Ih43 North South Freeway; Bridge Over CTH Ll B45-0048 (IH 043, Ozaukee County IH 43 North South Freeway). Let by Wisconsin DOT on August 12, 2025, Ozaukee. 5 bids received; low bid $229,232 by Vinton Construction Company.
- Owner
- Wisconsin DOT
- Letting
- 12 AUG 2025
- Pay items
- 53
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Vinton Construction Company | $229,232 | Low |
| 2 | Payne and Dolan, Inc | $267,268 | +17% |
| 3 | James Peterson Sons, Inc. | $290,588 | +27% |
| 4 | Musson Bros., Inc. | $312,092 | +36% |
| 5 | Zignego Company, Inc. | $360,228 | +57% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Vinton Construction Company | 2. Payne and Dolan, Inc | 3. James Peterson Sons, Inc. | 4. Musson Bros., Inc. | 5. Zignego Company, Inc. |
|---|---|---|---|---|---|---|---|---|
| 1 | Removing storm sewer (size) 01. 30-inch (204.0245) | LF | 16 | $25.85 | $102.00 | $50.00 | $200.00 | $1,000.00 |
| 2 | Abandoning sewer (204.0291.S) | CY | 46 | $341.00 | $409.00 | $400.00 | $200.00 | $300.00 |
| 3 | Excavation common (205.0100) | CY | 156 | $21.71 | $41.40 | $44.00 | $50.00 | $70.00 |
| 4 | Backfill controlled low strength (209.0200.S) | CY | 4 | $950.00 | $1,390.00 | $2,000.00 | $1,090.00 | $2,000.00 |
| 5 | Backfill granular grade 1 (209.1500) | TON | 53 | $144.96 | $172.50 | $125.00 | $20.00 | $100.00 |
| 6 | Finishing roadway (project) 01. 1450-05-73 (213.0100) | EACH | 1 | $2,000.00 | $4,450.00 | $2,000.00 | $1,010.00 | $1,000.00 |
| 7 | Base aggregate dense 3/4-inch (305.0110) | TON | 27 | $150.00 | $88.25 | $64.50 | $157.00 | $100.00 |
| 8 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 245 | $23.85 | $30.75 | $25.81 | $55.00 | $100.00 |
| 9 | Base aggregate open-graded (310.0110) | TON | 41 | $48.14 | $99.40 | $75.00 | $38.00 | $100.00 |
| 10 | HMA cold weather paving (450.4000) | TON | 104 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 11 | Tack coat (455.0605) | GAL | 22 | $2.50 | $2.50 | $2.50 | $2.50 | $2.50 |
| 12 | Incentive density HMA pavement (460.2000) | DOL | 70 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 13 | HMA pavement 3 MT 58-28 S (460.6223) | TON | 62 | $215.00 | $215.00 | $215.00 | $218.00 | $215.00 |
| 14 | HMA pavement 4 MT 58-28 S (460.6224) | TON | 42 | $215.00 | $215.00 | $215.00 | $218.00 | $215.00 |
| 15 | Culvert pipe reinforced concrete class III 30-inch (522.0130) | LF | 224 | $198.02 | $269.00 | $375.00 | $305.00 | $220.00 |
| 16 | Apron endwalls for culvert pipe reinforced concrete 30-inch (522.1030) | EACH | 2 | $2,778.75 | $2,625.00 | $2,150.00 | $2,260.00 | $5,000.00 |
| 17 | Slope paving repair crushed aggregate (604.9010.S) | CY | 7 | $78.50 | $1,950.00 | $125.00 | $79.50 | $175.00 |
| 18 | Reseal crushed aggregate slope paving (604.9015.S) | SY | 685 | $19.28 | $24.00 | $24.00 | $23.00 | $25.00 |
| 19 | Riprap medium (606.0200) | CY | 6 | $200.00 | $245.00 | $200.00 | $170.00 | $1,000.00 |
| 20 | Pipe underdrain 6-inch (612.0106) | LF | 548 | $17.45 | $15.50 | $30.00 | $13.00 | $35.00 |
| 21 | Pipe underdrain unperforated 6- inch (612.0206) | LF | 62 | $61.00 | $19.90 | $75.00 | $43.50 | $100.00 |
| 22 | Pipe underdrain wrapped 6-inch (612.0406) | LF | 86 | $61.00 | $7.95 | $110.00 | $32.00 | $100.00 |
| 23 | Apron endwalls for underdrain reinforced concrete 6-inch (612.0806) | EACH | 1 | $336.63 | $1,275.00 | $500.00 | $344.00 | $5,000.00 |
| 24 | Mobilization (619.1000) | EACH | 1 | $42,450 | $31,000 | $38,400 | $95,000 | $84,700 |
| 25 | Topsoil (625.0100) | SY | 594 | $7.50 | $11.65 | $12.00 | $12.00 | $6.95 |
| 26 | Silt fence (628.1504) | LF | 426 | $3.50 | $3.00 | $3.00 | $3.50 | $4.00 |
| 27 | Silt fence maintenance (628.1520) | LF | 426 | $0.10 | $0.25 | $0.25 | $0.10 | $1.00 |
| 28 | Mobilizations erosion control (628.1905) | EACH | 1 | $300.00 | $250.00 | $250.00 | $304.00 | $200.00 |
| 29 | Mobilizations emergency erosion control (628.1910) | EACH | 1 | $100.00 | $250.00 | $250.00 | $101.00 | $200.00 |
| 30 | Erosion mat class II type B (628.2023) | SY | 594 | $2.65 | $3.00 | $3.00 | $2.70 | $2.50 |
| 31 | Inlet protection type D (628.7020) | EACH | 1 | $150.00 | $150.00 | $150.00 | $152.00 | $125.00 |
| 32 | Temporary ditch checks (628.7504) | LF | 63 | $9.30 | $10.00 | $10.00 | $9.40 | $9.95 |
| 33 | Culvert pipe checks (628.7555) | EACH | 5 | $45.00 | $25.00 | $25.00 | $45.50 | $25.00 |
| 34 | Fertilizer type B (629.0210) | CWT | 1 | $100.00 | $125.00 | $125.00 | $101.00 | $200.00 |
| 35 | Seeding mixture no. 10 (630.0110) | LB | 16 | $25.00 | $25.00 | $25.00 | $25.50 | $75.00 |
| 36 | Seeding temporary (630.0200) | LB | 4 | $22.00 | $25.00 | $25.00 | $22.50 | $50.00 |
| 37 | Seed water (630.0500) | MGAL | 7 | $40.00 | $100.00 | $100.00 | $40.50 | $150.00 |
| 38 | Markers culvert end (633.5200) | EACH | 2 | $65.00 | $60.00 | $60.00 | $66.00 | $115.00 |
| 39 | Traffic control drums (643.0300) | DAY | 188 | $4.12 | $1.00 | $0.24 | $0.24 | $1.00 |
| 40 | Traffic control barricades type III (643.0420) | DAY | 220 | $3.76 | $1.50 | $0.59 | $0.60 | $1.50 |
| 41 | Traffic control warning lights type A (643.0705) | DAY | 360 | $0.85 | $0.50 | $10.00 | $10.00 | $0.50 |
| 42 | Traffic control signs (643.0900) | DAY | 1,308 | $1.50 | $0.35 | $0.75 | $0.76 | $0.35 |
| 43 | Traffic control covering signs type II (643.0920) | EACH | 1 | $151.08 | $140.00 | $135.00 | $137.00 | $140.00 |
| 44 | Traffic control signs PCMS (643.1050) | DAY | 14 | $60.00 | $45.00 | $35.00 | $35.50 | $45.00 |
| 45 | Traffic control (643.5000) | EACH | 1 | $7,800.00 | $14,540 | $6,981.00 | $15,000 | $13,150 |
| 46 | Geotextile type DF schedule A (645.0111) | SY | 244 | $4.77 | $5.60 | $4.00 | $3.40 | $10.00 |
| 47 | Geotextile type HR (645.0120) | SY | 12 | $10.00 | $88.80 | $15.00 | $15.50 | $100.00 |
| 48 | Marking line epoxy 4-inch (646.1020) | LF | 460 | $11.00 | $11.00 | $11.00 | $9.80 | $11.00 |
| 49 | Cold weather marking epoxy 4-inch (646.6464) | LF | 460 | $2.50 | $2.50 | $2.50 | $10.50 | $2.50 |
| 50 | Construction staking storm sewer (650.4000) | EACH | 3 | $1,000.00 | $1,200.00 | $1,000.00 | $354.00 | $1,000.00 |
| 51 | Sawing asphalt (690.0150) | LF | 62 | $10.00 | $2.95 | $2.95 | $3.50 | $2.95 |
| 52 | Special 01. connect to existing inlet (SPV.0060) | EACH | 1 | $463.00 | $945.00 | $350.00 | $253.00 | $2,000.00 |
| 53 | Special 02. utility line opening (ulo) (SPV.0060) | EACH | 1 | $1,400.00 | $2,105.00 | $1,500.00 | $253.00 | $2,000.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of August 12, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.