WisDOT contract 20260512009 bid tabulation
Division Rd Wetland Mitigation Site; Cedar Lane to Spring Valley Road (NON HWY, Washington County Division Rd Wetland Mitigation Site). Let by Wisconsin DOT on May 12, 2026, Washington. 3 bids received; low bid $999,951 by Mashuda Contractors, Inc..
- Owner
- Wisconsin DOT
- Letting
- 12 MAY 2026
- Pay items
- 36
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Mashuda Contractors, Inc. | $999,951 | Low |
| 2 | Super Western, Inc. | $1,044,168 | +4.0% |
| 3 | Musson Bros., Inc. | $1,282,943 | +28% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Mashuda Contractors, Inc. | 2. Super Western, Inc. | 3. Musson Bros., Inc. |
|---|---|---|---|---|---|---|
| 1 | Clearing (201.0115) | ACRE | 6.80 | $4,009.00 | $4,009.00 | $4,009.00 |
| 2 | Grubbing (201.0215) | ACRE | 6.80 | $1,055.00 | $1,055.00 | $1,055.00 |
| 3 | Removing small pipe culverts (203.0100) | EACH | 6 | $500.00 | $398.73 | $196.28 |
| 4 | Excavation common (205.0100) | CY | 49,000 | $9.21 | $8.38 | $8.72 |
| 5 | Apron endwalls for culvert pipe steel 12-inch (521.1012) | EACH | 2 | $461.00 | $956.00 | $400.02 |
| 6 | Culvert pipe corrugated steel 12- inch (521.3112) | LF | 19 | $126.00 | $88.00 | $103.43 |
| 7 | Riprap medium (606.0200) | CY | 143 | $160.00 | $138.29 | $137.13 |
| 8 | Fence temporary (616.0600.S) | LF | 2,674 | $4.00 | $15.00 | $4.00 |
| 9 | Maintenance and repair of haul roads (project) 01. 1009-23-72 (618.0100) | EACH | 1 | $1.00 | $1.00 | $100.00 |
| 10 | Mobilization (619.1000) | EACH | 1 | $64,378 | $222,248 | $235,851 |
| 11 | Salvaged topsoil (625.0500) | SY | 32,100 | $1.25 | $4.90 | $1.12 |
| 12 | Mulching (627.0200) | SY | 12,900 | $0.60 | $0.30 | $0.60 |
| 13 | Silt fence (628.1504) | LF | 8,426 | $1.70 | $1.90 | $1.70 |
| 14 | Silt fence maintenance (628.1520) | LF | 8,426 | $0.10 | $0.01 | $0.10 |
| 15 | Mobilizations erosion control (628.1905) | EACH | 2 | $250.00 | $100.00 | $250.00 |
| 16 | Mobilizations emergency erosion control (628.1910) | EACH | 3 | $125.00 | $100.00 | $125.00 |
| 17 | Temporary ditch checks (628.7504) | LF | 920 | $9.20 | $7.00 | $9.20 |
| 18 | Culvert pipe checks (628.7555) | EACH | 1 | $65.00 | $20.00 | $65.00 |
| 19 | Tracking pads (628.7560) | EACH | 3 | $3,500.00 | $1.00 | $100.00 |
| 20 | Field office type C (642.5201) | EACH | 1 | $10,500 | $11,587 | $12,500 |
| 21 | Traffic control barricades type III (643.0420) | DAY | 184 | $0.50 | $0.50 | $0.50 |
| 22 | Traffic control signs (643.0900) | DAY | 828 | $0.50 | $0.50 | $0.50 |
| 23 | Traffic control (643.5000) | EACH | 1 | $1,650.00 | $1,650.00 | $1,650.00 |
| 24 | Geotextile type HR (645.0120) | SY | 219 | $10.00 | $7.44 | $4.77 |
| 25 | Construction staking pipe culverts (650.6000) | EACH | 1 | $750.00 | $1,000.00 | $1,000.00 |
| 26 | Construction staking supplemental control (project) 01. 1009-23-72 (650.9911) | EACH | 1 | $1,250.00 | $4,000.00 | $1,500.00 |
| 27 | Special 01. clay borrow material (SPV.0035) | CY | 102 | $95.00 | $21.04 | $59.09 |
| 28 | Special 02. removal of unsuitable materials (SPV.0035) | CY | 40 | $100.00 | $34.43 | $241.17 |
| 29 | Special 01. construction staking wetland site (SPV.0060) | EACH | 1 | $4,577.00 | $5,000.00 | $4,577.00 |
| 30 | Special 01. seeding temporary (SPV.0085) | LB | 9,800 | $5.18 | $1.00 | $5.18 |
| 31 | Special 02. wetland meadow native seeding mixture A (SPV.0085) | LB | 650 | $186.19 | $15.00 | $186.19 |
| 32 | Special 03. wooded swamp/shrub swamp native seeding mixture B (SPV.0085) | LB | 111 | $230.28 | $20.00 | $230.28 |
| 33 | Special 04. upland buffer prairie native seeding mixture C (SPV.0085) | LB | 9 | $299.02 | $50.00 | $299.02 |
| 34 | Special 05. upland buffer forest native seeding mixture D (SPV.0085) | LB | 9 | $325.97 | $50.00 | $325.97 |
| 35 | Special 06. wetland meadow no credit areas native seeding mixture E (SPV.0085) | LB | 37 | $178.79 | $50.00 | $178.79 |
| 36 | Special 01. microtopography grading (SPV.0180) | SY | 178,950 | $0.46 | $0.41 | $1.31 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of May 12, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.