WisDOT contract 20250311025 bid tabulation
T Mishicot, Samz Road; Cherney Road - Ridge Road (LOC STR, Manitowoc County T Mishicot, Samz Road). Let by Wisconsin DOT on March 11, 2025, Manitowoc. 3 bids received; low bid $913,296 by Vinton Construction Company.
- Owner
- Wisconsin DOT
- Letting
- 11 MAR 2025
- Pay items
- 74
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Vinton Construction Company | $913,296 | Low |
| 2 | Peters Concrete Company | $1,026,322 | +12% |
| 3 | Michels Road & Stone, Inc. | $1,086,052 | +19% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Vinton Construction Company | 2. Peters Concrete Company | 3. Michels Road & Stone, Inc. |
|---|---|---|---|---|---|---|
| 1 | Removing small pipe culverts (203.0100) | EACH | 8 | $320.00 | $285.00 | $435.00 |
| 2 | Excavation common (205.0100) | CY | 11,030 | $14.24 | $15.25 | $13.80 |
| 3 | Finishing roadway (project) 01. 4307-02-71 (213.0100) | EACH | 1 | $2,000.00 | $1,000.00 | $6,500.00 |
| 4 | Obliterating old road (214.0100) | STA | 3 | $100.00 | $1,240.00 | $1,722.00 |
| 5 | Base aggregate dense 3/4-inch (305.0110) | TON | 1,560 | $21.60 | $20.82 | $18.30 |
| 6 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 14,590 | $9.80 | $15.54 | $10.10 |
| 7 | Breaker run (311.0110) | TON | 608 | $18.70 | $16.10 | $19.40 |
| 8 | HMA cold weather paving (450.4000) | TON | 1,766 | $2.25 | $0.01 | $2.25 |
| 9 | Tack coat (455.0605) | GAL | 990 | $4.00 | $4.50 | $4.00 |
| 10 | Incentive density HMA pavement (460.2000) | DOL | 2,260 | $1.00 | $1.00 | $1.00 |
| 11 | HMA pavement 3 LT 58-28 S (460.5223) | TON | 1,963 | $74.60 | $89.00 | $74.60 |
| 12 | HMA pavement 4 LT 58-28 S (460.5224) | TON | 1,568 | $79.30 | $86.00 | $79.30 |
| 13 | Asphaltic surface driveways and field entrances (465.0120) | TON | 38 | $210.00 | $135.00 | $210.00 |
| 14 | Asphaltic flumes (465.0315) | SY | 49 | $72.00 | $50.00 | $72.00 |
| 15 | Apron endwalls for culvert pipe 18- inch (520.1018) | EACH | 12 | $240.00 | $195.00 | $226.00 |
| 16 | Apron endwalls for culvert pipe 24- inch (520.1024) | EACH | 4 | $320.00 | $260.00 | $323.00 |
| 17 | Apron endwalls for pipe arch steel 17X13-inch (521.1217) | EACH | 4 | $226.00 | $165.00 | $210.00 |
| 18 | Culvert pipe corrugated steel 18- inch (521.3118) | LF | 360 | $56.00 | $51.55 | $66.00 |
| 19 | Culvert pipe corrugated steel 24- inch (521.3124) | LF | 120 | $67.00 | $66.40 | $75.00 |
| 20 | Pipe arch corrugated steel 17X13- inch (521.3717) | LF | 45 | $53.00 | $79.80 | $75.00 |
| 21 | Culvert pipe reinforced concrete class IV 18-inch (522.0418) | LF | 46 | $94.00 | $107.00 | $92.00 |
| 22 | Culvert pipe reinforced concrete class IV 24-inch (522.0424) | LF | 96 | $123.00 | $132.00 | $115.00 |
| 23 | Apron endwalls for culvert pipe reinforced concrete 18-inch (522.1018) | EACH | 2 | $1,386.00 | $2,215.00 | $1,415.00 |
| 24 | Apron endwalls for culvert pipe reinforced concrete 24-inch (522.1024) | EACH | 4 | $1,543.00 | $2,400.00 | $1,628.00 |
| 25 | Culvert pipe reinforced concrete horizontal elliptical class HE-III 14X23-inch (522.2314) | LF | 90 | $138.00 | $150.90 | $143.00 |
| 26 | Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 14X23-inch (522.2614) | EACH | 2 | $1,425.00 | $2,250.00 | $1,462.00 |
| 27 | Concrete curb & gutter 30-inch type D (601.0411) | LF | 114 | $34.20 | $33.00 | $33.00 |
| 28 | Concrete curb & gutter 6-inch sloped 36-inch type D (601.0557) | LF | 321 | $32.70 | $33.00 | $33.00 |
| 29 | Riprap medium (606.0200) | CY | 10 | $150.00 | $113.60 | $188.00 |
| 30 | Mobilization (619.1000) | EACH | 1 | $56,000 | $39,180 | $161,376 |
| 31 | Water (624.0100) | MGAL | 323 | $0.01 | $1.00 | $47.00 |
| 32 | Topsoil (625.0100) | SY | 20,610 | $1.90 | $1.73 | $3.45 |
| 33 | Mulching (627.0200) | SY | 14,500 | $0.36 | $0.36 | $0.35 |
| 34 | Silt fence (628.1504) | LF | 900 | $2.39 | $2.39 | $2.25 |
| 35 | Silt fence maintenance (628.1520) | LF | 900 | $0.01 | $0.01 | $0.01 |
| 36 | Mobilizations erosion control (628.1905) | EACH | 5 | $0.01 | $0.01 | $150.00 |
| 37 | Mobilizations emergency erosion control (628.1910) | EACH | 5 | $0.01 | $0.01 | $25.00 |
| 38 | Erosion mat class I type B (628.2004) | SY | 6,120 | $1.68 | $1.68 | $1.40 |
| 39 | Temporary ditch checks (628.7504) | LF | 48 | $8.67 | $8.67 | $10.00 |
| 40 | Culvert pipe checks (628.7555) | EACH | 33 | $22.15 | $22.15 | $18.00 |
| 41 | Fertilizer type B (629.0210) | CWT | 24 | $126.82 | $126.82 | $95.00 |
| 42 | Seeding mixture no. 30 (630.0130) | LB | 868 | $7.98 | $7.98 | $7.80 |
| 43 | Seeding mixture no. 40 (630.0140) | LB | 65 | $7.66 | $7.66 | $9.50 |
| 44 | Seeding temporary (630.0200) | LB | 560 | $2.75 | $2.75 | $3.75 |
| 45 | Seed water (630.0500) | MGAL | 572 | $0.01 | $0.01 | $8.00 |
| 46 | Markers culvert end (633.5200) | EACH | 8 | $63.45 | $63.45 | $68.00 |
| 47 | Posts wood 4X6-inch X 16-FT (634.0616) | EACH | 15 | $172.80 | $172.80 | $84.00 |
| 48 | Signs type II reflective H (637.2210) | SF | 67.51 | $22.00 | $22.00 | $22.00 |
| 49 | Signs type II reflective F (637.2230) | SF | 35 | $24.20 | $24.20 | $22.75 |
| 50 | Moving signs type II (638.2102) | EACH | 2 | $93.75 | $93.75 | $75.00 |
| 51 | Removing signs type II (638.2602) | EACH | 16 | $31.25 | $31.25 | $37.50 |
| 52 | Removing small sign supports (638.3000) | EACH | 15 | $34.38 | $34.38 | $37.50 |
| 53 | Field office type C (642.5201) | EACH | 1 | $8,500.00 | $8,650.00 | $16,000 |
| 54 | Traffic control drums (643.0300) | DAY | 1,800 | $0.19 | $0.19 | $0.19 |
| 55 | Traffic control barricades type III (643.0420) | DAY | 1,440 | $0.58 | $0.58 | $0.58 |
| 56 | Traffic control warning lights type A (643.0705) | DAY | 1,728 | $0.15 | $0.15 | $0.15 |
| 57 | Traffic control signs (643.0900) | DAY | 2,016 | $0.18 | $0.18 | $0.18 |
| 58 | Traffic control signs PCMS (643.1050) | DAY | 14 | $55.00 | $55.00 | $55.00 |
| 59 | Traffic control (643.5000) | EACH | 1 | $4,895.00 | $4,895.00 | $4,895.00 |
| 60 | Geotextile type HR (645.0120) | SY | 64 | $6.00 | $3.00 | $6.50 |
| 61 | Marking line epoxy 6-inch (646.2020) | LF | 9,295 | $0.87 | $0.87 | $0.87 |
| 62 | Marking stop line epoxy 18-inch (646.6120) | LF | 126 | $18.00 | $18.00 | $18.00 |
| 63 | Cold weather marking epoxy 6-inch (646.6466) | LF | 9,295 | $0.29 | $0.29 | $0.29 |
| 64 | Construction staking subgrade (650.4500) | LF | 4,682 | $0.01 | $0.01 | $0.01 |
| 65 | Construction staking base (650.5000) | LF | 4,682 | $0.58 | $0.58 | $0.58 |
| 66 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 435 | $0.75 | $0.75 | $0.75 |
| 67 | Construction staking pipe culverts (650.6000) | EACH | 4 | $100.00 | $100.00 | $100.00 |
| 68 | Construction staking supplemental control (project) 01. 4307-02-71 (650.9911) | EACH | 1 | $10.00 | $10.00 | $10.00 |
| 69 | Construction staking slope stakes (650.9920) | LF | 4,682 | $0.83 | $0.83 | $0.83 |
| 70 | Sawing asphalt (690.0150) | LF | 88 | $3.00 | $2.95 | $2.95 |
| 71 | Incentive iri ride (740.0440) | DOL | 3,180 | $1.00 | $1.00 | $1.00 |
| 72 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 300 | $5.00 | $5.00 | $5.00 |
| 73 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 600 | $5.00 | $5.00 | $5.00 |
| 74 | Special 01. reestablish section corner monuments (SPV.0060) | EACH | 2 | $800.00 | $800.00 | $800.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of March 11, 2025. Compiled by Mirage Metrics.