WisDOT contract 20250311035 bid tabulation
C WI Rapids, Wood Avenue; STH 13 Intersection Modification (LOC STR, Wood County C WI Rapids, Wood Avenue). Let by Wisconsin DOT on March 11, 2025, Wood. 4 bids received; low bid $170,984 by Chippewa Concrete Services, Inc..
- Owner
- Wisconsin DOT
- Letting
- 11 MAR 2025
- Pay items
- 70
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Chippewa Concrete Services, Inc. | $170,984 | Low |
| 2 | Janke General Contractors, Inc. | $188,954 | +11% |
| 3 | Pember Companies, Inc. | $200,015 | +17% |
| 4 | Sommers Construction Co., Inc. | $217,596 | +27% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Chippewa Concrete Services, Inc. | 2. Janke General Contractors, Inc. | 3. Pember Companies, Inc. | 4. Sommers Construction Co., Inc. |
|---|---|---|---|---|---|---|---|
| 1 | Removing concrete pavement (204.0100) | SY | 50 | $27.00 | $80.00 | $41.50 | $44.00 |
| 2 | Removing asphaltic surface (204.0110) | SY | 60 | $22.50 | $45.00 | $22.75 | $18.00 |
| 3 | Removing curb & gutter (204.0150) | LF | 110 | $12.27 | $25.00 | $16.00 | $12.40 |
| 4 | Removing concrete sidewalk (204.0155) | SY | 60 | $15.00 | $50.00 | $26.00 | $27.00 |
| 5 | Prepare foundation for asphaltic paving (project) 01. 6669-11-85 (211.0101) | EACH | 1 | $1,320.00 | $1,250.00 | $2,000.00 | $4,000.00 |
| 6 | Finishing roadway (project) 01. 6999-11-85 (213.0100) | EACH | 1 | $2,500.00 | $250.00 | $500.00 | $2,500.00 |
| 7 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 40 | $48.53 | $105.00 | $60.00 | $67.85 |
| 8 | Coloring concrete wisdot red (405.0100) | CY | 0.90 | $105.18 | $300.00 | $325.00 | $650.00 |
| 9 | Drilled tie bars (416.0610) | EACH | 35 | $16.03 | $17.00 | $7.00 | $15.00 |
| 10 | Asphaltic surface (465.0105) | TON | 20 | $290.00 | $290.00 | $325.00 | $290.00 |
| 11 | Asphaltic surface driveways and field entrances (465.0120) | TON | 3 | $290.00 | $290.00 | $325.00 | $290.00 |
| 12 | Concrete curb & gutter 30-inch type A (601.0409) | LF | 50 | $118.09 | $90.00 | $50.00 | $88.00 |
| 13 | Concrete curb & gutter 30-inch type D (601.0411) | LF | 36 | $123.36 | $95.00 | $50.00 | $88.00 |
| 14 | Concrete curb pedestrian (601.0600) | LF | 40 | $136.86 | $100.00 | $38.00 | $88.00 |
| 15 | Concrete sidewalk 4-inch (602.0405) | SF | 670 | $25.63 | $16.00 | $8.50 | $14.45 |
| 16 | Curb ramp detectable warning field natural patina (602.0515) | SF | 40 | $60.38 | $70.00 | $55.00 | $55.00 |
| 17 | Curb ramp detectable warning field radial natural patina (602.0615) | SF | 14.50 | $67.84 | $100.00 | $75.00 | $85.00 |
| 18 | Mobilization (619.1000) | EACH | 1 | $18,250 | $44,000 | $55,925 | $82,000 |
| 19 | Concrete median sloped nose (620.0300) | SF | 190 | $21.88 | $17.00 | $11.50 | $18.00 |
| 20 | Water (624.0100) | MGAL | 1.20 | $100.00 | $10.00 | $185.00 | $750.00 |
| 21 | Topsoil (625.0100) | SY | 4 | $142.32 | $175.00 | $100.00 | $65.00 |
| 22 | Mulching (627.0200) | SY | 4 | $50.00 | $105.00 | $79.00 | $10.00 |
| 23 | Mobilizations erosion control (628.1905) | EACH | 4 | $500.00 | $200.00 | $100.00 | $100.00 |
| 24 | Mobilizations emergency erosion control (628.1910) | EACH | 2 | $1.00 | $50.00 | $100.00 | $50.00 |
| 25 | Inlet protection type B (628.7010) | EACH | 1 | $100.00 | $70.00 | $130.00 | $70.00 |
| 26 | Inlet protection type C (628.7015) | EACH | 6 | $150.00 | $70.00 | $130.00 | $70.00 |
| 27 | Fertilizer type B (629.0210) | CWT | 0.10 | $1,000.00 | $500.00 | $600.00 | $200.00 |
| 28 | Seeding mixture no. 40 (630.0140) | LB | 0.10 | $50.00 | $500.00 | $1,210.00 | $75.00 |
| 29 | Seed water (630.0500) | MGAL | 0.10 | $1,000.00 | $100.00 | $925.00 | $45.50 |
| 30 | Signs type II reflective H (637.2210) | SF | 12.25 | $50.00 | $35.00 | $55.25 | $25.00 |
| 31 | Signs type II reflective F (637.2230) | SF | 43.50 | $50.00 | $32.00 | $46.25 | $27.00 |
| 32 | Field office type B (642.5001) | EACH | 1 | $5,000.00 | $1,000.00 | $6,500.00 | $9,500.00 |
| 33 | Traffic control drums (643.0300) | DAY | 2,661 | $0.50 | $0.50 | $0.60 | $0.50 |
| 34 | Traffic control barricades type III (643.0420) | DAY | 321 | $1.00 | $1.00 | $1.10 | $1.00 |
| 35 | Traffic control warning lights type A (643.0705) | DAY | 482 | $0.06 | $0.06 | $0.10 | $0.06 |
| 36 | Traffic control warning lights type C (643.0715) | DAY | 789 | $0.10 | $0.10 | $0.10 | $0.10 |
| 37 | Traffic control arrow boards (643.0800) | DAY | 81 | $10.00 | $10.00 | $11.10 | $10.00 |
| 38 | Traffic control signs (643.0900) | DAY | 2,486 | $1.50 | $1.50 | $1.70 | $1.50 |
| 39 | Traffic control signs PCMS (643.1050) | DAY | 20 | $25.00 | $25.00 | $28.00 | $25.00 |
| 40 | Traffic control cones 42-inch (643.1070) | DAY | 1,037 | $0.50 | $0.50 | $0.55 | $0.50 |
| 41 | Temporary marking line removable tape 6-inch (643.3180) | LF | 990 | $1.65 | $1.65 | $1.85 | $1.65 |
| 42 | Temporary marking removable mask out tape 6-inch (643.3960) | LF | 460 | $2.25 | $2.25 | $2.50 | $2.25 |
| 43 | Traffic control (643.5000) | EACH | 1 | $2,700.00 | $2,700.00 | $9,500.00 | $2,700.00 |
| 44 | Temporary pedestrian barricade (644.1810) | LF | 72 | $7.00 | $7.00 | $7.80 | $7.00 |
| 45 | Marking crosswalk epoxy transverse line 6-inch (646.7420) | LF | 200 | $20.00 | $18.50 | $20.60 | $18.50 |
| 46 | Marking curb epoxy (646.8120) | LF | 20 | $10.20 | $23.80 | $26.50 | $23.80 |
| 47 | Marking island nose epoxy (646.8220) | EACH | 2 | $400.00 | $350.00 | $390.00 | $350.00 |
| 48 | Marking removal line water blasting 6-inch (646.9012) | LF | 190 | $8.00 | $5.00 | $8.00 | $4.39 |
| 49 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 166 | $3.50 | $3.50 | $3.90 | $3.50 |
| 50 | Construction staking electrical installations (project) 01. 6999-11- 85 (650.8501) | EACH | 1 | $1,200.00 | $1,200.00 | $1,300.00 | $1,200.00 |
| 51 | Construction staking curb ramps (650.9000) | EACH | 5 | $400.00 | $400.00 | $450.00 | $400.00 |
| 52 | Construction staking sidewalk (project) 01. 6999-11-85 (650.9500) | EACH | 1 | $800.00 | $800.00 | $900.00 | $800.00 |
| 53 | Construction staking supplemental control (project) 01. 6999-11-85 (650.9911) | EACH | 1 | $1,000.00 | $1,000.00 | $1,100.00 | $1,000.00 |
| 54 | Conduit special 2-inch (652.0605) | LF | 40 | $150.00 | $150.00 | $165.00 | $44.00 |
| 55 | Concrete bases type 1 (654.0101) | EACH | 1 | $1,375.00 | $1,375.00 | $1,515.00 | $1,775.00 |
| 56 | Concrete bases type 2 (654.0102) | EACH | 2 | $2,010.00 | $2,010.00 | $2,215.00 | $1,975.00 |
| 57 | Pedestal bases (657.0100) | EACH | 1 | $558.00 | $558.00 | $615.00 | $450.00 |
| 58 | Transformer bases breakaway 11 1/2-inch bolt circle (657.0255) | EACH | 2 | $847.00 | $847.00 | $932.00 | $800.00 |
| 59 | Poles type 2 (657.0305) | EACH | 2 | $3,122.00 | $3,122.00 | $3,435.00 | $2,580.00 |
| 60 | Traffic signal standards aluminum 3.5-FT (657.0405) | EACH | 1 | $653.00 | $653.00 | $720.00 | $460.00 |
| 61 | Trombone arms 20-FT (657.0590) | EACH | 2 | $2,390.00 | $2,390.00 | $2,630.00 | $2,250.00 |
| 62 | Pedestrian push buttons (658.0500) | EACH | 3 | $1,050.00 | $1,050.00 | $1,160.00 | $975.00 |
| 63 | Sawing asphalt (690.0150) | LF | 40 | $1.75 | $1.75 | $3.20 | $2.00 |
| 64 | Sawing concrete (690.0250) | LF | 230 | $2.75 | $2.75 | $3.65 | $4.00 |
| 65 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 150 | $5.00 | $5.00 | $5.00 | $5.00 |
| 66 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 300 | $5.00 | $5.00 | $5.00 | $5.00 |
| 67 | Special 01. rectangular rapid flashing beacon (RRFB) system - sta. 71+82 LT (SPV.0060) | EACH | 1 | $9,473.00 | $9,473.00 | $12,000 | $8,500.00 |
| 68 | Special 02. rectangular rapid flashing beacon (RRFB) system - sta. 71+82 RT (SPV.0060) | EACH | 1 | $9,473.00 | $9,473.00 | $12,000 | $8,500.00 |
| 69 | Special 01. concrete curb & gutter 24-inch type A special (SPV.0090) | LF | 40 | $143.98 | $188.00 | $47.50 | $88.00 |
| 70 | Special 02. posts round tubular steel 2 3/8-inch (SPV.0090) | LF | 10.50 | $80.00 | $115.00 | $50.00 | $65.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of March 11, 2025. Compiled by Mirage Metrics.