Manitowoc - Green Bay; Sra 51 Maribel/Sra 52 Denmark (IH 043, Manitowoc County Manitowoc - Green Bay). Let by Wisconsin DOT on January 14, 2025, Manitowoc. 2 bids received; low bid $10,992,638 by Frank O. Zeise Construction Co., Inc..

Owner
Wisconsin DOT
Letting
14 JAN 2025
Pay items
34
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Frank O. Zeise Construction Co., Inc.$10,992,638Low
2Miron Construction Co., Inc.$12,633,855+15%
WisDOT contract 20250114044: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Frank O. Zeise Construction Co., Inc.2. Miron Construction Co., Inc.
1Finishing roadway (project) 01. 1225-10-73 (213.0100)EACH1$5,000.00$5,543.00
2Storm sewer pipe composite 8-inch (608.6008)LF985$73.00$94.13
3Maintenance and repair of haul roads (project) 01. 1225-10-73 (618.0100)EACH1$10,000$8,272.00
4Mobilization (619.1000)EACH1$20,420$1,173,780
5Drill hole in earth 12-inch (639.0112)LF442$252.00$279.05
6Drill hole in rock 8-inch (639.0508)LF548$192.00$212.61
7Drill hole in rock 12-inch (639.0512)LF138$300.00$332.24
8Well casing pipe 8-inch (639.1008)LF590$172.00$190.46
9Well screen (639.1700)LF40$400.00$221.60
10Grout for sealing well casing (639.2100)CF280$80.00$34.19
11Test pumping (639.4000)EACH4$3,713.00$4,113.50
12Special 01. rest area 51 building, general construction (SPV.0060)EACH1$3,185,709$3,012,133
13Special 02. rest area 52 building, general construction (SPV.0060)EACH1$3,185,709$3,012,144
14Special 03. rest area 51 building, plumbing (SPV.0060)EACH1$379,095$419,787
15Special 04. rest area 52 building, plumbing (SPV.0060)EACH1$379,095$419,787
16Special 05. rest area 51 building, heating and ventilation (SPV.0060)EACH1$822,250$905,521
17Special 06. rest area 52 building, heating and ventilation (SPV.0060)EACH1$822,250$905,521
18Special 07. rest area 51 building, electrical (SPV.0060)EACH1$319,750$354,071
19Special 08. rest area 52 building, electrical (SPV.0060)EACH1$319,750$354,071
20Special 09. rest area 51 maintenance building (SPV.0060)EACH1$253,514$394,062
21Special 10. rest area 52 maintenance building (SPV.0060)EACH1$253,514$394,061
22Special 11. picnic shelter large (SPV.0060)EACH2$31,768$59,131
23Special 12. picnic shelter small (SPV.0060)EACH4$27,521$54,958
24Special 13. pitless adaptor (SPV.0060)EACH4$4,634.00$5,133.25
25Special 14. well system controls (SPV.0060)EACH2$56,968$63,085
26Special 15. well pump (SPV.0060)EACH4$21,509$23,819
27Special 16. construction staking, water system (SPV.0060)EACH2$500.00$553.50
28Special 24. construction staking, building (SPV.0060)EACH4$1,500.00$1,662.50
29Special 25. coring manhole (SPV.0060)EACH5$750.00$1,386.00
30Special 01. underground copper water line, 3-inch (SPV.0090)LF711$145.00$148.39
31Special 02. underground copper water line, 1-inch (SPV.0090)LF436$62.00$60.92
32Special 03. sanitary sewer PVC, 6- inch (SPV.0090)LF95$89.00$94.22
33Special 04. sanitary sewer PVC, 8- inch (SPV.0090)LF102$97.00$127.42
34Special 05. construction staking, sanitary sewer system (SPV.0090)LF197$3.00$3.31
WisDOT contract 20250114044: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of January 14, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy