WisDOT contract 20250311037 bid tabulation

9876-00-70. Let by Wisconsin DOT on March 11, 2025, Oneida. 3 bids received; low bid $2,911,218 by American Asphalt of Wisconsin.

Owner
Wisconsin DOT
Letting
11 MAR 2025
Pay items
95
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1American Asphalt of Wisconsin$2,911,218Low
2Northeast Asphalt, Inc$3,093,966+6.0%
3Pitlik & Wick, Inc.$3,123,830+7.0%
WisDOT contract 20250311037: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. American Asphalt of Wisconsin2. Northeast Asphalt, Inc3. Pitlik & Wick, Inc.
1Clearing (201.0105)STA14$100.00$1.00$1.00
2Grubbing (201.0205)STA14$500.00$1.00$1.00
3Grubbing (201.0220)ID24$22.00$31.62$31.62
4Abatement of asbestos containing material (structure) 01. B-43-0672 (203.0211.S)EACH1$7,100.00$7,100.00$7,330.00
5Removing structure over waterway remove debris (structure) 01. B-43- 0672 (203.0250)EACH1$92,400$92,400$60,000
6Removing asphaltic surface (204.0110)SY1,399$9.50$10.23$10.23
7Removing asphaltic surface butt joints (204.0115)SY6,490$4.48$1.25$2.45
8Removing asphaltic surface milling (204.0120)SY107,100$0.78$1.00$1.45
9Removing guardrail (204.0165)LF374$5.00$5.00$5.00
10Removing cable barrier (204.0167)LF763$6.53$6.53$6.53
11Excavation common (205.0100)CY568$13.35$19.89$19.89
12Excavation for structures bridges (structure) 01. B-43-0068 (206.1001)EACH1$23,300$15,756$17,000
13Backfill structure type A (210.1500)TON560$18.05$16.63$19.52
14Finishing roadway (project) 01. 9876-00-70 (213.0100)EACH1$1,200.00$100.00$1,500.00
15Finishing roadway (project) 02. 9876-00-71 (213.0100)EACH1$1,200.00$100.00$4,500.00
16Base aggregate dense 3/4-inch (305.0110)TON7,100$20.05$21.89$21.57
17Base aggregate dense 1 1/4-inch (305.0120)TON3,096$14.75$20.31$20.67
18Shaping shoulders (305.0500)STA660$5.76$21.90$22.75
19Tack coat (455.0605)GAL13,704$3.65$2.80$3.25
20HMA percent within limits (PWL) test strip volumetrics (460.0105.S)EACH1$3,500.00$2,950.00$9,500.00
21HMA percent within limits (PWL) test strip density (460.0110.S)EACH1$3,500.00$4,250.00$9,500.00
22Incentive density PWL HMA pavement (460.2005)DOL16,970$1.00$1.00$1.00
23Incentive density HMA pavement longitudinal joints (460.2007)DOL12,410$1.00$1.00$1.00
24Incentive air voids HMA pavement (460.2010)DOL16,970$1.00$1.00$1.00
25HMA pavement 4 MT 58-28 S (460.6224)TON22,199$71.04$69.80$70.90
26Asphaltic surface (465.0105)TON617$78.49$85.90$108.90
27Asphaltic surface driveways and field entrances (465.0120)TON223$168.02$165.00$165.00
28Concrete masonry bridges (502.0100)CY289$760.00$760.00$640.00
29Protective surface treatment (502.3200)SY234$4.70$4.70$3.75
30Pigmented surface sealer (502.3210)SY52$11.00$11.00$20.00
31Bar steel reinforcement HS structures (505.0400)LB6,130$1.12$1.12$1.30
32Bar steel reinforcement HS coated structures (505.0600)LB41,410$1.12$1.12$1.35
33Rubberized membrane waterproofing (516.0500)SY18$60.00$60.00$68.00
34Piling steel HP 10-inch X 42 LB (550.1100)LF1,080$15.00$15.00$34.00
35Concrete curb & gutter 4-inch sloped 36-inch type TBT (601.0588)LF118$70.48$69.78$69.78
36Concrete surface drains (602.3010)CY2.20$1,416.45$1,402.43$1,402.43
37Riprap medium (606.0200)CY6$150.00$214.26$214.26
38Riprap heavy (606.0300)CY90$105.00$133.20$133.20
39Pipe underdrain wrapped 6-inch (612.0406)LF170$8.00$4.90$4.90
40Barrier system grading shaping finishing (614.0010)EACH2$29,869$15,200$13,200
41Anchor assemblies for steel plate beam guard (614.0150)EACH4$310.00$310.00$250.00
42MGS guardrail 3 (614.2300)LF728$25.00$25.00$25.00
43MGS guardrail short radius (614.2350)LF23.50$25.00$25.00$25.00
44MGS thrie beam transition (614.2500)LF157.60$86.00$86.00$86.00
45MGS guardrail terminal eat (614.2610)EACH7$3,233.00$3,233.00$3,233.00
46MGS guardrail short radius terminal (614.2630)EACH1$2,033.00$2,033.00$2,033.00
47Maintenance and repair of haul roads (project) 01. 9876-00-70 (618.0100)EACH1$0.01$1.00$1.00
48Maintenance and repair of haul roads (project) 02. 9876-00-71 (618.0100)EACH1$0.01$1.00$1.00
49Mobilization (619.1000)EACH1$45,450$246,000$205,602
50Water (624.0100)MGAL104.20$0.01$1.00$1.00
51Salvaged topsoil (625.0500)SY670$4.25$4.07$4.07
52Mulching (627.0200)SY670$0.75$0.75$0.75
53Silt fence (628.1504)LF7,695$1.60$1.60$1.60
54Silt fence maintenance (628.1520)LF13,668$0.03$0.03$0.03
55Mobilizations erosion control (628.1905)EACH8$173.00$173.00$173.00
56Mobilizations emergency erosion control (628.1910)EACH5$293.00$293.00$293.00
57Turbidity barriers (628.6005)SY155$43.00$43.00$43.00
58Fertilizer type B (629.0210)CWT1.40$100.00$100.00$100.00
59Seeding mixture no. 30 (630.0130)LB35$12.00$12.00$12.00
60Seeding temporary (630.0200)LB50$6.00$6.00$6.00
61Seed water (630.0500)MGAL37.50$5.00$5.00$5.00
62Posts wood 4X6-inch X 12-FT (634.0612)EACH4$95.00$95.00$95.00
63Posts wood 4X6-inch X 16-FT (634.0616)EACH2$100.00$100.00$100.00
64Signs type II reflective F (637.2230)SF24.50$50.00$50.00$50.00
65Moving signs type II (638.2102)EACH7$125.00$125.00$125.00
66Removing signs type II (638.2602)EACH10$30.00$30.00$30.00
67Removing small sign supports (638.3000)EACH8$30.00$30.00$30.00
68Moving small sign supports (638.4000)EACH3$125.00$125.00$125.00
69Field office type B (642.5001)EACH1$10,000$10,950$10,000
70Traffic control barricades type III (643.0420)DAY8,350$0.50$0.50$0.50
71Traffic control warning lights type A (643.0705)DAY15,880$0.05$0.05$0.05
72Traffic control signs (643.0900)DAY21,094$0.40$0.40$0.40
73Traffic control covering signs type II (643.0920)EACH2$25.25$25.00$25.00
74Traffic control signs PCMS (643.1050)DAY28$35.35$35.00$35.00
75Temporary marking line paint 4- inch (643.3105)LF55,304$0.20$0.38$0.20
76Traffic control (643.5000)EACH1$2,659.33$2,633.00$2,633.00
77Geotextile type DF schedule A (645.0111)SY90$4.00$10.40$10.40
78Geotextile type HR (645.0120)SY192$4.00$10.48$10.48
79Marking line epoxy 4-inch (646.1020)LF121,979$0.43$0.42$0.42
80Locating no-passing zones (648.0100)MI6.14$662.65$650.00$650.00
81Construction staking subgrade (650.4500)LF433$0.01$1.00$0.01
82Construction staking base (650.5000)LF433$1.60$1.60$0.01
83Construction staking curb gutter and curb & gutter (650.5500)LF118$2.00$2.00$2.00
84Construction staking structure layout (structure) 01. B-43-0068 (650.6501)EACH1$2,500.00$2,500.00$3,000.00
85Construction staking resurfacing reference (650.8000)LF32,391$0.15$0.15$0.07
86Construction staking supplemental control (project) 01. 9876-00-70 (650.9911)EACH1$1,573.77$1,573.77$2,750.00
87Construction staking supplemental control (project) 02. 9876-00-71 (650.9911)EACH1$1,573.78$1,573.78$2,750.00
88Construction staking slope stakes (650.9920)LF433$3.00$3.00$2.75
89Sawing asphalt (690.0150)LF699$2.00$2.00$3.00
90Incentive strength concrete structures (715.0502)DOL1,734$1.00$1.00$1.00
91Incentive iri ride (740.0440)DOL12,280$1.00$1.00$1.00
92On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS4,000$5.00$5.00$5.00
93On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS2,520$5.00$5.00$5.00
94Special 01. verify landmark reference monuments (SPV.0060)EACH3$375.00$375.00$500.00
95Special 01. base aggregate dense 3/4-inch beam guard (SPV.0195)TON110$20.05$46.78$46.63
WisDOT contract 20250311037: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of March 11, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy