WisDOT contract 20250513012 bid tabulation

C Waukesha, Les Paul Parkway; Intersection With Woodmans Entrance (USH 018, Waukesha County C Waukesha, Les Paul Parkway). Let by Wisconsin DOT on May 13, 2025, Waukesha. 6 bids received; low bid $385,185 by Wandel Contractors Inc.

Owner
Wisconsin DOT
Letting
13 MAY 2025
Pay items
82
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Wandel Contractors Inc$385,185Low
2Zignego Company, Inc.$421,258+9.0%
3Musson Bros., Inc.$439,602+14%
4Lalonde Contractors Incorporated$447,083+16%
5Zenith Tech., Inc. - Waukesha$486,475+26%
6Michels Road & Stone, Inc.$503,890+31%
WisDOT contract 20250513012: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Wandel Contractors Inc2. Zignego Company, Inc.3. Musson Bros., Inc.4. Lalonde Contractors Incorporated5. Zenith Tech., Inc. - Waukesha6. Michels Road & Stone, Inc.
1Removing concrete pavement (204.0100)SY811$11.23$11.00$13.00$10.97$31.46$4.00
2Removing curb & gutter (204.0150)LF320$7.00$10.00$30.00$7.96$13.94$11.00
3Removing concrete bases (204.0195)EACH3$400.00$300.00$268.26$328.58$328.58$328.58
4Removing (item description) 01. inlet covers (204.9060.S)EACH2$250.00$500.00$230.00$500.00$1.00$1.00
5Excavation common (205.0100)CY1,016$25.59$25.00$48.50$26.88$64.29$26.00
6Finishing roadway (project) 01. 2450-05-71 (213.0100)EACH1$1,500.00$1,000.00$500.00$2,404.00$2,010.24$2,500.00
7Base aggregate dense 1 1/4-inch (305.0120)TON910$12.00$0.01$0.15$26.21$36.62$24.00
8Base aggregate open-graded (310.0110)TON395$28.00$0.01$38.00$33.55$35.45$31.00
9Concrete pavement 9-inch (415.0090)SY886$68.73$79.00$63.00$80.11$72.82$83.00
10Concrete pavement joint filling (415.4100)SY1,225$3.00$1.50$2.00$2.29$3.11$5.00
11Drilled tie bars (416.0610)EACH395$8.00$20.00$10.00$13.71$9.33$12.00
12Concrete curb & gutter 30-inch type A (601.0409)LF911$25.18$25.00$25.00$40.51$29.74$53.00
13Concrete sidewalk 5-inch (602.0410)SF642$10.00$8.00$8.00$12.81$8.65$14.00
14Storm sewer pipe reinforced concrete class IV 12-inch (608.0412)LF20$133.00$170.00$207.00$170.00$171.00$171.00
15Storm sewer pipe reinforced concrete class IV 15-inch (608.0415)LF245$121.00$80.00$94.50$80.00$88.00$88.00
16Reconstructing manholes (611.0420)EACH1$3,252.00$2,000.00$931.00$2,000.00$1,325.00$1,325.00
17Reconstructing inlets (611.0430)EACH2$3,252.00$2,000.00$650.00$2,000.00$1,325.00$1,325.00
18Inlet covers type H (611.0624)EACH4$995.00$1,200.00$2,210.00$1,200.00$1,246.00$1,246.00
19Inlets 4-FT diameter (611.3004)EACH3$4,664.00$4,500.00$2,130.00$4,500.00$2,568.00$2,568.00
20Inlets 2X3-FT (611.3230)EACH1$3,498.00$4,000.00$1,830.00$4,000.00$2,071.00$2,071.00
21Pipe underdrain 6-inch (612.0106)LF1,015$20.00$25.00$12.00$25.00$37.00$37.00
22Mobilization (619.1000)EACH1$16,500$79,200$84,604$48,442$22,647$78,738
23Concrete median sloped nose (620.0300)SF162$26.00$15.00$15.00$18.61$22.64$17.00
24Water (624.0100)MGAL20$100.00$50.00$1.80$54.40$1.00$75.00
25Topsoil (625.0100)SY1,215$6.01$5.95$7.00$5.95$9.48$9.00
26Mobilizations erosion control (628.1905)EACH4$151.50$150.00$250.00$150.00$250.00$250.00
27Mobilizations emergency erosion control (628.1910)EACH4$151.50$150.00$300.00$150.00$300.00$300.00
28Erosion mat class I type A (628.2002)SY1,215$1.26$1.25$1.00$1.25$1.00$1.00
29Inlet protection type A (628.7005)EACH5$106.05$105.00$130.00$105.00$130.00$130.00
30Inlet protection type C (628.7015)EACH17$60.60$60.00$60.00$60.00$60.00$60.00
31Inlet protection type D (628.7020)EACH9$95.95$95.00$125.00$95.00$125.00$125.00
32Temporary ditch checks (628.7504)LF45$8.03$7.95$9.50$7.95$9.50$9.50
33Rock bags (628.7570)EACH20$12.12$12.00$20.00$12.00$20.00$20.00
34Fertilizer type B (629.0210)CWT1$95.95$95.00$200.00$95.00$200.00$200.00
35Seeding mixture no. 30 (630.0130)LB55$10.05$9.95$20.00$9.95$20.00$20.00
36Seeding temporary (630.0200)LB10$5.05$5.00$25.00$5.00$25.00$25.00
37Seed water (630.0500)MGAL1$50.50$50.00$300.00$50.00$300.00$300.00
38Posts wood 4X6-inch X 18-FT (634.0618)EACH15$126.25$125.00$125.00$125.00$125.00$125.00
39Signs type II reflective H (637.2210)SF163.50$22.22$22.00$19.95$22.00$19.95$19.95
40Signs type II reflective F (637.2230)SF10$24.24$24.00$26.00$24.00$26.00$26.00
41Moving signs type II (638.2102)EACH1$111.10$110.00$100.00$110.00$100.00$100.00
42Removing signs type II (638.2602)EACH7$30.30$30.00$50.00$30.00$50.00$50.00
43Removing small sign supports (638.3000)EACH7$30.30$30.00$50.00$30.00$50.00$50.00
44Field office type D (642.5401)EACH1$7,250.00$10,000$10,600$9,968.00$8,890.60$6,500.00
45Traffic control drums (643.0300)DAY5,400$0.15$0.15$0.25$0.25$0.15$0.15
46Traffic control barricades type III (643.0420)DAY1,170$0.45$0.45$0.50$0.50$0.45$0.45
47Traffic control warning lights type A (643.0705)DAY2,340$0.25$0.25$0.10$0.10$0.25$0.25
48Traffic control warning lights type C (643.0715)DAY1,020$0.10$0.10$0.10$0.10$0.10$0.10
49Traffic control signs (643.0900)DAY2,580$0.20$0.20$0.50$0.50$0.20$0.20
50Traffic control signs PCMS (643.1050)DAY14$35.00$35.00$98.00$98.00$35.00$35.00
51Temporary marking line removable tape 6-inch (643.3180)LF4,770$1.95$1.95$1.10$1.10$1.95$1.95
52Traffic control (643.5000)EACH1$7,825.00$7,825.00$2,500.00$2,500.00$7,825.00$7,825.00
53Geotextile type DF schedule A (645.0111)SY820$5.00$3.00$2.20$2.00$1.00$1.00
54Marking line grooved black epoxy 6-inch (646.2025)LF810$2.35$2.35$2.35$1.75$2.35$2.35
55Marking line grooved wet ref epoxy 6-inch (646.2040)LF4,940$1.48$1.48$1.48$1.90$1.48$1.48
56Marking line grooved wet ref epoxy 10-inch (646.4040)LF1,133$3.00$3.00$3.00$3.00$3.00$3.00
57Marking arrow epoxy (646.5020)EACH5$348.65$348.65$348.65$325.00$348.65$348.65
58Marking word epoxy (646.5120)EACH3$400.65$400.65$400.65$340.00$400.65$400.65
59Marking diagonal epoxy 12-inch (646.7120)LF242$14.25$14.25$14.25$14.00$14.25$14.25
60Marking curb epoxy (646.8120)LF168$7.00$7.00$7.00$7.00$7.00$7.00
61Marking island nose epoxy (646.8220)EACH3$280.00$280.00$280.00$325.00$280.00$280.00
62Marking removal line water blasting 4-inch (646.9010)LF1,520$0.30$0.30$0.99$0.60$0.30$0.30
63Marking removal line water blasting 8-inch (646.9110)LF227$0.75$0.75$0.99$0.95$0.75$0.75
64Marking removal line water blasting wide 12-inch (646.9210)LF173$7.00$7.00$1.00$2.60$7.00$7.00
65Marking removal special marking water blasting (646.9310)EACH2$220.00$220.00$50.00$150.00$220.00$220.00
66Construction staking storm sewer (650.4000)EACH7$105.00$105.00$105.00$105.00$105.00$125.00
67Construction staking subgrade (650.4500)LF850$1.00$1.00$1.00$1.00$1.00$1.75
68Construction staking concrete pavement (650.7000)LF850$3.00$3.00$3.00$3.00$3.00$1.75
69Construction staking electrical installations (project) 01. 2450-05- 71 (650.8501)EACH1$500.00$500.00$500.00$500.00$500.00$1,000.00
70Construction staking supplemental control (project) 01. 2450-05-71 (650.9911)EACH1$1,700.00$1,700.00$1,700.00$1,700.00$1,700.00$2,000.00
71Construction staking slope stakes (650.9920)LF850$1.00$1.00$1.00$1.00$1.00$1.85
72Conduit rigid nonmetallic schedule 40 2-inch (652.0225)LF755$9.60$7.90$7.90$7.90$7.90$7.90
73Concrete bases type 5 (654.0105)EACH3$1,573.77$1,193.04$1,193.04$1,193.04$1,193.04$1,193.04
74Electrical wire lighting 12 AWG (655.0610)LF150$1.74$1.08$1.08$1.08$1.08$1.08
75Electrical wire lighting 8 AWG (655.0620)LF3,020$2.48$1.72$1.72$1.72$1.72$1.72
76Sawing concrete (690.0250)LF990$2.00$2.50$7.00$2.15$2.15$2.50
77Incentive compressive strength concrete pavement (715.0720)DOL500$1.00$1.00$1.00$1.00$1.00$1.00
78On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS150$5.00$5.00$5.00$5.00$5.00$5.00
79On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS400$5.00$5.00$5.00$5.00$5.00$5.00
80Special 01. lighting units salvaged (SPV.0060)EACH3$892.71$1,538.16$1,538.16$1,538.16$1,538.16$1,538.16
81Special 02. inlet cover type special (SPV.0060)EACH2$2,890.00$2,800.00$2,640.00$2,800.00$3,105.00$3,105.00
82Special 03. utility line opening (ulo) (SPV.0060)EACH5$700.00$1.00$690.00$1,425.76$2,107.00$2,107.00
WisDOT contract 20250513012: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of May 13, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy