WisDOT contract 20250909015 bid tabulation

Ser Tree Clearing Project; Various Ser Counties (VAR HWY, SE Wide SER Tree Clearing). Let by Wisconsin DOT on September 9, 2025, Southeast Region Wide. 4 bids received; low bid $999,010 by Interstate Tree Landscaping.

Owner
Wisconsin DOT
Letting
09 SEP 2025
Pay items
21
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Interstate Tree Landscaping$999,010Low
2Highway Landscapers, Inc.$1,096,447+10%
3Graber Construction & Excavation Inc$1,171,840+17%
4Homer Tree Service, Inc.$1,186,547+19%
WisDOT contract 20250909015: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Interstate Tree Landscaping2. Highway Landscapers, Inc.3. Graber Construction & Excavation Inc4. Homer Tree Service, Inc.
1Clearing (201.0105)STA454$1,572.00$1,375.00$1,795.00$1,799.00
2Clearing (201.0120)ID655$77.00$110.00$60.00$55.00
3Finishing roadway (project) 01. 3742-03-70 (213.0100)EACH1$1.00$500.00$4,000.00$500.00
4Maintenance and repair of haul roads (project) 01. 3742-03-70 (618.0100)EACH1$1.00$250.00$990.00$1.00
5Silt fence (628.1504)LF400$3.00$4.00$3.30$3.00
6Silt fence maintenance (628.1520)LF400$1.00$0.01$0.50$0.50
7Mobilizations erosion control (628.1905)EACH15$300.00$500.00$440.00$350.00
8Mobilizations emergency erosion control (628.1910)EACH15$500.00$1.00$160.00$500.00
9Temporary ditch checks (628.7504)LF300$3.41$7.00$5.50$5.00
10Traffic control signs PCMS (643.1050)DAY200$45.00$150.00$49.50$40.00
11Special 01. traffic control - lane closure (SPV.0045)DAY16$1,150.00$2,900.00$2,500.00$2,900.00
12Special 02. traffic control - shoulder closure (SPV.0045)DAY78$775.00$400.00$1,100.00$1,100.00
13Special 03. traffic control - pedestrian accommodation (SPV.0045)DAY12$550.00$5,000.00$700.00$1,050.00
14Special 04. traffic control - no parking signs (SPV.0045)DAY14$110.00$150.00$50.00$975.00
15Special 05. traffic control - trail closure (SPV.0045)DAY3$924.00$976.00$50.00$975.00
16Special 01. frozen ground erosion control (SPV.0060)EACH6$250.00$250.00$4,500.00$4,500.00
17Special 02. semi-frozen ground erosion control (SPV.0060)EACH7$250.00$250.00$2,500.00$4,250.00
18Special 03. thawed ground erosion control (SPV.0060)EACH7$1,750.00$250.00$2,500.00$4,000.00
19Special 04. semi-permanent restoration (SPV.0060)EACH10$4,500.00$250.00$2,500.00$4,000.00
20Special 05. site mobilization (SPV.0060)EACH15$4,000.00$13,750$4,500.00$1,500.00
21Special 01. staked wattles (SPV.0090)LF200$5.00$9.00$5.00$5.00
WisDOT contract 20250909015: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of September 9, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy