WisDOT contract 20250311037 bid tabulation
9876-00-70. Let by Wisconsin DOT on March 11, 2025, Oneida. 3 bids received; low bid $2,911,218 by American Asphalt of Wisconsin.
- Owner
- Wisconsin DOT
- Letting
- 11 MAR 2025
- Pay items
- 95
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | American Asphalt of Wisconsin | $2,911,218 | Low |
| 2 | Northeast Asphalt, Inc | $3,093,966 | +6.0% |
| 3 | Pitlik & Wick, Inc. | $3,123,830 | +7.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. American Asphalt of Wisconsin | 2. Northeast Asphalt, Inc | 3. Pitlik & Wick, Inc. |
|---|---|---|---|---|---|---|
| 1 | Clearing (201.0105) | STA | 14 | $100.00 | $1.00 | $1.00 |
| 2 | Grubbing (201.0205) | STA | 14 | $500.00 | $1.00 | $1.00 |
| 3 | Grubbing (201.0220) | ID | 24 | $22.00 | $31.62 | $31.62 |
| 4 | Abatement of asbestos containing material (structure) 01. B-43-0672 (203.0211.S) | EACH | 1 | $7,100.00 | $7,100.00 | $7,330.00 |
| 5 | Removing structure over waterway remove debris (structure) 01. B-43- 0672 (203.0250) | EACH | 1 | $92,400 | $92,400 | $60,000 |
| 6 | Removing asphaltic surface (204.0110) | SY | 1,399 | $9.50 | $10.23 | $10.23 |
| 7 | Removing asphaltic surface butt joints (204.0115) | SY | 6,490 | $4.48 | $1.25 | $2.45 |
| 8 | Removing asphaltic surface milling (204.0120) | SY | 107,100 | $0.78 | $1.00 | $1.45 |
| 9 | Removing guardrail (204.0165) | LF | 374 | $5.00 | $5.00 | $5.00 |
| 10 | Removing cable barrier (204.0167) | LF | 763 | $6.53 | $6.53 | $6.53 |
| 11 | Excavation common (205.0100) | CY | 568 | $13.35 | $19.89 | $19.89 |
| 12 | Excavation for structures bridges (structure) 01. B-43-0068 (206.1001) | EACH | 1 | $23,300 | $15,756 | $17,000 |
| 13 | Backfill structure type A (210.1500) | TON | 560 | $18.05 | $16.63 | $19.52 |
| 14 | Finishing roadway (project) 01. 9876-00-70 (213.0100) | EACH | 1 | $1,200.00 | $100.00 | $1,500.00 |
| 15 | Finishing roadway (project) 02. 9876-00-71 (213.0100) | EACH | 1 | $1,200.00 | $100.00 | $4,500.00 |
| 16 | Base aggregate dense 3/4-inch (305.0110) | TON | 7,100 | $20.05 | $21.89 | $21.57 |
| 17 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 3,096 | $14.75 | $20.31 | $20.67 |
| 18 | Shaping shoulders (305.0500) | STA | 660 | $5.76 | $21.90 | $22.75 |
| 19 | Tack coat (455.0605) | GAL | 13,704 | $3.65 | $2.80 | $3.25 |
| 20 | HMA percent within limits (PWL) test strip volumetrics (460.0105.S) | EACH | 1 | $3,500.00 | $2,950.00 | $9,500.00 |
| 21 | HMA percent within limits (PWL) test strip density (460.0110.S) | EACH | 1 | $3,500.00 | $4,250.00 | $9,500.00 |
| 22 | Incentive density PWL HMA pavement (460.2005) | DOL | 16,970 | $1.00 | $1.00 | $1.00 |
| 23 | Incentive density HMA pavement longitudinal joints (460.2007) | DOL | 12,410 | $1.00 | $1.00 | $1.00 |
| 24 | Incentive air voids HMA pavement (460.2010) | DOL | 16,970 | $1.00 | $1.00 | $1.00 |
| 25 | HMA pavement 4 MT 58-28 S (460.6224) | TON | 22,199 | $71.04 | $69.80 | $70.90 |
| 26 | Asphaltic surface (465.0105) | TON | 617 | $78.49 | $85.90 | $108.90 |
| 27 | Asphaltic surface driveways and field entrances (465.0120) | TON | 223 | $168.02 | $165.00 | $165.00 |
| 28 | Concrete masonry bridges (502.0100) | CY | 289 | $760.00 | $760.00 | $640.00 |
| 29 | Protective surface treatment (502.3200) | SY | 234 | $4.70 | $4.70 | $3.75 |
| 30 | Pigmented surface sealer (502.3210) | SY | 52 | $11.00 | $11.00 | $20.00 |
| 31 | Bar steel reinforcement HS structures (505.0400) | LB | 6,130 | $1.12 | $1.12 | $1.30 |
| 32 | Bar steel reinforcement HS coated structures (505.0600) | LB | 41,410 | $1.12 | $1.12 | $1.35 |
| 33 | Rubberized membrane waterproofing (516.0500) | SY | 18 | $60.00 | $60.00 | $68.00 |
| 34 | Piling steel HP 10-inch X 42 LB (550.1100) | LF | 1,080 | $15.00 | $15.00 | $34.00 |
| 35 | Concrete curb & gutter 4-inch sloped 36-inch type TBT (601.0588) | LF | 118 | $70.48 | $69.78 | $69.78 |
| 36 | Concrete surface drains (602.3010) | CY | 2.20 | $1,416.45 | $1,402.43 | $1,402.43 |
| 37 | Riprap medium (606.0200) | CY | 6 | $150.00 | $214.26 | $214.26 |
| 38 | Riprap heavy (606.0300) | CY | 90 | $105.00 | $133.20 | $133.20 |
| 39 | Pipe underdrain wrapped 6-inch (612.0406) | LF | 170 | $8.00 | $4.90 | $4.90 |
| 40 | Barrier system grading shaping finishing (614.0010) | EACH | 2 | $29,869 | $15,200 | $13,200 |
| 41 | Anchor assemblies for steel plate beam guard (614.0150) | EACH | 4 | $310.00 | $310.00 | $250.00 |
| 42 | MGS guardrail 3 (614.2300) | LF | 728 | $25.00 | $25.00 | $25.00 |
| 43 | MGS guardrail short radius (614.2350) | LF | 23.50 | $25.00 | $25.00 | $25.00 |
| 44 | MGS thrie beam transition (614.2500) | LF | 157.60 | $86.00 | $86.00 | $86.00 |
| 45 | MGS guardrail terminal eat (614.2610) | EACH | 7 | $3,233.00 | $3,233.00 | $3,233.00 |
| 46 | MGS guardrail short radius terminal (614.2630) | EACH | 1 | $2,033.00 | $2,033.00 | $2,033.00 |
| 47 | Maintenance and repair of haul roads (project) 01. 9876-00-70 (618.0100) | EACH | 1 | $0.01 | $1.00 | $1.00 |
| 48 | Maintenance and repair of haul roads (project) 02. 9876-00-71 (618.0100) | EACH | 1 | $0.01 | $1.00 | $1.00 |
| 49 | Mobilization (619.1000) | EACH | 1 | $45,450 | $246,000 | $205,602 |
| 50 | Water (624.0100) | MGAL | 104.20 | $0.01 | $1.00 | $1.00 |
| 51 | Salvaged topsoil (625.0500) | SY | 670 | $4.25 | $4.07 | $4.07 |
| 52 | Mulching (627.0200) | SY | 670 | $0.75 | $0.75 | $0.75 |
| 53 | Silt fence (628.1504) | LF | 7,695 | $1.60 | $1.60 | $1.60 |
| 54 | Silt fence maintenance (628.1520) | LF | 13,668 | $0.03 | $0.03 | $0.03 |
| 55 | Mobilizations erosion control (628.1905) | EACH | 8 | $173.00 | $173.00 | $173.00 |
| 56 | Mobilizations emergency erosion control (628.1910) | EACH | 5 | $293.00 | $293.00 | $293.00 |
| 57 | Turbidity barriers (628.6005) | SY | 155 | $43.00 | $43.00 | $43.00 |
| 58 | Fertilizer type B (629.0210) | CWT | 1.40 | $100.00 | $100.00 | $100.00 |
| 59 | Seeding mixture no. 30 (630.0130) | LB | 35 | $12.00 | $12.00 | $12.00 |
| 60 | Seeding temporary (630.0200) | LB | 50 | $6.00 | $6.00 | $6.00 |
| 61 | Seed water (630.0500) | MGAL | 37.50 | $5.00 | $5.00 | $5.00 |
| 62 | Posts wood 4X6-inch X 12-FT (634.0612) | EACH | 4 | $95.00 | $95.00 | $95.00 |
| 63 | Posts wood 4X6-inch X 16-FT (634.0616) | EACH | 2 | $100.00 | $100.00 | $100.00 |
| 64 | Signs type II reflective F (637.2230) | SF | 24.50 | $50.00 | $50.00 | $50.00 |
| 65 | Moving signs type II (638.2102) | EACH | 7 | $125.00 | $125.00 | $125.00 |
| 66 | Removing signs type II (638.2602) | EACH | 10 | $30.00 | $30.00 | $30.00 |
| 67 | Removing small sign supports (638.3000) | EACH | 8 | $30.00 | $30.00 | $30.00 |
| 68 | Moving small sign supports (638.4000) | EACH | 3 | $125.00 | $125.00 | $125.00 |
| 69 | Field office type B (642.5001) | EACH | 1 | $10,000 | $10,950 | $10,000 |
| 70 | Traffic control barricades type III (643.0420) | DAY | 8,350 | $0.50 | $0.50 | $0.50 |
| 71 | Traffic control warning lights type A (643.0705) | DAY | 15,880 | $0.05 | $0.05 | $0.05 |
| 72 | Traffic control signs (643.0900) | DAY | 21,094 | $0.40 | $0.40 | $0.40 |
| 73 | Traffic control covering signs type II (643.0920) | EACH | 2 | $25.25 | $25.00 | $25.00 |
| 74 | Traffic control signs PCMS (643.1050) | DAY | 28 | $35.35 | $35.00 | $35.00 |
| 75 | Temporary marking line paint 4- inch (643.3105) | LF | 55,304 | $0.20 | $0.38 | $0.20 |
| 76 | Traffic control (643.5000) | EACH | 1 | $2,659.33 | $2,633.00 | $2,633.00 |
| 77 | Geotextile type DF schedule A (645.0111) | SY | 90 | $4.00 | $10.40 | $10.40 |
| 78 | Geotextile type HR (645.0120) | SY | 192 | $4.00 | $10.48 | $10.48 |
| 79 | Marking line epoxy 4-inch (646.1020) | LF | 121,979 | $0.43 | $0.42 | $0.42 |
| 80 | Locating no-passing zones (648.0100) | MI | 6.14 | $662.65 | $650.00 | $650.00 |
| 81 | Construction staking subgrade (650.4500) | LF | 433 | $0.01 | $1.00 | $0.01 |
| 82 | Construction staking base (650.5000) | LF | 433 | $1.60 | $1.60 | $0.01 |
| 83 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 118 | $2.00 | $2.00 | $2.00 |
| 84 | Construction staking structure layout (structure) 01. B-43-0068 (650.6501) | EACH | 1 | $2,500.00 | $2,500.00 | $3,000.00 |
| 85 | Construction staking resurfacing reference (650.8000) | LF | 32,391 | $0.15 | $0.15 | $0.07 |
| 86 | Construction staking supplemental control (project) 01. 9876-00-70 (650.9911) | EACH | 1 | $1,573.77 | $1,573.77 | $2,750.00 |
| 87 | Construction staking supplemental control (project) 02. 9876-00-71 (650.9911) | EACH | 1 | $1,573.78 | $1,573.78 | $2,750.00 |
| 88 | Construction staking slope stakes (650.9920) | LF | 433 | $3.00 | $3.00 | $2.75 |
| 89 | Sawing asphalt (690.0150) | LF | 699 | $2.00 | $2.00 | $3.00 |
| 90 | Incentive strength concrete structures (715.0502) | DOL | 1,734 | $1.00 | $1.00 | $1.00 |
| 91 | Incentive iri ride (740.0440) | DOL | 12,280 | $1.00 | $1.00 | $1.00 |
| 92 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 4,000 | $5.00 | $5.00 | $5.00 |
| 93 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 2,520 | $5.00 | $5.00 | $5.00 |
| 94 | Special 01. verify landmark reference monuments (SPV.0060) | EACH | 3 | $375.00 | $375.00 | $500.00 |
| 95 | Special 01. base aggregate dense 3/4-inch beam guard (SPV.0195) | TON | 110 | $20.05 | $46.78 | $46.63 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of March 11, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.