WisDOT contract 20251014016 bid tabulation

St Croix Falls - Turtle Lake; STH 35 N to STH 46 S (USH 008, Polk County St Croix Falls - Turtle Lake). Let by Wisconsin DOT on October 14, 2025, Polk. 1 bid received; low bid $7,520,828 by Monarch Paving Company.

Owner
Wisconsin DOT
Letting
14 OCT 2025
Pay items
113
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Monarch Paving Company$7,520,828Low
WisDOT contract 20251014016: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Monarch Paving Company
1Clearing (201.0105)STA2$2,214.00
2Grubbing (201.0205)STA2$2,067.00
3Removing small pipe culverts (203.0100)EACH1$1,393.00
4Removing concrete pavement (204.0100)SY1,417$8.00
5Removing asphaltic surface butt joints (204.0115)SY2,287$9.04
6Removing asphaltic surface milling (204.0120)SY207,731$1.88
7Removing asphaltic longitudinal notched wedge joint milling (204.0126.S)LF49,440$0.94
8Removing curb & gutter (204.0150)LF697$11.75
9Removing guardrail (204.0165)LF180$5.85
10Removing (item description) 01. culvert endwalls (204.9060.S)EACH9$150.00
11Excavation common (205.0100)CY2,985$14.15
12Prepare foundation for asphaltic paving (project) 01. 1570-00-78 (211.0101)EACH1$62,815
13Prepare foundation for asphaltic shoulders (211.0400)STA760$30.60
14Finishing roadway (project) 01. 1570-00-78 (213.0100)EACH1$3,990.00
15Base aggregate dense 3/4-inch (305.0110)TON1,969$24.42
16Base aggregate dense 1 1/4-inch (305.0120)TON1,570$27.50
17Base aggregate dense 3-inch (305.0130)TON720$30.35
18Shaping shoulders (305.0500)STA996$30.33
19Base aggregate open-graded (310.0110)TON200$48.35
20Select crushed material (312.0110)TON1,655$35.00
21Tack coat (455.0605)GAL26,540$3.27
22HMA percent within limits (PWL) test strip volumetrics (460.0105.S)EACH1$8,600.00
23HMA pavement test strip volumetrics (460.0115.S)EACH1$8,000.00
24HMA pavement test strip density (460.0120.S)EACH1$2,220.00
25Incentive density HMA pavement (460.2000)DOL14,970$1.00
26Incentive density PWL HMA pavement (460.2005)DOL10,410$1.00
27Incentive density HMA pavement longitudinal joints (460.2007)DOL49,460$1.00
28Incentive air voids HMA pavement (460.2010)DOL14,620$1.00
29HMA pavement 5 MT 58-34 V (460.6645)TON17,295$102.30
30HMA pavement 4 SMA 58-34 V (460.8644)TON26,468$113.40
31Material transfer vehicle (460.9000.S)EACH1$28,200
32Asphaltic surface (465.0105)TON443$140.37
33Asphaltic surface driveways and field entrances (465.0120)TON195$201.30
34Asphaltic surface temporary (465.0125)TON240$130.43
35Asphaltic curb (465.0310)LF350$11.65
36Asphaltic flumes (465.0315)SY100$57.36
37Asphaltic rumble strips, shoulder (465.0520)LF92,556$0.25
38Asphaltic rumble strips, centerline (465.0560)LF41,303$0.30
39Apron endwalls for culvert pipe 24- inch (520.1024)EACH3$1,765.00
40Concrete collars for pipe (520.8000)EACH4$1,320.00
41Cleaning culvert pipes (520.8700)EACH12$3,100.00
42Culvert pipe reinforced concrete class III 24-inch (522.0124)LF74$242.00
43Culvert pipe reinforced concrete class III 30-inch (522.0130)LF16$295.00
44Apron endwalls for culvert pipe reinforced concrete 24-inch (522.1024)EACH7$2,058.00
45Apron endwalls for culvert pipe reinforced concrete 30-inch (522.1030)EACH2$2,413.00
46Culvert pipe salvaged 30-inch (524.0130)LF16$59.00
47Concrete curb & gutter 6-inch sloped 36-inch type D (601.0557)LF697$36.00
48Concrete barrier temporary precast delivered (603.8000)LF1,375$13.10
49Concrete barrier temporary precast installed (603.8125)LF2,150$5.25
50Anchoring concrete barrier temporary precast (603.8500)LF800$11.25
51Riprap heavy (606.0300)CY25$125.00
52Pipe underdrain 6-inch (612.0106)LF300$7.00
53Pipe underdrain unperforated 6- inch (612.0206)LF15$43.00
54Apron endwalls for underdrain reinforced concrete 6-inch (612.0806)EACH1$715.00
55Adjusting steel plate beam guard (614.0400)LF425$9.50
56Maintenance and repair of haul roads (project) 01. 1570-00-78 (618.0100)EACH1$1.00
57Mobilization (619.1000)EACH1$520,000
58Water (624.0100)MGAL24$52.13
59Salvaged topsoil (625.0500)SY3,880$2.95
60Silt fence (628.1504)LF1,400$2.80
61Silt fence maintenance (628.1520)LF1,400$0.01
62Mobilizations erosion control (628.1905)EACH4$720.00
63Mobilizations emergency erosion control (628.1910)EACH2$10.00
64Erosion mat class I type B (628.2004)SY934$1.50
65Erosion mat urban class I type B (628.2008)SY3,512$2.06
66Temporary ditch checks (628.7504)LF40$8.40
67Culvert pipe checks (628.7555)EACH25$15.00
68Fertilizer type B (629.0210)CWT5$153.00
69Seeding mixture no. 10 (630.0110)LB94$26.80
70Seed water (630.0500)MGAL323$1.00
71Markers culvert end (633.5200)EACH57$53.00
72Posts wood 4X6-inch X 16-FT (634.0616)EACH2$100.00
73Signs type II reflective F (637.2230)SF18$22.35
74Field office type B (642.5001)EACH1$15,900
75Traffic control drums (643.0300)DAY6,700$0.44
76Traffic control barricades type III (643.0420)DAY288$2.95
77Traffic control warning lights type A (643.0705)DAY500$1.52
78Traffic control warning lights type C (643.0715)DAY820$0.93
79Connected arrow board (643.0810.S)DAY50$28.60
80Traffic control signs (643.0900)DAY6,340$0.60
81Temporary marking line paint 6- inch (643.3165)LF231,587$0.30
82Temporary marking stop line paint 18-inch (643.3805)LF60$16.00
83Traffic control (643.5000)EACH1$89,185
84Geotextile type DF schedule B (645.0112)SY360$3.25
85Geotextile type HR (645.0120)SY50$4.81
86Geotextile type SR (645.0135)SY3,690$4.60
87Marking line grooved wet ref epoxy 6-inch (646.2040)LF176,906$1.30
88Marking line grooved wet ref epoxy 10-inch (646.4040)LF3,205$2.30
89Marking arrow epoxy (646.5020)EACH17$280.00
90Marking word epoxy (646.5120)EACH6$350.00
91Marking stop line epoxy 18-inch (646.6120)LF92$23.00
92Marking diagonal epoxy 12-inch (646.7120)LF1,172$13.00
93Marking corrugated median epoxy (646.8020)SF967$5.00
94Marking curb epoxy (646.8120)LF110$12.00
95Marking island nose epoxy (646.8220)EACH4$340.00
96Marking removal line 4-inch (646.9000)LF5,100$0.55
97Marking removal line wide (646.9200)LF120$1.85
98Construction staking subgrade (650.4500)LF675$0.01
99Construction staking base (650.5000)LF2,025$0.01
100Construction staking curb gutter and curb & gutter (650.5500)LF697$1.20
101Construction staking pipe culverts (650.6000)EACH1$360.00
102Construction staking resurfacing reference (650.8000)LF49,670$0.06
103Construction staking supplemental control (project) 01. 1570-00-78 (650.9911)EACH1$1,561.40
104Construction staking slope stakes (650.9920)LF675$1.00
105Temporary traffic signals for bridges (structure) 01. roadway sloughing (661.0101)EACH2$18,245
106Sawing asphalt (690.0150)LF1,035$1.95
107Sawing concrete (690.0250)LF495$2.75
108Incentive iri ride (740.0440)DOL42,240$1.00
109On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS2,400$5.00
110On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS2,000$5.00
111Special 01. ditch cleaning (SPV.0060)EACH1$780.00
112Special 02. abandon cattle pass (SPV.0060)EACH1$25,550
113Special 01. UV GRP cipp 24-inch (SPV.0090)LF602$302.00
WisDOT contract 20251014016: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of October 14, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy