 | $0.15 | $0.15 | $0.15 | $0.16 |
| 127 | Construction staking curb ramps (650.9000) | EACH | 55 | $125.00 | $125.00 | $125.00 | $125.00 | $125.00 | $135.00 |
| 128 | Construction staking supplemental control (project) 01. 2225-00-73 (650.9911) | EACH | 1 | $2,500.00 | $2,500.00 | $2,500.00 | $2,500.00 | $2,500.00 | $2,700.00 |
| 129 | Construction staking slope stakes (650.9920) | LF | 3,337 | $0.70 | $0.70 | $0.70 | $0.70 | $0.70 | $0.76 |
| 130 | Sawing asphalt (690.0150) | LF | 13,013 | $1.39 | $1.39 | $1.39 | $1.56 | $1.75 | $1.51 |
| 131 | Sawing concrete (690.0250) | LF | 4,023 | $3.50 | $3.50 | $3.50 | $2.50 | $5.00 | $6.05 |
| 132 | Incentive iri ride (740.0440) | DOL | 5,234 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 133 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 1,000 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 |
| 134 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 2,400 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 |
| 135 | Special 01. temporary pedestrian crossings (SPV.0060) | EACH | 20 | $6,320.00 | $806.89 | $2,800.00 | $2,800.00 | $5,230.42 | $8,695.36 |
| 136 | Special 02. utility line opening (SPV.0060) | EACH | 24 | $950.00 | $0.01 | $925.00 | $925.00 | $1,200.00 | $999.00 |
| 137 | Special 03. concrete base special (SPV.0060) | EACH | 1 | $3,283.50 | $3,283.50 | $2,700.00 | $3,283.50 | $2,700.00 | $3,546.18 |
| 138 | Special 31. pipe connection to existing structure (SPV.0060) | EACH | 5 | $600.00 | $650.00 | $855.00 | $855.00 | $600.00 | $923.40 |
| 139 | Special 32. manhole covers special (SPV.0060) | EACH | 8 | $800.00 | $400.00 | $503.00 | $503.00 | $800.00 | $543.24 |
| 140 | Special 33. inlet covers special (SPV.0060) | EACH | 5 | $780.00 | $300.00 | $484.00 | $484.00 | $780.00 | $522.72 |
| 141 | Special 40. hydrant assembly with 6-inch gate valve (SPV.0060) | EACH | 27 | $8,650.00 | $8,100.00 | $11,330 | $11,330 | $8,650.00 | $12,236 |
| 142 | Special 41. 8-inch gate valve and valve box (SPV.0060) | EACH | 14 | $2,750.00 | $2,500.00 | $3,055.00 | $3,055.00 | $2,750.00 | $3,299.40 |
| 143 | Special 42. 12-inch gate valve and valve box (SPV.0060) | EACH | 24 | $7,100.00 | $4,500.00 | $7,000.00 | $7,000.00 | $7,100.00 | $7,560.00 |
| 144 | Special 43. 1.25-inch corporation stop (SPV.0060) | EACH | 42 | $630.00 | $650.00 | $1,974.00 | $1,974.00 | $630.00 | $2,131.92 |
| 145 | Special 44. 1.5-inch corporation stop (SPV.0060) | EACH | 1 | $600.00 | $750.00 | $2,161.50 | $2,161.50 | $600.00 | $2,334.42 |
| 146 | Special 45. 2-inch corporation stop (SPV.0060) | EACH | 1 | $725.00 | $850.00 | $2,307.00 | $2,307.00 | $725.00 | $2,491.56 |
| 147 | Special 46. 1.25-inch curb box (SPV.0060) | EACH | 42 | $380.00 | $350.00 | $1,743.00 | $1,743.00 | $380.00 | $1,882.44 |
| 148 | Special 47. 1.5-inch curb box (SPV.0060) | EACH | 1 | $500.00 | $400.00 | $1,530.00 | $1,530.00 | $500.00 | $1,652.40 |
| 149 | Special 48. 2-inch curb box (SPV.0060) | EACH | 1 | $650.00 | $500.00 | $1,671.00 | $1,671.00 | $650.00 | $1,804.68 |
| 150 | Special 49. cap and abandon existing water main (SPV.0060) | EACH | 21 | $2,000.00 | $1,500.00 | $333.35 | $333.35 | $2,000.00 | $360.02 |
| 151 | Special 50. adjusting sanitary manhole (SPV.0060) | EACH | 6 | $900.00 | $425.00 | $1,368.00 | $1,368.00 | $900.00 | $1,477.44 |
| 152 | Special 51. adjusting water valve boxes (SPV.0060) | EACH | 10 | $800.00 | $150.00 | $475.00 | $475.00 | $800.00 | $513.00 |
