WisDOT contract 20250812014 bid tabulation
Wausau - Wittenberg; CTH D to CTH Oo (STH 029, Marathon County Wausau - Wittenberg). Let by Wisconsin DOT on August 12, 2025, Marathon. 4 bids received; low bid $3,706,974 by Vinton Construction Company.
- Owner
- Wisconsin DOT
- Letting
- 12 AUG 2025
- Pay items
- 117
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Vinton Construction Company | $3,706,974 | Low |
| 2 | Michels Road & Stone, Inc. | $3,965,513 | +7.0% |
| 3 | Chippewa Concrete Services, Inc. | $4,429,006 | +19% |
| 4 | Zignego Company, Inc. | $4,436,835 | +20% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Vinton Construction Company | 2. Michels Road & Stone, Inc. | 3. Chippewa Concrete Services, Inc. | 4. Zignego Company, Inc. |
|---|---|---|---|---|---|---|---|
| 1 | Debris containment over waterway (structure) 01. B-58-0039 (203.0335) | EACH | 1 | $0.01 | $1,500.00 | $1,533.00 | $1,500.00 |
| 2 | Removing concrete pavement (204.0100) | SY | 14,700 | $5.40 | $8.00 | $12.78 | $8.80 |
| 3 | Removing asphaltic surface (204.0110) | SY | 6,860 | $2.95 | $4.00 | $4.09 | $5.00 |
| 4 | Removing asphaltic surface butt joints (204.0115) | SY | 500 | $5.49 | $5.49 | $5.61 | $5.49 |
| 5 | Removing asphaltic surface milling (204.0120) | SY | 54,100 | $2.53 | $2.53 | $2.59 | $2.53 |
| 6 | Removing curb & gutter (204.0150) | LF | 210 | $10.00 | $6.00 | $9.20 | $5.00 |
| 7 | Removing guardrail (204.0165) | LF | 1,570 | $2.50 | $2.50 | $4.09 | $2.50 |
| 8 | Removing delineators and markers (204.0180) | EACH | 250 | $15.00 | $15.00 | $20.44 | $15.00 |
| 9 | Removing surface drains (204.0190) | EACH | 2 | $200.00 | $400.00 | $511.00 | $500.00 |
| 10 | Prepare foundation for concrete pavement (project) 01. 1053-07-60 (211.0201) | EACH | 1 | $5,000.00 | $10,000 | $7,665.00 | $1.00 |
| 11 | Prepare foundation for asphaltic shoulders (211.0400) | STA | 122 | $90.00 | $175.00 | $137.97 | $180.00 |
| 12 | Prepare foundation for base aggregate (211.0500) | STA | 51 | $100.00 | $235.00 | $222.29 | $200.00 |
| 13 | Finishing roadway (project) 01. 1053-07-60 (213.0100) | EACH | 1 | $2,000.00 | $5,000.00 | $5,110.00 | $1,000.00 |
| 14 | Base aggregate dense 3/4-inch (305.0110) | TON | 5,420 | $22.15 | $26.00 | $31.68 | $30.00 |
| 15 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 1,366 | $13.75 | $21.00 | $25.04 | $30.00 |
| 16 | Shaping shoulders (305.0500) | STA | 20 | $1.00 | $230.00 | $511.00 | $200.00 |
| 17 | Removing pavement for base patching (390.0100) | CY | 68 | $0.01 | $69.04 | $204.40 | $200.00 |
| 18 | Concrete pavement 11-inch (415.0110) | SY | 14,560 | $56.75 | $46.43 | $80.15 | $69.09 |
| 19 | Concrete pavement gaps (415.0210) | EACH | 3 | $0.01 | $500.00 | $7,194.88 | $1,000.00 |
| 20 | Rout and seal (415.6000.S) | LF | 69,300 | $0.65 | $1.01 | $1.03 | $0.83 |
| 21 | Drilled tie bars (416.0610) | EACH | 3,731 | $9.50 | $11.07 | $8.99 | $15.00 |
| 22 | Drilled dowel bars (416.0620) | EACH | 4,488 | $14.50 | $16.14 | $16.86 | $30.00 |
| 23 | Concrete pavement repair (416.1710) | SY | 2,020 | $95.24 | $107.19 | $98.06 | $114.60 |
| 24 | Concrete pavement replacement (416.1720) | SY | 3,340 | $99.24 | $106.84 | $98.06 | $114.60 |
| 25 | Continuous diamond grinding concrete pavement (420.1000) | SY | 9,360 | $6.45 | $6.45 | $6.59 | $6.45 |
| 26 | HMA cold weather paving (450.4000) | TON | 1,930 | $0.80 | $0.80 | $0.82 | $0.80 |
| 27 | Tack coat (455.0605) | GAL | 4,340 | $5.65 | $5.65 | $5.77 | $5.65 |
| 28 | Incentive density HMA pavement (460.2000) | DOL | 4,950 | $1.00 | $1.00 | $1.00 | $1.00 |
| 29 | HMA pavement 4 LT 58-28 S (460.5224) | TON | 7,280 | $83.10 | $83.10 | $84.93 | $83.10 |
| 30 | HMA pavement 4 HT 58-28 H (460.7424) | TON | 430 | $121.33 | $121.33 | $124.00 | $121.33 |
| 31 | Asphaltic surface (465.0105) | TON | 12 | $253.57 | $253.57 | $259.15 | $253.57 |
| 32 | Asphaltic surface patching (465.0110) | TON | 173 | $126.84 | $126.84 | $129.63 | $126.84 |
| 33 | Asphaltic rumble strips, shoulder divided roadway (465.0510) | LF | 31,600 | $0.40 | $0.40 | $0.41 | $0.40 |
| 34 | Protective surface treatment (502.3200) | SY | 22 | $30.00 | $30.00 | $30.66 | $30.00 |
| 35 | Bar steel reinforcement HS coated structures (505.0600) | LB | 83 | $25.00 | $25.00 | $25.55 | $25.00 |
| 36 | Concrete surface repair (509.1500) | SF | 235 | $250.00 | $250.00 | $255.50 | $250.00 |
| 37 | Polymer overlay (509.5100.S) | SY | 2 | $1,067.00 | $1,067.00 | $1,090.47 | $1,067.00 |
| 38 | Removing polymer overlay (structure) 01. B-58-0039 (509.9015.S) | SY | 2 | $534.00 | $534.00 | $545.75 | $534.00 |
| 39 | Concrete curb & gutter 6-inch sloped 36-inch type D (601.0557) | LF | 210 | $60.00 | $45.00 | $72.52 | $70.00 |
| 40 | Concrete curb & gutter 4-inch sloped 36-inch type TBT (601.0588) | LF | 30 | $60.00 | $65.00 | $72.52 | $70.00 |
| 41 | Concrete curb & gutter 4-inch sloped 36-inch type TBTT (601.0590) | LF | 29 | $60.00 | $65.00 | $72.52 | $70.00 |
| 42 | Concrete surface drains (602.3010) | CY | 2.20 | $1,000.00 | $1,100.00 | $2,022.52 | $1,000.00 |
| 43 | Concrete rumble strips, shoulder divided roadway (602.3210) | LF | 26,900 | $0.45 | $0.45 | $0.46 | $0.45 |
| 44 | Concrete barrier temporary precast delivered (603.8000) | LF | 235 | $9.50 | $30.00 | $9.71 | $20.00 |
| 45 | Concrete barrier temporary precast installed (603.8125) | LF | 470 | $9.00 | $7.50 | $9.20 | $10.00 |
| 46 | Riprap medium (606.0200) | CY | 10 | $163.10 | $155.00 | $143.08 | $300.00 |
| 47 | Barrier system grading shaping finishing (614.0010) | EACH | 5 | $3,950.00 | $4,850.00 | $5,559.68 | $4,000.00 |
| 48 | MGS guardrail 3 (614.2300) | LF | 962.50 | $28.00 | $28.00 | $29.64 | $28.00 |
| 49 | MGS thrie beam transition (614.2500) | LF | 197 | $96.00 | $96.00 | $96.07 | $96.00 |
| 50 | MGS guardrail terminal eat (614.2610) | EACH | 5 | $3,850.00 | $3,850.00 | $5,007.80 | $3,850.00 |
| 51 | Maintenance and repair of haul roads (project) 01. 1053-07-60 (618.0100) | EACH | 1 | $0.01 | $0.01 | $2,555.00 | $1.00 |
| 52 | Mobilization (619.1000) | EACH | 1 | $191,500 | $296,642 | $165,625 | $240,000 |
| 53 | Water (624.0100) | MGAL | 106 | $30.00 | $80.00 | $1.02 | $100.00 |
| 54 | Topsoil (625.0100) | SY | 400 | $8.60 | $10.00 | $8.18 | $10.00 |
| 55 | Silt fence (628.1504) | LF | 2,070 | $2.25 | $2.25 | $2.81 | $2.25 |
| 56 | Silt fence maintenance (628.1520) | LF | 2,070 | $0.05 | $0.05 | $0.01 | $0.05 |
| 57 | Mobilizations erosion control (628.1905) | EACH | 4 | $250.00 | $250.00 | $357.70 | $250.00 |
| 58 | Mobilizations emergency erosion control (628.1910) | EACH | 2 | $300.00 | $300.00 | $1.02 | $300.00 |
| 59 | Erosion mat urban class I type B (628.2008) | SY | 2,170 | $1.75 | $1.75 | $4.09 | $1.75 |
| 60 | Temporary ditch checks (628.7504) | LF | 40 | $9.00 | $9.00 | $11.24 | $9.00 |
| 61 | Culvert pipe checks (628.7555) | EACH | 2 | $25.00 | $25.00 | $204.40 | $25.00 |
| 62 | Rock bags (628.7570) | EACH | 40 | $25.00 | $25.00 | $20.44 | $25.00 |
| 63 | Fertilizer type B (629.0210) | CWT | 3 | $80.00 | $80.00 | $153.30 | $80.00 |
| 64 | Seeding mixture no. 30 (630.0130) | LB | 110 | $8.45 | $8.45 | $12.26 | $8.45 |
| 65 | Seeding temporary (630.0200) | LB | 20 | $5.00 | $5.00 | $5.11 | $5.00 |
| 66 | Seed water (630.0500) | MGAL | 60 | $75.00 | $75.00 | $102.20 | $75.00 |
| 67 | Delineator posts steel (633.0100) | EACH | 107 | $30.00 | $30.00 | $86.87 | $30.00 |
| 68 | Delineator reflectors (633.0500) | EACH | 123 | $6.00 | $6.00 | $15.33 | $6.00 |
| 69 | Delineators temporary (633.1100) | EACH | 76 | $29.80 | $29.80 | $86.87 | $35.00 |
| 70 | Markers permanent flexible (633.5350) | EACH | 194 | $50.00 | $50.00 | $71.54 | $50.00 |
| 71 | Field office type B (642.5001) | EACH | 1 | $9,500.00 | $7,000.00 | $7,665.00 | $10,000 |
| 72 | Traffic control drums (643.0300) | DAY | 25,700 | $0.20 | $0.20 | $0.51 | $0.20 |
| 73 | Traffic control barricades type III (643.0420) | DAY | 10,900 | $0.55 | $0.55 | $0.51 | $0.55 |
| 74 | Traffic control flexible tubular marker posts (643.0500) | EACH | 846 | $30.00 | $30.00 | $22.48 | $30.00 |
| 75 | Traffic control flexible tubular marker bases (643.0600) | EACH | 736 | $11.00 | $11.00 | $8.94 | $11.00 |
| 76 | Traffic control warning lights type A (643.0705) | DAY | 6,880 | $0.12 | $0.12 | $0.10 | $0.12 |
| 77 | Traffic control warning lights type C (643.0715) | DAY | 6,910 | $0.14 | $0.14 | $0.10 | $0.14 |
| 78 | Connected arrow board (643.0810.S) | DAY | 310 | $8.85 | $8.85 | $16.35 | $8.85 |
| 79 | Traffic control signs (643.0900) | DAY | 16,000 | $0.25 | $0.25 | $0.51 | $0.25 |
| 80 | Traffic control covering signs type II (643.0920) | EACH | 177 | $45.00 | $45.00 | $20.44 | $45.00 |
| 81 | Traffic control signs fixed message (643.1000) | SF | 64 | $15.00 | $15.00 | $6.64 | $15.00 |
| 82 | Connected work zone start and end location markers (643.1220.S) | DAY | 310 | $6.50 | $6.50 | $10.22 | $6.50 |
| 83 | Temporary marking line paint 6- inch (643.3165) | LF | 115,000 | $0.25 | $0.25 | $0.26 | $0.25 |
| 84 | Temporary marking stop line removable tape 18-inch (643.3850) | LF | 189 | $6.99 | $6.99 | $5.18 | $6.99 |
| 85 | Traffic control (643.5000) | EACH | 1 | $39,250 | $39,250 | $16,352 | $39,250 |
| 86 | Geotextile type HR (645.0120) | SY | 32 | $10.00 | $5.00 | $12.26 | $50.00 |
| 87 | Marking line epoxy 6-inch (646.2020) | LF | 572 | $1.00 | $1.00 | $1.02 | $1.00 |
| 88 | Marking line grooved black epoxy 6-inch (646.2025) | LF | 9,150 | $0.90 | $0.90 | $0.92 | $0.90 |
| 89 | Marking line grooved wet ref epoxy 6-inch (646.2040) | LF | 72,400 | $1.20 | $1.20 | $1.23 | $1.20 |
| 90 | Marking line grooved permanent tape 6-inch (646.2050) | LF | 9,150 | $7.00 | $7.00 | $7.15 | $7.00 |
| 91 | Marking line grooved wet ref epoxy 10-inch (646.4040) | LF | 163 | $3.00 | $3.00 | $3.07 | $3.00 |
| 92 | Marking line grooved permanent tape 10-inch (646.4050) | LF | 2,240 | $11.00 | $11.00 | $11.24 | $11.00 |
| 93 | Marking arrow epoxy (646.5020) | EACH | 2 | $400.00 | $400.00 | $408.80 | $400.00 |
| 94 | Marking stop line epoxy 18-inch (646.6120) | LF | 85 | $16.60 | $16.60 | $16.97 | $16.60 |
| 95 | Cold weather marking epoxy 6-inch (646.6466) | LF | 82,000 | $0.01 | $0.33 | $0.34 | $0.33 |
| 96 | Cold weather marking epoxy 10- inch (646.6470) | LF | 163 | $0.01 | $1.12 | $1.14 | $1.12 |
| 97 | Marking chevron epoxy 12-inch (646.7320) | LF | 177 | $24.65 | $24.65 | $25.19 | $24.65 |
| 98 | Marking curb epoxy (646.8120) | LF | 38 | $8.00 | $8.00 | $8.18 | $8.00 |
| 99 | Marking island nose epoxy (646.8220) | EACH | 3 | $300.00 | $300.00 | $306.60 | $300.00 |
| 100 | Marking removal line 6-inch (646.9002) | LF | 43,200 | $0.24 | $0.24 | $0.25 | $0.24 |
| 101 | Construction staking concrete pavement (650.7000) | LF | 5,041 | $1.27 | $1.27 | $1.30 | $1.27 |
| 102 | Construction staking resurfacing reference (650.8000) | LF | 36,761 | $0.07 | $0.07 | $0.07 | $0.07 |
| 103 | Construction staking supplemental control (project) 01. 1053-07-60 (650.9911) | EACH | 1 | $10.00 | $10.00 | $10.22 | $10.00 |
| 104 | Sawing asphalt (690.0150) | LF | 1,620 | $1.75 | $1.75 | $1.79 | $1.75 |
| 105 | Sawing concrete (690.0250) | LF | 18,750 | $2.30 | $2.30 | $2.40 | $4.30 |
| 106 | Incentive compressive strength concrete pavement (715.0720) | DOL | 4,370 | $1.00 | $1.00 | $1.00 | $1.00 |
| 107 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 2,000 | $5.00 | $5.00 | $5.00 | $5.00 |
| 108 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 1,260 | $5.00 | $5.00 | $5.00 | $5.00 |
| 109 | Special 01. reseal railing post connection (SPV.0060) | EACH | 22 | $200.00 | $200.00 | $204.40 | $200.00 |
| 110 | Special 02. removing raised pavement markers and filling voids (SPV.0060) | EACH | 297 | $50.00 | $71.00 | $72.56 | $71.00 |
| 111 | Special 03. embedded galvanic anodes (SPV.0060) | EACH | 130 | $50.00 | $50.00 | $51.10 | $50.00 |
| 112 | Special 04. coring of existing concrete pavement (SPV.0060) | EACH | 60 | $170.00 | $100.00 | $76.65 | $500.00 |
| 113 | Special 01. flashing stainless steel (SPV.0090) | LF | 121 | $65.00 | $65.00 | $66.43 | $65.00 |
| 114 | Special 02. concrete joint and crack cleaning and repair (SPV.0090) | LF | 230 | $49.39 | $49.39 | $102.67 | $50.00 |
| 115 | Special 01. removing distressed asphaltic surface milling (SPV.0180) | SY | 3,040 | $5.75 | $5.75 | $5.88 | $5.75 |
| 116 | Special 02. concrete pavement repair - centerline (SPV.0180) | SY | 908 | $103.24 | $176.88 | $133.88 | $150.00 |
| 117 | Special 01. full depth asphalt patch (SPV.0195) | TON | 35 | $150.00 | $100.46 | $50.48 | $100.46 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of August 12, 2025. Compiled by Mirage Metrics.