WisDOT contract 20260113014 bid tabulation
5760-00-72. Let by Wisconsin DOT on January 13, 2026, Sauk. 1 bid received; low bid $6,753,463 by D L Gasser Construction.
- Owner
- Wisconsin DOT
- Letting
- 13 JAN 2026
- Pay items
- 135
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | D L Gasser Construction | $6,753,463 | Low |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. D L Gasser Construction |
|---|---|---|---|---|
| 1 | Debris containment over waterway (structure) 01. B-52-21 (203.0335) | EACH | 1 | $10,000 |
| 2 | Debris containment over waterway (structure) 02. B-52-67 (203.0335) | EACH | 1 | $10,000 |
| 3 | Removing asphaltic surface (204.0110) | SY | 240 | $8.50 |
| 4 | Removing asphaltic surface butt joints (204.0115) | SY | 7,270 | $3.54 |
| 5 | Removing asphaltic surface milling (204.0120) | SY | 167,850 | $1.68 |
| 6 | Removing curb & gutter (204.0150) | LF | 320 | $19.25 |
| 7 | Removing concrete sidewalk (204.0155) | SY | 70 | $50.00 |
| 8 | Removing guardrail (204.0165) | LF | 1,364 | $2.00 |
| 9 | Removing fence (204.0170) | LF | 93 | $7.00 |
| 10 | Removing inlets (204.0220) | EACH | 2 | $500.00 |
| 11 | Removing storm sewer (size) 01. 18-inch (204.0245) | LF | 64 | $15.63 |
| 12 | Excavation common (205.0100) | CY | 1,030 | $20.69 |
| 13 | Prepare foundation for asphaltic paving (project) 01. 5760-00-72 (211.0101) | EACH | 1 | $1.00 |
| 14 | Prepare foundation for asphaltic shoulders (211.0400) | STA | 3 | $1.00 |
| 15 | Finishing roadway (project) 01. 5760-00-72 (213.0100) | EACH | 1 | $1,050.00 |
| 16 | Finishing roadway (project) 02. 5760-00-73 (213.0100) | EACH | 1 | $1,050.00 |
| 17 | Base aggregate dense 3/4-inch (305.0110) | TON | 10,310 | $25.31 |
| 18 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 971 | $19.15 |
| 19 | Mill and relay (330.0100) | SY | 275,650 | $1.67 |
| 20 | QMP mill and relay compaction (374.1010.S) | SY | 174,450 | $0.09 |
| 21 | Tack coat (455.0605) | GAL | 17,314 | $2.20 |
| 22 | HMA percent within limits (PWL) test strip volumetrics (460.0105.S) | EACH | 2 | $11,860 |
| 23 | HMA percent within limits (PWL) test strip density (460.0110.S) | EACH | 6 | $375.00 |
| 24 | Incentive density HMA pavement (460.2000) | DOL | 240 | $1.00 |
| 25 | Incentive density PWL HMA pavement (460.2005) | DOL | 45,200 | $1.00 |
| 26 | Incentive density HMA pavement longitudinal joints (460.2007) | DOL | 24,080 | $1.00 |
| 27 | Incentive air voids HMA pavement (460.2010) | DOL | 49,410 | $1.00 |
| 28 | HMA pavement 4 LT 58-28 S (460.5224) | TON | 50,386 | $72.23 |
| 29 | Asphaltic surface driveways and field entrances (465.0120) | TON | 159 | $203.82 |
| 30 | Asphaltic flumes (465.0315) | SY | 6 | $185.93 |
| 31 | Asphaltic rumble strips, centerline (465.0560) | LF | 84,806 | $0.27 |
| 32 | Protective surface treatment (502.3200) | SY | 436 | $4.50 |
| 33 | Protective surface treatment reseal (502.3215) | SY | 30 | $60.00 |
| 34 | Bar steel reinforcement HS structures (505.0400) | LB | 500 | $4.00 |
| 35 | Preparation decks type 1 (509.0301) | SY | 116 | $220.00 |
| 36 | Preparation decks type 2 (509.0302) | SY | 47 | $260.00 |
| 37 | Sawing pavement deck preparation areas (509.0310.S) | LF | 407 | $6.00 |
| 38 | Cleaning decks (509.0500) | SY | 370 | $15.51 |
| 39 | Curb repair (509.1200) | LF | 58 | $135.00 |
| 40 | Concrete surface repair (509.1500) | SF | 473 | $220.00 |
| 41 | Full-depth deck repair (509.2000) | SY | 3 | $1,600.00 |
| 42 | Concrete masonry deck repair (509.2100.S) | CY | 7 | $1,000.00 |
| 43 | Concrete masonry overlay decks (509.2500) | CY | 25 | $2,400.00 |
| 44 | Removing asphaltic concrete deck overlay (structure) 01. B-52-21 (509.9010.S) | SY | 210 | $5.01 |
| 45 | Removing asphaltic concrete deck overlay (structure) 02. B-52-20 (509.9010.S) | SY | 207 | $5.01 |
| 46 | Sheet membrane waterproofing for asphalt overlays (516.0600.S) | SY | 207 | $115.00 |
| 47 | Structure repainting recycled abrasive (structure) 01. B-52-20 (517.1801.S) | EACH | 1 | $91,250 |
| 48 | Structure overcoating cleaning and priming (structure) 01. B-52-21 (517.3001.S) | EACH | 1 | $56,220 |
| 49 | Containment and collection of waste materials (structure) 01. B- 52-21 (517.4001.S) | EACH | 1 | $28,110 |
| 50 | Negative pressure containment and collection of waste materials (structure) 01. B-52-20 (517.4501.S) | EACH | 1 | $54,750 |
| 51 | Portable decontamination facility (517.6001.S) | EACH | 2 | $2,000.00 |
| 52 | Apron endwalls for culvert pipe 24- inch (520.1024) | EACH | 3 | $725.00 |
| 53 | Culvert pipe class III-A 24-inch (520.3324) | LF | 182 | $46.22 |
| 54 | Apron endwalls for culvert pipe sloped side drains steel 24-inch 6 to 1 (521.1524) | EACH | 1 | $2,278.00 |
| 55 | Apron endwalls for culvert pipe reinforced concrete 24-inch (522.1024) | EACH | 1 | $3,190.00 |
| 56 | Culvert pipe reinforced concrete horizontal elliptical class HE-IV 14X23-inch (522.2414) | LF | 31 | $210.00 |
| 57 | Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 14X23-inch (522.2614) | EACH | 2 | $3,245.00 |
| 58 | Concrete curb & gutter 30-inch type D (601.0411) | LF | 420 | $30.30 |
| 59 | Concrete sidewalk 4-inch (602.0405) | SF | 1,400 | $10.10 |
| 60 | Concrete driveway 6-inch (602.0810) | SY | 54 | $90.90 |
| 61 | Riprap medium (606.0200) | CY | 7 | $61.00 |
| 62 | Storm sewer pipe reinforced concrete class IV 24-inch (608.0424) | LF | 77 | $140.26 |
| 63 | Inlet covers type H (611.0624) | EACH | 1 | $1,100.00 |
| 64 | Inlet covers type H-S (611.0639) | EACH | 1 | $1,100.00 |
| 65 | Inlets 4-FT diameter (611.3004) | EACH | 1 | $3,940.00 |
| 66 | Inlets 2X3-FT (611.3230) | EACH | 1 | $3,781.00 |
| 67 | Barrier system grading shaping finishing (614.0010) | EACH | 12 | $3,624.00 |
| 68 | MGS guardrail 3 (614.2300) | LF | 206 | $26.00 |
| 69 | MGS guardrail 3 HS (614.2310) | LF | 131.50 | $33.00 |
| 70 | MGS thrie beam transition (614.2500) | LF | 465.20 | $87.00 |
| 71 | MGS guardrail terminal eat (614.2610) | EACH | 16 | $3,393.00 |
| 72 | Anchor post assembly top mount (614.8010) | EACH | 16 | $850.00 |
| 73 | Maintenance and repair of haul roads (project) 01. 5760-00-72 (618.0100) | EACH | 1 | $1.00 |
| 74 | Maintenance and repair of haul roads (project) 02. 5760-00-73 (618.0100) | EACH | 1 | $1.00 |
| 75 | Mobilization (619.1000) | EACH | 1 | $189,864 |
| 76 | Water (624.0100) | MGAL | 521.70 | $15.00 |
| 77 | Topsoil (625.0100) | SY | 630 | $2.00 |
| 78 | Silt fence (628.1504) | LF | 4,155 | $1.70 |
| 79 | Silt fence maintenance (628.1520) | LF | 7,572 | $0.03 |
| 80 | Mobilizations erosion control (628.1905) | EACH | 15 | $105.00 |
| 81 | Mobilizations emergency erosion control (628.1910) | EACH | 5 | $205.00 |
| 82 | Erosion mat urban class I type B (628.2008) | SY | 630 | $2.50 |
| 83 | Temporary ditch checks (628.7504) | LF | 8 | $12.00 |
| 84 | Culvert pipe checks (628.7555) | EACH | 18 | $25.00 |
| 85 | Fertilizer type B (629.0210) | CWT | 1 | $200.00 |
| 86 | Seeding mixture no. 40 (630.0140) | LB | 30 | $15.25 |
| 87 | Seeding temporary (630.0200) | LB | 18 | $7.85 |
| 88 | Seed water (630.0500) | MGAL | 16 | $40.00 |
| 89 | Markers culvert end (633.5200) | EACH | 3 | $75.00 |
| 90 | Posts wood 4X6-inch X 12-FT (634.0612) | EACH | 11 | $95.00 |
| 91 | Posts wood 4X6-inch X 14-FT (634.0614) | EACH | 4 | $99.00 |
| 92 | Posts wood 4X6-inch X 16-FT (634.0616) | EACH | 1 | $115.00 |
| 93 | Signs type II reflective H (637.2210) | SF | 13.18 | $50.00 |
| 94 | Signs type II reflective F (637.2230) | SF | 5.56 | $50.00 |
| 95 | Moving signs type II (638.2102) | EACH | 17 | $125.00 |
| 96 | Removing signs type II (638.2602) | EACH | 4 | $35.00 |
| 97 | Removing small sign supports (638.3000) | EACH | 4 | $35.00 |
| 98 | Field office type C (642.5201) | EACH | 1 | $39,320 |
| 99 | Traffic control drums (643.0300) | DAY | 1,154 | $0.66 |
| 100 | Traffic control barricades type III (643.0420) | DAY | 5,732 | $0.79 |
| 101 | Traffic control warning lights type A (643.0705) | DAY | 8,604 | $0.25 |
| 102 | Traffic control signs (643.0900) | DAY | 33,354 | $0.62 |
| 103 | Traffic control covering signs type II (643.0920) | EACH | 15 | $160.94 |
| 104 | Traffic control signs PCMS (643.1050) | DAY | 14 | $62.13 |
| 105 | Temporary marking line paint 6- inch (643.3165) | LF | 275,603 | $0.15 |
| 106 | Traffic control (643.5000) | EACH | 1 | $23,542 |
| 107 | Geotextile type R (645.0130) | SY | 14 | $28.57 |
| 108 | Marking line grooved wet ref epoxy 6-inch (646.2040) | LF | 330,889 | $1.12 |
| 109 | Marking line same day epoxy 6- inch (646.4720) | LF | 45,065 | $0.95 |
| 110 | Marking stop line epoxy 18-inch (646.6120) | LF | 81 | $16.00 |
| 111 | Locating no-passing zones (648.0100) | MI | 17.52 | $370.00 |
| 112 | Construction staking storm sewer (650.4000) | EACH | 3 | $300.00 |
| 113 | Construction staking subgrade (650.4500) | LF | 430 | $0.01 |
| 114 | Construction staking base (650.5000) | LF | 430 | $1.50 |
| 115 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 420 | $2.00 |
| 116 | Construction staking pipe culverts (650.6000) | EACH | 2 | $400.00 |
| 117 | Construction staking resurfacing reference (650.8000) | LF | 92,147 | $0.24 |
| 118 | Construction staking sidewalk (project) 01. 5760-00-72 (650.9500) | EACH | 1 | $1,200.00 |
| 119 | Construction staking supplemental control (project) 01. 5760-00-72 (650.9911) | EACH | 1 | $1,000.00 |
| 120 | Construction staking supplemental control (project) 02. 5760-00-73 (650.9911) | EACH | 1 | $1,000.00 |
| 121 | Construction staking slope stakes (650.9920) | LF | 575 | $1.50 |
| 122 | Public land reference monument verify and reset (680.0100) | EACH | 4 | $1,200.00 |
| 123 | Sawing asphalt (690.0150) | LF | 1,749 | $1.86 |
| 124 | Sawing concrete (690.0250) | LF | 120 | $3.96 |
| 125 | Incentive iri ride (740.0440) | DOL | 70,106 | $1.00 |
| 126 | Installing and maintaining bird deterrent system (station) 01. 29+86 (999.2000.S) | EACH | 1 | $1,000.00 |
| 127 | Installing and maintaining bird deterrent system (station) 02. 289+40 (999.2000.S) | EACH | 1 | $1,000.00 |
| 128 | Installing and maintaining bird deterrent system (station) 03. 357+47 (999.2000.S) | EACH | 1 | $1,000.00 |
| 129 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 2,500 | $5.00 |
| 130 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 3,520 | $5.00 |
| 131 | Special 01. steel thrie beam railing retrofit (SPV.0090) | LF | 146 | $125.00 |
| 132 | Special 02. removing and replacing modular block retaining wall cap blocks (SPV.0090) | LF | 216 | $23.00 |
| 133 | Special 03. remove and RE-install W-rail and timber rail post B-52- 20 (SPV.0090) | LF | 146 | $40.00 |
| 134 | Special 04. flashing stainless steel (SPV.0090) | LF | 198 | $60.00 |
| 135 | Special 01. salvaged asphaltic pavement base (SPV.0195) | TON | 2,750 | $20.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of January 13, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.