| 153 | Special 61. RRFB system STH 32 NB at barnett LN assembly (SPV.0060) | EACH | 1 | $10,053 | $10,053 | $10,053 | $10,053 | $10,053 | $10,857 |
| 154 | Special 62. RRFB system STH 32 SB at holly CT assembly (SPV.0060) | EACH | 1 | $10,053 | $10,053 | $10,053 | $10,053 | $10,053 | $10,857 |
| 155 | Special 63. RRFB system STH 32 NB at green tree RD assembly (SPV.0060) | EACH | 1 | $10,053 | $10,053 | $10,053 | $10,053 | $10,053 | $10,857 |
| 156 | Special 64. RRFB system STH 32 SB at green tree RD assembly (SPV.0060) | EACH | 1 | $10,053 | $10,053 | $10,053 | $10,053 | $10,053 | $10,857 |
| 157 | Special 65. RRFB system STH 32 NB at bridge LN assembly (SPV.0060) | EACH | 1 | $10,053 | $10,053 | $10,053 | $10,053 | $10,053 | $10,857 |
| 158 | Special 66. RRFB system STH 32 SB at bridge LN assembly (SPV.0060) | EACH | 1 | $10,053 | $10,053 | $10,053 | $10,053 | $10,053 | $10,857 |
| 159 | Special 67. RRFB system STH 32 NB at beach DR assembly (SPV.0060) | EACH | 1 | $10,053 | $10,053 | $10,053 | $10,053 | $10,053 | $10,857 |
| 160 | Special 68. RRFB system STH 32 SB at beach DR assembly (SPV.0060) | EACH | 1 | $10,053 | $10,053 | $10,053 | $10,053 | $10,053 | $10,857 |
| 161 | Special 69. RRFB system STH 32 NB at fox LN assembly (SPV.0060) | EACH | 1 | $10,053 | $10,053 | $10,053 | $10,053 | $10,053 | $10,857 |
| 162 | Special 70. RRFB system STH 32 SB at fox LN assembly (SPV.0060) | EACH | 1 | $10,053 | $10,053 | $10,053 | $10,053 | $10,053 | $10,857 |
| 163 | Special 71. RRFB system STH 32 NB at dean RD assembly (SPV.0060) | EACH | 1 | $10,053 | $10,053 | $10,053 | $10,053 | $10,053 | $10,857 |
| 164 | Special 72. RRFB system STH 32 SB at dean RD assembly (SPV.0060) | EACH | 1 | $10,053 | $10,053 | $10,053 | $10,053 | $10,053 | $10,857 |
| 165 | Special 01. pavement cleanup project 2225-00-73 (SPV.0075) | HRS | 40 | $250.00 | $250.00 | $250.00 | $250.00 | $250.00 | $250.00 |
| 166 | Special 01. concrete ditch bottoms (SPV.0090) | LF | 99 | $75.00 | $100.00 | $75.00 | $110.63 | $67.53 | $64.80 |
| 167 | Special 31. pipe underdrain exploration (SPV.0090) | LF | 100 | $25.00 | $50.00 | $10.60 | $10.60 | $25.00 | $11.45 |
| 168 | Special 32. storm sewer lateral exploation (SPV.0090) | LF | 100 | $25.00 | $50.00 | $10.60 | $10.60 | $25.00 | $11.45 |
| 169 | Special 40. hydrant lead 6-inch (SPV.0090) | LF | 490 | $100.00 | $105.00 | $80.25 | $80.25 | $100.00 | $86.67 |
| 170 | Special 41. PVC water main 6-inch (SPV.0090) | LF | 166 | $340.00 | $110.00 | $224.00 | $224.00 | $340.00 | $241.92 |
| 171 | Special 42. PVC water main 8-inch (SPV.0090) | LF | 1,761 | $150.00 | $145.00 | $196.00 | $196.00 | $150.00 | $211.68 |
| 172 | Special 43. PVC water main 12- inch (SPV.0090) | LF | 2,435 | $270.00 | $155.00 | $229.50 | $229.50 | $270.00 | $247.86 |
| 173 | Special 44. HDPE water service 1.25-inch (SPV.0090) | LF | 1,668 | $115.00 | $105.00 | $38.00 | $38.00 | $115.00 | $41.04 |
| 174 | Special 45. HDPE water service 1. 5-inch (SPV.0090) | LF | 26 | $120.00 | $135.00 | $47.50 | $47.50 | $120.00 | $51.30 |
| 175 | Special 46. HDPE water service 2- inch (SPV.0090) | LF | 55 | $140.00 | $150.00 | $69.75 | $69.75 | $140.00 | $75.33 |
| 176 | Special 01. management of solid waste (SPV.0195) | TON | 125 | $135.00 | $100.00 | $150.00 | $150.00 | $134.44 | $162.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of January 14, 2025. Compiled by Mirage Metrics.