WisDOT contract 20250610003 bid tabulation
Merrimac Ferry; Ferry Operations Building (STH 113, Columbia County Merrimac Ferry). Let by Wisconsin DOT on June 10, 2025, Columbia. 1 bid received; low bid $749,999 by Joe Daniels Construction Co., Inc..
- Owner
- Wisconsin DOT
- Letting
- 10 JUN 2025
- Pay items
- 48
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Joe Daniels Construction Co., Inc. | $749,999 | Low |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Joe Daniels Construction Co., Inc. |
|---|---|---|---|---|
| 1 | Removing concrete pavement (204.0100) | SY | 121 | $33.09 |
| 2 | Removing concrete sidewalk (204.0155) | SY | 11 | $44.12 |
| 3 | Removing fence (204.0170) | LF | 48 | $4.27 |
| 4 | Removing building (station) 01. sta 5+75 (204.0231) | EACH | 1 | $10,995 |
| 5 | Finishing roadway (project) 01. 5640-01-87 (213.0100) | EACH | 1 | $120,967 |
| 6 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 284 | $25.49 |
| 7 | Tack coat (455.0605) | GAL | 18 | $5.69 |
| 8 | Asphaltic surface (465.0105) | TON | 68 | $248.21 |
| 9 | Cleaning culvert pipes (520.8700) | EACH | 1 | $868.12 |
| 10 | Concrete sidewalk 5-inch (602.0410) | SF | 180 | $26.76 |
| 11 | Concrete driveway 7-inch (602.0815) | SY | 130 | $136.21 |
| 12 | Maintenance and repair of haul roads (project) 01. 5640-01-87 (618.0100) | EACH | 1 | $35,579 |
| 13 | Mobilization (619.1000) | EACH | 1 | $3,444.00 |
| 14 | Water (624.0100) | MGAL | 7 | $213.47 |
| 15 | Salvaged topsoil (625.0500) | SY | 468 | $6.70 |
| 16 | Silt fence (628.1504) | LF | 214 | $8.55 |
| 17 | Silt fence maintenance (628.1520) | LF | 214 | $1.45 |
| 18 | Mobilizations erosion control (628.1905) | EACH | 7 | $498.10 |
| 19 | Mobilizations emergency erosion control (628.1910) | EACH | 4 | $498.10 |
| 20 | Erosion mat urban class I type B (628.2008) | SY | 468 | $5.69 |
| 21 | Culvert pipe checks (628.7555) | EACH | 2 | $71.16 |
| 22 | Tracking pads (628.7560) | EACH | 1 | $3,054.06 |
| 23 | Fertilizer type B (629.0210) | CWT | 0.40 | $711.57 |
| 24 | Seeding mixture no. 40 (630.0140) | LB | 21 | $71.16 |
| 25 | Seed water (630.0500) | MGAL | 10.70 | $213.47 |
| 26 | Field office type B (642.5001) | EACH | 1 | $24,891 |
| 27 | Traffic control drums (643.0300) | DAY | 1,080 | $0.63 |
| 28 | Traffic control signs (643.0900) | DAY | 540 | $5.22 |
| 29 | Traffic control signs fixed message (643.1000) | SF | 18 | $90.13 |
| 30 | Traffic control (643.5000) | EACH | 1 | $3,445.43 |
| 31 | Temporary pedestrian barricade (644.1810) | LF | 118 | $15.78 |
| 32 | Construction staking subgrade (650.4500) | LF | 119 | $4.78 |
| 33 | Construction staking base (650.5000) | LF | 119 | $7.18 |
| 34 | Construction staking structure layout (structure) 01. ferry operations building (650.6501) | EACH | 1 | $1,565.46 |
| 35 | Construction staking sidewalk (project) 01. 5640-01-87 (650.9500) | EACH | 1 | $1,565.46 |
| 36 | Construction staking supplemental control (project) 01. 5640-01-87 (650.9911) | EACH | 1 | $1,138.51 |
| 37 | Sawing asphalt (690.0150) | LF | 51 | $24.22 |
| 38 | Sawing concrete (690.0250) | LF | 5 | $28.18 |
| 39 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 800 | $5.00 |
| 40 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 500 | $5.00 |
| 41 | Special 01. ferry operations building (SPV.0060) | EACH | 1 | $278,205 |
| 42 | Special 02. ferry operations building hvac (SPV.0060) | EACH | 1 | $55,776 |
| 43 | Special 03. ferry operations building electrical (SPV.0060) | EACH | 1 | $99,890 |
| 44 | Special 04. grading and shaping site (SPV.0060) | EACH | 1 | $10,772 |
| 45 | Special 05. gate system metal 14- FT (SPV.0060) | EACH | 1 | $5,362.40 |
| 46 | Special 06. salvage sign (surveillance) (SPV.0060) | EACH | 1 | $341.55 |
| 47 | Special 07. construction staking driveways 5640-01-87 (SPV.0060) | EACH | 1 | $1,565.46 |
| 48 | Special 01. fence wood 6-FT (SPV.0090) | LF | 56 | $66.71 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of June 10, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.