WisDOT contract 20260113022 bid tabulation
Silvernail Frontage Road; Maple Avenue to Elmhurst Road (OFF SYS, Waukesha County Silvernail Frontage Road). Let by Wisconsin DOT on January 13, 2026, Waukesha. 7 bids received; low bid $2,043,973 by Payne and Dolan, Inc.
- Owner
- Wisconsin DOT
- Letting
- 13 JAN 2026
- Pay items
- 86
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Payne and Dolan, Inc | $2,043,973 | Low |
| 2 | Super Western, Inc. | $2,114,211 | +3.0% |
| 3 | Michels Road & Stone, Inc. | $2,140,394 | +5.0% |
| 4 | Vinton Construction Company | $2,271,668 | +11% |
| 5 | Rock Road Companies, Inc. | $2,344,892 | +15% |
| 6 | James Peterson Sons, Inc. | $2,445,093 | +20% |
| 7 | Musson Bros., Inc. | $2,580,152 | +26% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Payne and Dolan, Inc | 2. Super Western, Inc. | 3. Michels Road & Stone, Inc. | 4. Vinton Construction Company | 5. Rock Road Companies, Inc. | 6. James Peterson Sons, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing (201.0105) | STA | 11 | $252.53 | $250.00 | $250.00 | $250.00 | $250.00 | $250.00 |
| 2 | Clearing (201.0120) | ID | 67 | $50.51 | $50.00 | $50.00 | $50.00 | $50.00 | $50.00 |
| 3 | Grubbing (201.0205) | STA | 11 | $55.56 | $55.00 | $55.00 | $55.00 | $55.00 | $55.00 |
| 4 | Grubbing (201.0220) | ID | 67 | $15.15 | $15.00 | $15.00 | $15.00 | $15.00 | $15.00 |
| 5 | Removing small pipe culverts (203.0100) | EACH | 6 | $617.05 | $900.00 | $600.00 | $640.00 | $1,313.84 | $855.00 |
| 6 | Removing asphaltic surface milling (204.0120) | SY | 1,400 | $5.00 | $5.00 | $5.00 | $5.00 | $7.31 | $5.00 |
| 7 | Removing curb (204.0130) | LF | 42 | $9.79 | $8.90 | $10.00 | $10.00 | $6.06 | $20.00 |
| 8 | Removing guardrail (204.0165) | LF | 476 | $4.00 | $4.00 | $4.00 | $4.00 | $4.00 | $4.00 |
| 9 | Removing fence (204.0170) | LF | 2,962 | $1.50 | $1.50 | $1.50 | $1.50 | $1.50 | $1.50 |
| 10 | Excavation common (205.0100) | CY | 26,389 | $16.51 | $16.07 | $13.00 | $17.75 | $20.54 | $22.90 |
| 11 | Finishing roadway (project) .01 2717-03-71 (213.0100) | EACH | 1 | $3,226.76 | $3,000.00 | $5,000.00 | $2,000.00 | $5,893.67 | $2,500.00 |
| 12 | Base aggregate dense 3/4-inch (305.0110) | TON | 1,280 | $24.66 | $25.16 | $22.70 | $27.00 | $22.83 | $28.00 |
| 13 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 14,650 | $14.57 | $14.21 | $10.90 | $13.50 | $10.01 | $19.00 |
| 14 | Select crushed material (312.0110) | TON | 27,425 | $13.93 | $15.37 | $17.30 | $18.80 | $19.98 | $17.95 |
| 15 | QMP base aggregate dense 1 1/4- inch compaction (371.2000.S) | EACH | 16 | $750.00 | $500.00 | $750.00 | $750.00 | $400.00 | $600.00 |
| 16 | Drilled tie bars (416.0610) | EACH | 25 | $50.00 | $50.00 | $50.00 | $50.00 | $50.00 | $50.00 |
| 17 | Tack coat (455.0605) | GAL | 1,400 | $2.50 | $2.50 | $2.50 | $2.50 | $3.43 | $2.50 |
| 18 | Incentive density HMA pavement (460.2000) | DOL | 4,610 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 19 | HMA pavement 3 LT 58-28 S (460.5223) | TON | 4,200 | $57.45 | $57.45 | $57.45 | $57.45 | $64.59 | $57.45 |
| 20 | HMA pavement 4 LT 58-28 H (460.5424) | TON | 3,000 | $67.45 | $67.45 | $67.45 | $67.45 | $78.17 | $67.45 |
| 21 | Asphaltic surface driveways and field entrances (465.0120) | TON | 110 | $67.45 | $67.45 | $67.45 | $67.45 | $143.12 | $67.45 |
| 22 | Concrete masonry endwalls (504.0900) | CY | 11 | $2,675.00 | $2,675.00 | $2,675.00 | $3,045.00 | $2,675.00 | $3,675.00 |
| 23 | Concrete collars for pipe (520.8000) | EACH | 2 | $490.81 | $728.00 | $1,500.00 | $950.00 | $1,267.34 | $1,000.00 |
| 24 | Apron endwalls for culvert pipe steel 18-inch (521.1018) | EACH | 6 | $379.72 | $868.00 | $580.00 | $409.00 | $773.99 | $350.00 |
| 25 | Culvert pipe corrugated steel 18- inch (521.3118) | LF | 114 | $78.15 | $118.00 | $82.00 | $116.00 | $121.44 | $85.00 |
| 26 | Culvert pipe reinforced concrete class IV 36-inch (522.0436) | LF | 153 | $160.26 | $217.00 | $278.00 | $265.00 | $259.12 | $309.00 |
| 27 | Culvert pipe reinforced concrete horizontal elliptical class HE-IV 29X45-inch (522.2429) | LF | 75 | $314.36 | $338.00 | $314.00 | $323.00 | $310.29 | $385.00 |
| 28 | Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 29X45-inch (522.2629) | EACH | 1 | $2,575.85 | $3,904.00 | $2,600.00 | $4,052.00 | $3,072.57 | $2,750.00 |
| 29 | Concrete curb type D (601.0110) | LF | 42 | $85.00 | $69.94 | $69.94 | $100.00 | $69.94 | $69.94 |
| 30 | Guardrail mow strip emulsified asphalt (614.0397) | SY | 390 | $8.85 | $8.85 | $8.85 | $8.85 | $15.00 | $8.85 |
| 31 | MGS guardrail 3 (614.2300) | LF | 887.50 | $26.50 | $26.50 | $26.50 | $26.50 | $26.50 | $26.50 |
| 32 | MGS guardrail terminal eat (614.2610) | EACH | 2 | $4,426.91 | $3,900.00 | $3,900.00 | $3,900.00 | $3,900.00 | $3,900.00 |
| 33 | Fence woven wire (height) .01 4 feet (616.0100) | LF | 2,962 | $7.50 | $7.50 | $7.50 | $7.50 | $7.50 | $7.50 |
| 34 | Maintenance and repair of haul roads (project) .01 2717-03-71 (618.0100) | EACH | 1 | $500.00 | $1.00 | $0.01 | $0.01 | $0.01 | $100.00 |
| 35 | Mobilization (619.1000) | EACH | 1 | $56,000 | $92,173 | $200,530 | $118,000 | $146,000 | $81,300 |
| 36 | Water (624.0100) | MGAL | 320 | $1.00 | $14.45 | $50.00 | $0.01 | $0.01 | $20.00 |
| 37 | Topsoil (625.0100) | SY | 20,425 | $3.65 | $3.59 | $2.10 | $5.35 | $0.01 | $2.80 |
| 38 | Mulching (627.0200) | SY | 20,425 | $0.35 | $0.35 | $0.35 | $0.01 | $0.35 | $0.35 |
| 39 | Erosion bales (628.1104) | EACH | 25 | $12.50 | $12.50 | $12.50 | $12.50 | $12.50 | $12.50 |
| 40 | Silt fence (628.1504) | LF | 250 | $3.00 | $4.25 | $3.00 | $3.00 | $3.00 | $3.00 |
| 41 | Silt fence maintenance (628.1520) | LF | 250 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 |
| 42 | Mobilizations erosion control (628.1905) | EACH | 12 | $100.00 | $100.00 | $100.00 | $100.00 | $100.00 | $100.00 |
| 43 | Mobilizations emergency erosion control (628.1910) | EACH | 6 | $100.00 | $100.00 | $100.00 | $100.00 | $100.00 | $100.00 |
| 44 | Erosion mat urban class I type B (628.2008) | SY | 20,425 | $1.60 | $1.60 | $1.60 | $0.01 | $1.60 | $1.60 |
| 45 | Inlet protection type B (628.7010) | EACH | 3 | $75.00 | $75.00 | $75.00 | $75.00 | $75.00 | $75.00 |
| 46 | Temporary ditch checks (628.7504) | LF | 525 | $8.50 | $8.50 | $8.50 | $8.50 | $8.50 | $8.50 |
| 47 | Culvert pipe checks (628.7555) | EACH | 75 | $19.00 | $19.00 | $19.00 | $19.00 | $19.00 | $19.00 |
| 48 | Tracking pads (628.7560) | EACH | 2 | $0.01 | $1.00 | $1,600.00 | $0.01 | $900.00 | $2,500.00 |
| 49 | Fertilizer type B (629.0210) | CWT | 13 | $85.00 | $85.00 | $85.00 | $85.00 | $85.00 | $85.00 |
| 50 | Seeding mixture no. 30 (630.0130) | LB | 925 | $9.25 | $9.25 | $9.25 | $9.25 | $9.25 | $9.25 |
| 51 | Seeding temporary (630.0200) | LB | 563 | $3.65 | $3.65 | $3.65 | $3.65 | $3.65 | $3.65 |
| 52 | Seed water (630.0500) | MGAL | 463 | $10.00 | $10.00 | $10.00 | $10.00 | $10.00 | $10.00 |
| 53 | Sod water (631.0300) | MGAL | 1 | $300.00 | $300.00 | $300.00 | $300.00 | $300.00 | $300.00 |
| 54 | Sod lawn (631.1000) | SY | 39 | $20.00 | $20.00 | $20.00 | $20.00 | $20.00 | $20.00 |
| 55 | Markers culvert end (633.5200) | EACH | 4 | $69.00 | $69.00 | $69.00 | $69.00 | $69.00 | $69.00 |
| 56 | Posts wood 4X6-inch X 18-FT (634.0618) | EACH | 37 | $95.00 | $95.00 | $95.00 | $95.00 | $95.00 | $95.00 |
| 57 | Signs type II reflective H (637.2210) | SF | 132.40 | $20.00 | $20.00 | $20.00 | $20.00 | $20.00 | $20.00 |
| 58 | Signs type II reflective F (637.2230) | SF | 91.81 | $21.00 | $21.00 | $21.00 | $21.00 | $21.00 | $21.00 |
| 59 | Moving signs type II (638.2102) | EACH | 11 | $200.00 | $200.00 | $200.00 | $200.00 | $200.00 | $200.00 |
| 60 | Removing signs type II (638.2602) | EACH | 21 | $35.00 | $35.00 | $35.00 | $35.00 | $35.00 | $35.00 |
| 61 | Removing small sign supports (638.3000) | EACH | 28 | $35.00 | $35.00 | $35.00 | $35.00 | $35.00 | $35.00 |
| 62 | Field office type D (642.5401) | EACH | 1 | $22,000 | $13,823 | $18,500 | $10,000 | $7,800.00 | $18,000 |
| 63 | Traffic control drums (643.0300) | DAY | 10,500 | $0.23 | $0.23 | $0.23 | $0.23 | $0.23 | $0.23 |
| 64 | Traffic control barricades type III (643.0420) | DAY | 1,260 | $0.78 | $0.78 | $0.78 | $0.78 | $0.78 | $0.78 |
| 65 | Traffic control warning lights type A (643.0705) | DAY | 2,520 | $0.18 | $0.18 | $0.18 | $0.18 | $0.18 | $0.18 |
| 66 | Traffic control connected arrow boards (643.0810) | DAY | 210 | $10.02 | $10.02 | $10.02 | $10.02 | $10.02 | $10.02 |
| 67 | Traffic control signs (643.0900) | DAY | 25,830 | $0.36 | $0.36 | $0.36 | $0.36 | $0.36 | $0.36 |
| 68 | Traffic control signs fixed message (643.1000) | SF | 150 | $19.00 | $19.00 | $19.00 | $19.00 | $19.00 | $19.00 |
| 69 | Traffic control (643.5000) | EACH | 1 | $3,476.41 | $3,476.41 | $3,476.41 | $3,476.41 | $3,476.41 | $3,476.41 |
| 70 | Marking line epoxy 4-inch (646.1020) | LF | 394 | $3.54 | $3.50 | $3.50 | $3.50 | $3.50 | $3.50 |
| 71 | Marking line grooved wet ref epoxy 6-inch (646.2040) | LF | 17,674 | $1.41 | $1.40 | $1.40 | $1.40 | $1.40 | $1.40 |
| 72 | Marking line grooved wet ref epoxy 10-inch (646.4040) | LF | 80 | $3.03 | $3.00 | $3.00 | $3.00 | $3.00 | $3.00 |
| 73 | Marking stop line epoxy 18-inch (646.6120) | LF | 231 | $15.91 | $15.75 | $15.75 | $15.75 | $15.75 | $15.75 |
| 74 | Marking diagonal epoxy 12-inch (646.7120) | LF | 41 | $10.61 | $10.50 | $10.50 | $10.50 | $10.50 | $10.50 |
| 75 | Locating no-passing zones (648.0100) | MI | 1.25 | $909.09 | $900.00 | $900.00 | $900.00 | $900.00 | $900.00 |
| 76 | Construction staking subgrade (650.4500) | LF | 6,572 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 |
| 77 | Construction staking base (650.5000) | LF | 6,572 | $1.20 | $1.20 | $0.75 | $0.75 | $0.01 | $1.20 |
| 78 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 42 | $1.25 | $1.25 | $20.00 | $20.00 | $1.00 | $1.25 |
| 79 | Construction staking pipe culverts (650.6000) | EACH | 3 | $150.00 | $150.00 | $700.00 | $700.00 | $10.00 | $150.00 |
| 80 | Construction staking supplemental control (project) .01 2717-03-71 (650.9911) | EACH | 1 | $2,500.00 | $2,500.00 | $6,500.00 | $6,500.00 | $7,500.00 | $3,000.00 |
| 81 | Construction staking slope stakes (650.9920) | LF | 6,572 | $0.75 | $0.75 | $0.80 | $0.80 | $0.40 | $0.75 |
| 82 | Sawing asphalt (690.0150) | LF | 590 | $1.39 | $2.86 | $1.39 | $1.39 | $1.39 | $2.00 |
| 83 | Sawing concrete (690.0250) | LF | 33 | $2.25 | $4.77 | $2.25 | $2.25 | $10.00 | $3.00 |
| 84 | Incentive iri ride (740.0440) | DOL | 4,926 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 85 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 1,800 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 |
| 86 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 2,100 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of January 13, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.