WisDOT contract 20260512011 bid tabulation
Oshkosh - Green Bay; USH 45 - IH 43 (IH 041, Brown and Winnebago Counties Oshkosh - Green Bay). Let by Wisconsin DOT on May 12, 2026, Brown. 3 bids received; low bid $6,868,868 by Truesdell Corporation of Wisconsin, Inc..
- Owner
- Wisconsin DOT
- Letting
- 12 MAY 2026
- Pay items
- 42
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Truesdell Corporation of Wisconsin, Inc. | $6,868,868 | Low |
| 2 | Myers & Sons Construction, LLC | $7,505,687 | +9.0% |
| 3 | American Civil Constructors West Coast L | $7,953,000 | +16% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Truesdell Corporation of Wisconsin, Inc. | 2. Myers & Sons Construction, LLC | 3. American Civil Constructors West Coast L |
|---|---|---|---|---|---|---|
| 1 | Preparation decks type 1 (509.0301) | SY | 7 | $1,250.00 | $6,700.00 | $3,000.00 |
| 2 | Preparation decks type 2 (509.0302) | SY | 7 | $1,450.00 | $7,400.00 | $4,500.00 |
| 3 | Sawing pavement deck preparation areas (509.0310.S) | LF | 70 | $20.00 | $120.26 | $50.00 |
| 4 | Cleaning decks (509.0500) | SY | 61,336 | $7.25 | $10.17 | $10.00 |
| 5 | Concrete surface repair (509.1500) | SF | 1 | $2,500.00 | $2,000.00 | $4,000.00 |
| 6 | Polymer overlay (509.5100.S) | SY | 3,685 | $38.00 | $36.88 | $35.00 |
| 7 | Removing polymer overlay (structure) 01. B-05-658 (509.9015.S) | SY | 7,811 | $0.85 | $0.80 | $5.50 |
| 8 | Removing polymer overlay (structure) 02. B-05-660 (509.9015.S) | SY | 12,500 | $0.85 | $0.80 | $4.75 |
| 9 | Removing polymer overlay (structure) 03. B-05-661 (509.9015.S) | SY | 1,386 | $0.85 | $0.80 | $15.00 |
| 10 | Removing polymer overlay (structure) 04. B-05-671 (509.9015.S) | SY | 10,859 | $0.85 | $0.80 | $5.25 |
| 11 | Removing polymer overlay (structure) 05. B-05-678 (509.9015.S) | SY | 18,580 | $0.85 | $0.80 | $4.25 |
| 12 | Removing polymer overlay (structure) 06. B-05-679 (509.9015.S) | SY | 10,200 | $0.85 | $0.80 | $5.25 |
| 13 | Removing polymer overlay (structure) 07. B-70-269 (509.9015.S) | SY | 3,685 | $9.50 | $7.00 | $13.00 |
| 14 | Maintenance and repair of haul roads (project) 01. 1130-73-71 (618.0100) | EACH | 1 | $2,500.00 | $10,000 | $19,141 |
| 15 | Mobilization (619.1000) | EACH | 1 | $523,518 | $700,000 | $756,000 |
| 16 | Mobilizations erosion control (628.1905) | EACH | 7 | $160.00 | $150.00 | $150.00 |
| 17 | Mobilizations emergency erosion control (628.1910) | EACH | 7 | $110.00 | $100.00 | $100.00 |
| 18 | Inlet protection type C (628.7015) | EACH | 75 | $75.00 | $72.00 | $72.00 |
| 19 | Field office type B (642.5001) | EACH | 1 | $8,800.00 | $23,000 | $50,000 |
| 20 | Traffic control drums (643.0300) | DAY | 10,739 | $0.25 | $0.20 | $0.20 |
| 21 | Traffic control barricades type III (643.0420) | DAY | 540 | $1.00 | $0.75 | $0.75 |
| 22 | Traffic control warning lights type A (643.0705) | DAY | 982 | $0.50 | $0.25 | $0.25 |
| 23 | Traffic control warning lights type C (643.0715) | DAY | 3,004 | $0.50 | $0.25 | $0.25 |
| 24 | Traffic control connected arrow boards (643.0810) | DAY | 188 | $10.00 | $9.60 | $9.60 |
| 25 | Traffic control signs (643.0900) | DAY | 4,282 | $0.50 | $0.22 | $0.22 |
| 26 | Traffic control covering signs type I (643.0910) | EACH | 2 | $800.00 | $750.00 | $750.00 |
| 27 | Traffic control covering signs type II (643.0920) | EACH | 6 | $200.00 | $150.00 | $150.00 |
| 28 | Traffic control signs fixed message (643.1000) | SF | 162 | $46.00 | $45.00 | $45.00 |
| 29 | Traffic control signs PCMS (643.1050) | DAY | 63 | $26.00 | $25.00 | $25.00 |
| 30 | Traffic control cones 42-inch (643.1070) | DAY | 7,266 | $0.25 | $0.20 | $0.20 |
| 31 | Basic traffic queue warning system (643.1205.S) | DAY | 85 | $240.00 | $230.00 | $230.00 |
| 32 | Traffic control connected work zone start and end location markers (643.1220) | DAY | 188 | $5.00 | $4.25 | $4.25 |
| 33 | Temporary marking line paint 6- inch (643.3165) | LF | 9,525 | $0.50 | $0.40 | $0.40 |
| 34 | Temporary marking line removable tape 6-inch (643.3180) | LF | 19,811 | $1.90 | $1.85 | $1.85 |
| 35 | Traffic control (643.5000) | EACH | 1 | $70,000 | $87,885 | $120,000 |
| 36 | Marking line epoxy 6-inch (646.2020) | LF | 32,619 | $0.60 | $0.56 | $0.56 |
| 37 | Marking line epoxy 10-inch (646.4020) | LF | 1,064 | $2.00 | $1.50 | $1.50 |
| 38 | Marking removal line 4-inch (646.9000) | LF | 11,012 | $0.65 | $0.60 | $0.60 |
| 39 | Marking removal line grooved contrast permanent tape 4-inch (646.9055) | LF | 85 | $6.00 | $5.00 | $5.00 |
| 40 | Marking removal line grooved contrast permanent tape 8-inch (646.9155) | LF | 1,064 | $6.00 | $5.50 | $5.50 |
| 41 | Special 01. rapid set deck repair (SPV.0035) | CY | 7 | $1,600.00 | $3,500.00 | $3,000.00 |
| 42 | Special 01. polyester polymer concrete overlay (SPV.0180) | SY | 61,336 | $88.50 | $91.25 | $93.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of May 12, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.