WisDOT contract 20250311025 bid tabulation

T Mishicot, Samz Road; Cherney Road - Ridge Road (LOC STR, Manitowoc County T Mishicot, Samz Road). Let by Wisconsin DOT on March 11, 2025, Manitowoc. 3 bids received; low bid $913,296 by Vinton Construction Company.

Owner
Wisconsin DOT
Letting
11 MAR 2025
Pay items
74
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Vinton Construction Company$913,296Low
2Peters Concrete Company$1,026,322+12%
3Michels Road & Stone, Inc.$1,086,052+19%
WisDOT contract 20250311025: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Vinton Construction Company2. Peters Concrete Company3. Michels Road & Stone, Inc.
1Removing small pipe culverts (203.0100)EACH8$320.00$285.00$435.00
2Excavation common (205.0100)CY11,030$14.24$15.25$13.80
3Finishing roadway (project) 01. 4307-02-71 (213.0100)EACH1$2,000.00$1,000.00$6,500.00
4Obliterating old road (214.0100)STA3$100.00$1,240.00$1,722.00
5Base aggregate dense 3/4-inch (305.0110)TON1,560$21.60$20.82$18.30
6Base aggregate dense 1 1/4-inch (305.0120)TON14,590$9.80$15.54$10.10
7Breaker run (311.0110)TON608$18.70$16.10$19.40
8HMA cold weather paving (450.4000)TON1,766$2.25$0.01$2.25
9Tack coat (455.0605)GAL990$4.00$4.50$4.00
10Incentive density HMA pavement (460.2000)DOL2,260$1.00$1.00$1.00
11HMA pavement 3 LT 58-28 S (460.5223)TON1,963$74.60$89.00$74.60
12HMA pavement 4 LT 58-28 S (460.5224)TON1,568$79.30$86.00$79.30
13Asphaltic surface driveways and field entrances (465.0120)TON38$210.00$135.00$210.00
14Asphaltic flumes (465.0315)SY49$72.00$50.00$72.00
15Apron endwalls for culvert pipe 18- inch (520.1018)EACH12$240.00$195.00$226.00
16Apron endwalls for culvert pipe 24- inch (520.1024)EACH4$320.00$260.00$323.00
17Apron endwalls for pipe arch steel 17X13-inch (521.1217)EACH4$226.00$165.00$210.00
18Culvert pipe corrugated steel 18- inch (521.3118)LF360$56.00$51.55$66.00
19Culvert pipe corrugated steel 24- inch (521.3124)LF120$67.00$66.40$75.00
20Pipe arch corrugated steel 17X13- inch (521.3717)LF45$53.00$79.80$75.00
21Culvert pipe reinforced concrete class IV 18-inch (522.0418)LF46$94.00$107.00$92.00
22Culvert pipe reinforced concrete class IV 24-inch (522.0424)LF96$123.00$132.00$115.00
23Apron endwalls for culvert pipe reinforced concrete 18-inch (522.1018)EACH2$1,386.00$2,215.00$1,415.00
24Apron endwalls for culvert pipe reinforced concrete 24-inch (522.1024)EACH4$1,543.00$2,400.00$1,628.00
25Culvert pipe reinforced concrete horizontal elliptical class HE-III 14X23-inch (522.2314)LF90$138.00$150.90$143.00
26Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 14X23-inch (522.2614)EACH2$1,425.00$2,250.00$1,462.00
27Concrete curb & gutter 30-inch type D (601.0411)LF114$34.20$33.00$33.00
28Concrete curb & gutter 6-inch sloped 36-inch type D (601.0557)LF321$32.70$33.00$33.00
29Riprap medium (606.0200)CY10$150.00$113.60$188.00
30Mobilization (619.1000)EACH1$56,000$39,180$161,376
31Water (624.0100)MGAL323$0.01$1.00$47.00
32Topsoil (625.0100)SY20,610$1.90$1.73$3.45
33Mulching (627.0200)SY14,500$0.36$0.36$0.35
34Silt fence (628.1504)LF900$2.39$2.39$2.25
35Silt fence maintenance (628.1520)LF900$0.01$0.01$0.01
36Mobilizations erosion control (628.1905)EACH5$0.01$0.01$150.00
37Mobilizations emergency erosion control (628.1910)EACH5$0.01$0.01$25.00
38Erosion mat class I type B (628.2004)SY6,120$1.68$1.68$1.40
39Temporary ditch checks (628.7504)LF48$8.67$8.67$10.00
40Culvert pipe checks (628.7555)EACH33$22.15$22.15$18.00
41Fertilizer type B (629.0210)CWT24$126.82$126.82$95.00
42Seeding mixture no. 30 (630.0130)LB868$7.98$7.98$7.80
43Seeding mixture no. 40 (630.0140)LB65$7.66$7.66$9.50
44Seeding temporary (630.0200)LB560$2.75$2.75$3.75
45Seed water (630.0500)MGAL572$0.01$0.01$8.00
46Markers culvert end (633.5200)EACH8$63.45$63.45$68.00
47Posts wood 4X6-inch X 16-FT (634.0616)EACH15$172.80$172.80$84.00
48Signs type II reflective H (637.2210)SF67.51$22.00$22.00$22.00
49Signs type II reflective F (637.2230)SF35$24.20$24.20$22.75
50Moving signs type II (638.2102)EACH2$93.75$93.75$75.00
51Removing signs type II (638.2602)EACH16$31.25$31.25$37.50
52Removing small sign supports (638.3000)EACH15$34.38$34.38$37.50
53Field office type C (642.5201)EACH1$8,500.00$8,650.00$16,000
54Traffic control drums (643.0300)DAY1,800$0.19$0.19$0.19
55Traffic control barricades type III (643.0420)DAY1,440$0.58$0.58$0.58
56Traffic control warning lights type A (643.0705)DAY1,728$0.15$0.15$0.15
57Traffic control signs (643.0900)DAY2,016$0.18$0.18$0.18
58Traffic control signs PCMS (643.1050)DAY14$55.00$55.00$55.00
59Traffic control (643.5000)EACH1$4,895.00$4,895.00$4,895.00
60Geotextile type HR (645.0120)SY64$6.00$3.00$6.50
61Marking line epoxy 6-inch (646.2020)LF9,295$0.87$0.87$0.87
62Marking stop line epoxy 18-inch (646.6120)LF126$18.00$18.00$18.00
63Cold weather marking epoxy 6-inch (646.6466)LF9,295$0.29$0.29$0.29
64Construction staking subgrade (650.4500)LF4,682$0.01$0.01$0.01
65Construction staking base (650.5000)LF4,682$0.58$0.58$0.58
66Construction staking curb gutter and curb & gutter (650.5500)LF435$0.75$0.75$0.75
67Construction staking pipe culverts (650.6000)EACH4$100.00$100.00$100.00
68Construction staking supplemental control (project) 01. 4307-02-71 (650.9911)EACH1$10.00$10.00$10.00
69Construction staking slope stakes (650.9920)LF4,682$0.83$0.83$0.83
70Sawing asphalt (690.0150)LF88$3.00$2.95$2.95
71Incentive iri ride (740.0440)DOL3,180$1.00$1.00$1.00
72On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS300$5.00$5.00$5.00
73On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS600$5.00$5.00$5.00
74Special 01. reestablish section corner monuments (SPV.0060)EACH2$800.00$800.00$800.00
WisDOT contract 20250311025: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of March 11, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy