WisDOT contract 20250513029 bid tabulation

Shawano - Green Bay; Slope Stabilization B-58-0075 (STH 029, Shawano County Shawano - Green Bay). Let by Wisconsin DOT on May 13, 2025, Shawano. 3 bids received; low bid $1,691,679 by Relyco Plus, LLC.

Owner
Wisconsin DOT
Letting
13 MAY 2025
Pay items
108
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Relyco Plus, LLC$1,691,679Low
2James Peterson Sons, Inc.$1,732,170+2.0%
3Zignego Company, Inc.$1,892,587+12%
WisDOT contract 20250513029: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Relyco Plus, LLC2. James Peterson Sons, Inc.3. Zignego Company, Inc.
1Grubbing (201.0205)STA3$1,000.00$1,000.00$1,100.00
2Removing concrete pavement (204.0100)SY1,147$6.75$7.47$7.47
3Removing asphaltic surface (204.0110)SY525$4.00$5.00$5.00
4Removing inlets (204.0220)EACH1$385.00$500.00$500.00
5Removing storm sewer (size) 01. 18-inch (204.0245)LF377$15.00$35.00$35.00
6Excavation common (205.0100)CY5,615$18.73$15.44$15.44
7Backfill coarse aggregate (size) 01. no. 2 (209.0300.S)CY740$58.15$25.28$25.28
8Backfill granular grade 1 (209.1100)CY890$64.94$38.39$38.39
9Finishing roadway (project) 01. 1058-25-62 (213.0100)EACH1$2,500.00$2,500.00$1,000.00
10Base aggregate dense 3/4-inch (305.0110)TON1,760$33.76$27.26$27.26
11Base aggregate dense 1 1/4-inch (305.0120)TON5,905$18.81$17.98$17.98
12Base aggregate open-graded (310.0110)TON320$40.00$44.24$30.00
13Concrete pavement 7-inch (415.0070)SY37$82.46$70.00$100.00
14Concrete pavement 10-inch (415.0100)SY1,005$65.99$72.65$91.00
15Concrete pavement approach slab (415.0410)SY105$205.00$240.00$250.00
16Drilled tie bars (416.0610)EACH30$10.00$8.00$100.00
17Drilled dowel bars (416.0620)EACH803$16.50$14.00$30.00
18Concrete pavement repair (416.1710)SY260$97.46$87.45$123.00
19Concrete pavement replacement (416.1720)SY2,120$67.46$87.45$123.00
20Continuous diamond grinding concrete pavement (420.1000)SY5,580$6.94$6.94$6.94
21Tack coat (455.0605)GAL410$3.90$3.90$3.90
22Asphaltic surface (465.0105)TON120$156.00$156.00$156.00
23Asphaltic surface temporary (465.0125)TON1,470$92.40$92.40$92.40
24Asphaltic flumes (465.0315)SY5$146.00$146.00$146.00
25Temporary shoring (location) 01. sta 199+50 RT (511.1300)SF660$0.01$24.00$24.00
26Culvert pipe temporary 21-inch (520.2021)LF10$116.25$85.00$85.00
27Slope paving crushed aggregate (604.0500)SY160$24.20$65.00$60.00
28Riprap heavy (606.0300)CY347$81.07$78.46$78.46
29Storm sewer pipe reinforced concrete class IV 18-inch (608.0418)LF377$90.25$90.72$90.72
30Inlet covers type MS (611.0642)EACH1$478.00$1,100.00$1,100.00
31Inlets median 1 grate (611.3901)EACH1$3,356.00$3,501.17$3,501.17
32Pipe underdrain 6-inch (612.0106)LF1,997$24.00$65.61$65.61
33Pipe underdrain unperforated 6- inch (612.0206)LF253$29.00$55.00$55.00
34Apron endwalls for underdrain reinforced concrete 6-inch (612.0806)EACH2$359.00$375.00$375.00
35MGS guardrail temporary (614.1000)LF112.50$22.00$22.00$25.00
36MGS guardrail temporary thrie beam transition (614.1100)LF78.80$75.00$75.00$85.00
37MGS guardrail temporary terminal eat (614.1200)EACH2$2,950.00$2,950.00$4,200.00
38Maintenance and repair of haul roads (project) 01. 1058-25-62 (618.0100)EACH1$0.01$1.00$1.00
39Mobilization (619.1000)EACH1$212,000$138,051$213,000
40Water (624.0100)MGAL79$20.00$45.00$50.00
41Topsoil (625.0100)SY17,300$1.94$1.50$1.50
42Silt fence (628.1504)LF3,500$2.50$2.50$2.05
43Silt fence maintenance (628.1520)LF3,500$0.02$0.02$0.01
44Mobilizations erosion control (628.1905)EACH5$301.00$301.00$350.00
45Mobilizations emergency erosion control (628.1910)EACH6$395.00$395.00$350.00
46Erosion mat class I type A (628.2002)SY17,200$1.08$1.08$1.10
47Erosion mat class II type C (628.2027)SY130$20.00$20.00$7.95
48Turbidity barriers (628.6005)SY280$22.00$22.00$42.00
49Inlet protection type A (628.7005)EACH5$125.00$125.00$110.00
50Inlet protection type B (628.7010)EACH1$85.00$85.00$65.00
51Temporary ditch checks (628.7504)LF470$8.00$8.00$6.95
52Culvert pipe checks (628.7555)EACH5$32.00$32.00$20.00
53Rock bags (628.7570)EACH50$12.00$12.00$14.00
54Fertilizer type B (629.0210)CWT11$105.00$105.00$90.00
55Seeding mixture no. 20 (630.0120)LB190$9.25$9.25$8.95
56Seeding mixture no. 30 (630.0130)LB590$9.25$9.25$8.95
57Seed water (630.0500)MGAL385$1.00$1.00$15.00
58Delineators temporary (633.1100)EACH50$25.25$25.25$25.25
59Field office type B (642.5001)EACH1$8,500.00$10,000$20,000
60Traffic control drums (643.0300)DAY26,500$0.15$0.15$0.15
61Traffic control barricades type III (643.0420)DAY1,360$1.00$1.00$1.00
62Traffic control flexible tubular marker posts (643.0500)EACH290$37.00$37.00$37.00
63Traffic control flexible tubular marker bases (643.0600)EACH290$12.25$12.25$12.25
64Traffic control warning lights type A (643.0705)DAY2,700$0.13$0.13$0.13
65Traffic control warning lights type C (643.0715)DAY7,770$0.13$0.13$0.13
66Traffic control arrow boards (643.0800)DAY200$7.50$7.50$7.50
67Connected arrow board (643.0810.S)DAY90$15.00$15.00$15.00
68Traffic control signs (643.0900)DAY6,010$0.22$0.22$0.22
69Traffic control covering signs type I (643.0910)EACH2$235.00$235.00$235.00
70Traffic control covering signs type II (643.0920)EACH1$125.00$125.00$125.00
71Traffic control signs fixed message (643.1000)SF192$24.25$24.25$24.25
72Connected work zone start and end location markers (643.1220.S)DAY180$12.15$12.15$12.15
73Temporary marking line paint 6- inch (643.3165)LF45,980$0.24$0.24$0.24
74Temporary marking line removable tape 6-inch (643.3180)LF1,620$2.15$2.15$2.15
75Temporary marking line paint 10- inch (643.3265)LF400$0.99$0.99$0.99
76Temporary marking raised pavement marker type I (643.3760)EACH275$5.55$5.55$5.55
77Temporary marking removable mask out tape 6-inch (643.3960)LF1,320$2.75$2.75$2.75
78Traffic control (643.5000)EACH1$25,630$25,630$25,630
79Geotextile type DF schedule A (645.0111)SY2,570$2.50$2.77$2.77
80Geotextile type DF schedule B (645.0112)SY380$3.00$3.94$3.94
81Geotextile type HR (645.0120)SY380$3.00$4.58$4.58
82Geotextile type sas (645.0140)SY1,165$2.75$2.90$2.90
83Marking line epoxy 6-inch (646.2020)LF20,020$0.56$0.56$0.56
84Marking line epoxy 10-inch (646.4020)LF665$1.50$1.50$1.50
85Marking stop line epoxy 18-inch (646.6120)LF30$16.00$16.00$16.00
86Cold weather marking epoxy 6-inch (646.6466)LF2,095$0.60$0.60$0.60
87Marking removal line 6-inch (646.9002)LF8,190$0.50$0.50$0.50
88Marking removal line 10-inch (646.9102)LF400$2.00$2.00$2.00
89Construction staking storm sewer (650.4000)EACH2$41.31$41.31$41.31
90Construction staking subgrade (650.4500)LF3,123$0.01$0.01$0.01
91Construction staking base (650.5000)LF3,123$1.21$1.21$1.21
92Construction staking supplemental control (project) 01. 1058-25-62 (650.9911)EACH1$622.81$622.81$622.81
93Construction staking slope stakes (650.9920)LF6,387$0.84$0.84$0.84
94Sawing asphalt (690.0150)LF2,177$1.35$1.35$1.35
95Sawing concrete (690.0250)LF1,420$2.25$2.25$2.25
96Incentive compressive strength concrete pavement (715.0720)DOL500$1.00$1.00$1.00
97On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS2,000$5.00$5.00$5.00
98On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS1,260$5.00$5.00$5.00
99Special 02. excavation special (SPV.0035)CY380$58.03$21.84$21.84
100Special 03. flowable fill (SPV.0035)CY30$250.00$770.00$770.00
101Special 01. temporary access road (SPV.0060)EACH1$104,000$100,000$50,000
102Special 02. temporary causeway (SPV.0060)EACH1$75,000$108,650$108,650
103Special 03. underdrain connection to inlet (SPV.0060)EACH1$475.00$350.00$350.00
104Special 04. clean existing underdrain outlet (SPV.0060)EACH3$792.00$250.00$250.00
105Special 05. removing raised pavement markers & filling voids (SPV.0060)EACH10$65.00$65.00$65.00
106Special 01. construction staking pavement replacement reference (SPV.0090)LF350$5.00$5.00$5.00
107Special 02. construction staking stability berm (SPV.0090)LF110$12.00$12.00$12.00
108Special 03. marking diagonal epoxy 24-inch special (SPV.0090)LF210$16.25$16.25$16.25
WisDOT contract 20250513029: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of May 13, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy