WisDOT contract 20260210005 bid tabulation

Cobb - Avoca; CTH I to STH 133 (STH 080, Iowa County Cobb - Avoca). Let by Wisconsin DOT on February 10, 2026, Iowa. 1 bid received; low bid $3,123,752 by Iverson Construction, A Div. of Mathy Co.

Owner
Wisconsin DOT
Letting
10 FEB 2026
Pay items
102
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Iverson Construction, A Div. of Mathy Co$3,123,752Low
WisDOT contract 20260210005: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Iverson Construction, A Div. of Mathy Co
1Removing structure over waterway remove debris (structure) 01. B-25- 176 (203.0250)EACH1$20,700
2Removing asphaltic surface (204.0110)SY330$10.00
3Removing asphaltic surface butt joints (204.0115)SY513$7.31
4Removing asphaltic surface milling (204.0120)SY140,017$1.94
5Removing guardrail (204.0165)LF661$3.00
6Excavation common (205.0100)CY1,835$15.25
7Excavation for structures bridges (structure) 01. B-25-194 (206.1001)EACH1$16,300
8Backfill structure type A (210.1500)TON95$33.00
9Prepare foundation for asphaltic paving (project) 01. 5939-00-63 (211.0101)EACH1$16,459
10Prepare foundation for asphaltic shoulders (211.0400)STA418$77.23
11Finishing roadway (project) 01. 5939-00-63 (213.0100)EACH1$500.00
12Base aggregate dense 3/4-inch (305.0110)TON1,292$41.00
13Base aggregate dense 1 1/4-inch (305.0120)TON1,374$21.25
14Select crushed material (312.0110)TON1,653$19.70
15Concrete pavement 6-inch (415.0060)SY6$100.00
16Drilled tie bars (416.0610)EACH6$15.00
17Tack coat (455.0605)GAL10,444$3.30
18HMA percent within limits (PWL) test strip volumetrics (460.0105.S)EACH1$3,845.00
19HMA percent within limits (PWL) test strip density (460.0110.S)EACH1$3,845.00
20Incentive density HMA pavement (460.2000)DOL2,940$1.00
21Incentive density PWL HMA pavement (460.2005)DOL13,430$1.00
22Incentive density HMA pavement longitudinal joints (460.2007)DOL23,300$1.00
23Incentive air voids HMA pavement (460.2010)DOL16,370$1.00
24HMA pavement 4 LT 58-28 S (460.5224)TON16,941$81.30
25Asphaltic surface (465.0105)TON1,032$94.85
26Asphaltic surface driveways and field entrances (465.0120)TON70$119.15
27Asphaltic rumble strips, shoulder (465.0520)LF39,775$0.16
28Asphaltic rumble strips, centerline (465.0560)LF35,772$0.14
29Concrete masonry bridges (502.0100)CY170$850.00
30Protective surface treatment (502.3200)SY136$4.80
31Pigmented surface sealer (502.3210)SY50$15.00
32Bar steel reinforcement HS structures (505.0400)LB3,080$1.15
33Bar steel reinforcement HS coated structures (505.0600)LB27,500$1.15
34Rubberized membrane waterproofing (516.0500)SY18$61.00
35Apron endwalls for pipe arch sloped side drains steel 21X15- inch 10 to 1 (521.1821)EACH1$2,200.00
36Pile points (550.0500)EACH14$100.00
37Piling steel HP 12-inch X 53 LB (550.1120)LF1,330$19.00
38Concrete curb & gutter 4-inch sloped 36-inch type TBT (601.0588)LF126$50.00
39Concrete surface drains (602.3010)CY4$1,000.00
40Riprap medium (606.0200)CY6$90.00
41Riprap heavy (606.0300)CY137$65.00
42Pipe underdrain wrapped 6-inch (612.0406)LF162$6.40
43Anchor assemblies for steel plate beam guard (614.0150)EACH4$330.00
44MGS guardrail 3 (614.2300)LF225$25.00
45MGS thrie beam transition (614.2500)LF157.60$92.00
46MGS guardrail terminal eat (614.2610)EACH4$3,835.00
47Maintenance and repair of haul roads (project) 01. 5939-00-63 (618.0100)EACH1$1,000.00
48Mobilization (619.1000)EACH1$306,695
49Water (624.0100)MGAL40$105.00
50Salvaged topsoil (625.0500)SY2,055$3.50
51Silt fence (628.1504)LF1,337$2.20
52Silt fence maintenance (628.1520)LF1,337$0.01
53Mobilizations erosion control (628.1905)EACH3$500.00
54Mobilizations emergency erosion control (628.1910)EACH3$250.00
55Erosion mat class I type B (628.2004)SY1,407$1.35
56Erosion mat urban class I type A (628.2006)SY648$2.00
57Turbidity barriers (628.6005)SY222$43.00
58Temporary ditch checks (628.7504)LF90$8.00
59Rock bags (628.7570)EACH75$14.00
60Fertilizer type B (629.0210)CWT1.33$100.00
61Seeding mixture no. 20 (630.0120)LB66$8.00
62Seeding mixture no. 40 (630.0140)LB28.90$13.80
63Seeding temporary (630.0200)LB55.20$3.55
64Seed water (630.0500)MGAL95$1.00
65Posts wood 4X6-inch X 12-FT (634.0612)EACH4$80.00
66Posts wood 4X6-inch X 16-FT (634.0616)EACH16$85.00
67Signs type II reflective F (637.2230)SF12$22.00
68Moving signs type II (638.2102)EACH16$110.00
69Removing signs type II (638.2602)EACH4$20.00
70Removing small sign supports (638.3000)EACH20$20.00
71Field office type B (642.5001)EACH1$11,400
72Traffic control drums (643.0300)DAY100$5.00
73Traffic control barricades type III (643.0420)DAY3,600$1.00
74Traffic control warning lights type A (643.0705)DAY6,560$0.25
75Traffic control signs (643.0900)DAY27,840$0.25
76Traffic control covering signs type II (643.0920)EACH12$25.00
77Traffic control signs PCMS (643.1050)DAY14$85.00
78Temporary marking line paint 6- inch (643.3165)LF142,030$0.20
79Traffic control (643.5000)EACH1$12,000
80Geotextile type DF schedule A (645.0111)SY54$5.30
81Geotextile type HR (645.0120)SY330$6.60
82Marking line epoxy 4-inch (646.1020)LF281$1.45
83Marking line grooved wet ref epoxy 6-inch (646.2040)LF163,687$1.17
84Marking line epoxy 10-inch (646.4020)LF546$1.30
85Marking stop line epoxy 18-inch (646.6120)LF106$17.00
86Locating no-passing zones (648.0100)MI8.83$360.00
87Construction staking subgrade (650.4500)LF705$0.01
88Construction staking base (650.5000)LF705$1.40
89Construction staking curb gutter and curb & gutter (650.5500)LF126$4.00
90Construction staking structure layout (structure) 01. B-25-194 (650.6501)EACH1$1,500.00
91Construction staking resurfacing reference (650.8000)LF46,116$0.13
92Construction staking supplemental control (project) 01. 5939-00-63 (650.9911)EACH1$1,000.00
93Construction staking slope stakes (650.9920)LF705$1.50
94Public land reference monument verify and reset (680.0100)EACH2$1,000.00
95Sawing asphalt (690.0150)LF404$1.84
96Incentive strength concrete structures (715.0502)DOL1,021$1.00
97Incentive iri ride (740.0440)DOL35,303$1.00
98Installing and maintaining bird deterrent system (station) 01. 568+80 (999.2000.S)EACH1$0.01
99On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS2,000$5.00
100On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS1,320$5.00
101Special 01. removing distressed pavement milling (SPV.0180)SY1,401$5.75
102Special 02. resin binder high friction surface treatment (SPV.0180)SY2,677$23.69
WisDOT contract 20260210005: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of February 10, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy