WisDOT contract 20250909005 bid tabulation
T Fox Lake - T Trenton (CTH A); STH 68 to USH 151 (CTH A, Dodge County T Fox Lake - T Trenton (CTH A)). Let by Wisconsin DOT on September 9, 2025, Dodge. 4 bids received; low bid $5,437,937 by Michels Road & Stone, Inc..
- Owner
- Wisconsin DOT
- Letting
- 09 SEP 2025
- Pay items
- 42
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Michels Road & Stone, Inc. | $5,437,937 | Low |
| 2 | Zignego Company, Inc. | $6,064,719 | +12% |
| 3 | Trierweiler Construction & Supply Company, Inc. | $6,073,740 | +12% |
| 4 | Lalonde Contractors Incorporated | $7,674,099 | +41% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Michels Road & Stone, Inc. | 2. Zignego Company, Inc. | 3. Trierweiler Construction & Supply Company, Inc. | 4. Lalonde Contractors Incorporated |
|---|---|---|---|---|---|---|---|
| 1 | Removing concrete pavement (204.0100) | SY | 73 | $20.00 | $20.00 | $35.00 | $16.47 |
| 2 | Removing asphaltic surface milling (204.0120) | SY | 119,200 | $1.55 | $1.86 | $0.65 | $3.44 |
| 3 | Removing curb & gutter (204.0150) | LF | 31 | $15.00 | $20.00 | $25.00 | $29.83 |
| 4 | Prepare foundation for asphaltic paving (project) 01. 6316-00-70 (211.0101) | EACH | 1 | $22,750 | $22,750 | $22,750 | $31,534 |
| 5 | Prepare foundation for concrete pavement (project) 01. 6316-00-70 (211.0201) | EACH | 1 | $20,000 | $1.00 | $2,500.00 | $1.00 |
| 6 | Finishing roadway (project) 01. 6316-00-70 (213.0100) | EACH | 1 | $3,500.00 | $1,000.00 | $2,500.00 | $4,650.00 |
| 7 | Base aggregate dense 3/4-inch (305.0110) | TON | 11,000 | $15.60 | $0.01 | $18.83 | $17.87 |
| 8 | Shaping shoulders (305.0500) | STA | 621 | $54.00 | $1.00 | $27.50 | $49.74 |
| 9 | Concrete pavement 8-inch (415.0080) | SY | 118,310 | $35.08 | $43.12 | $38.74 | $50.86 |
| 10 | Concrete pavement gaps (415.0210) | EACH | 38 | $500.00 | $1.00 | $746.54 | $1,140.67 |
| 11 | Drilled tie bars (416.0610) | EACH | 823 | $12.53 | $10.00 | $10.34 | $11.08 |
| 12 | Drilled dowel bars (416.0620) | EACH | 22 | $24.66 | $30.00 | $15.05 | $15.13 |
| 13 | Tack coat (455.0605) | GAL | 89 | $14.25 | $14.25 | $14.25 | $14.25 |
| 14 | Asphaltic surface (465.0105) | TON | 398 | $123.50 | $123.50 | $123.50 | $123.50 |
| 15 | Asphaltic surface driveways and field entrances (465.0120) | TON | 210 | $179.25 | $179.25 | $179.25 | $179.25 |
| 16 | Asphaltic flumes (465.0315) | SY | 33 | $51.25 | $51.25 | $51.25 | $51.25 |
| 17 | Concrete curb & gutter 30-inch type A (601.0409) | LF | 45 | $54.60 | $100.00 | $64.19 | $56.38 |
| 18 | Concrete curb & gutter 6-inch sloped 36-inch type A (601.0555) | LF | 1,560 | $39.60 | $40.00 | $72.62 | $59.53 |
| 19 | Maintenance and repair of haul roads (project) 01. 6316-00-70 (618.0100) | EACH | 1 | $0.01 | $1.00 | $500.00 | $1.00 |
| 20 | Mobilization (619.1000) | EACH | 1 | $404,716 | $228,000 | $638,593 | $451,326 |
| 21 | Water (624.0100) | MGAL | 150 | $80.00 | $50.00 | $45.00 | $55.60 |
| 22 | Field office type B (642.5001) | EACH | 1 | $11,000 | $10,000 | $11,000 | $10,008 |
| 23 | Traffic control drums (643.0300) | DAY | 4,000 | $0.25 | $0.89 | $0.89 | $0.89 |
| 24 | Traffic control barricades type III (643.0420) | DAY | 2,262 | $1.00 | $1.73 | $1.73 | $1.73 |
| 25 | Traffic control warning lights type A (643.0705) | DAY | 4,524 | $0.25 | $0.28 | $0.28 | $0.28 |
| 26 | Traffic control signs (643.0900) | DAY | 30,537 | $0.25 | $0.40 | $0.40 | $0.40 |
| 27 | Traffic control covering signs type I (643.0910) | EACH | 6 | $150.00 | $78.20 | $78.20 | $78.20 |
| 28 | Traffic control covering signs type II (643.0920) | EACH | 1 | $35.00 | $156.28 | $156.28 | $156.28 |
| 29 | Traffic control signs PCMS (643.1050) | DAY | 21 | $75.00 | $60.00 | $60.00 | $60.00 |
| 30 | Traffic control (643.5000) | EACH | 1 | $10,000 | $7,164.44 | $7,164.44 | $7,164.44 |
| 31 | Marking line grooved wet ref epoxy 6-inch (646.2040) | LF | 82,736 | $1.28 | $1.28 | $1.30 | $1.30 |
| 32 | Locating no-passing zones (648.0100) | MI | 6.10 | $480.93 | $480.93 | $425.00 | $425.00 |
| 33 | Construction staking base (650.5000) | LF | 451 | $0.55 | $1.00 | $0.75 | $0.55 |
| 34 | Construction staking concrete pavement (650.7000) | LF | 33,165 | $0.40 | $2.00 | $0.50 | $1.25 |
| 35 | Construction staking resurfacing reference (650.8000) | LF | 33,616 | $0.07 | $0.12 | $0.25 | $0.07 |
| 36 | Construction staking supplemental control (project) 01. 6316-00-70 (650.9911) | EACH | 1 | $10.00 | $5,000.00 | $3,000.00 | $10.00 |
| 37 | Sawing asphalt (690.0150) | LF | 850 | $0.90 | $1.39 | $1.25 | $1.25 |
| 38 | Sawing concrete (690.0250) | LF | 35 | $2.00 | $2.50 | $6.00 | $6.00 |
| 39 | Incentive flexural strength concrete pavement (715.0715) | DOL | 35,493 | $1.00 | $1.00 | $1.00 | $1.00 |
| 40 | Incentive iri ride (740.0440) | DOL | 24,416 | $1.00 | $1.00 | $1.00 | $1.00 |
| 41 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 2,400 | $5.00 | $5.00 | $5.00 | $5.00 |
| 42 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 3,200 | $5.00 | $5.00 | $5.00 | $5.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of September 9, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.