WisDOT contract 20260512012 bid tabulation
Wisconsin St, C Oshkosh; Fox River Bridge B-70-0247 (STH 044, Winnebago County Wisconsin St, C Oshkosh). Let by Wisconsin DOT on May 12, 2026, Winnebago. 6 bids received; low bid $1,276,615 by Omega Coatings & Construction, LLC.
- Owner
- Wisconsin DOT
- Letting
- 12 MAY 2026
- Pay items
- 27
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Omega Coatings & Construction, LLC | $1,276,615 | Low |
| 2 | Zenith Tech., Inc. - Waukesha | $1,462,043 | +15% |
| 3 | Civil Coatings & Construction, Inc. | $1,492,093 | +17% |
| 4 | Kalymnos Bridge Painting, LLC. | $1,723,602 | +35% |
| 5 | North Star Painting Company, Inc. | $1,935,498 | +52% |
| 6 | Abhe & Svoboda, Inc. | $3,868,798 | +203% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Omega Coatings & Construction, LLC | 2. Zenith Tech., Inc. - Waukesha | 3. Civil Coatings & Construction, Inc. | 4. Kalymnos Bridge Painting, LLC. | 5. North Star Painting Company, Inc. | 6. Abhe & Svoboda, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Structure repainting recycled abrasive (structure) 01. B-70-0247 (517.1801.S) | EACH | 1 | $400,000 | $437,000 | $532,000 | $390,000 | $800,000 | $1,321,162 |
| 2 | Structure overcoating cleaning and priming (structure) 01. B-70-0247 (517.3001.S) | EACH | 1 | $5,000.00 | $15,000 | $5,000.00 | $390,000 | $200,000 | $15,265 |
| 3 | Containment and collection of waste materials (structure) 01. B- 70-0247 (517.4001.S) | EACH | 1 | $500.00 | $5,000.00 | $2,500.00 | $100,000 | $50,000 | $610,580 |
| 4 | Negative pressure containment and collection of waste materials (structure) 01. B-70-0247 (517.4501.S) | EACH | 1 | $240,000 | $299,000 | $350,000 | $100,000 | $200,000 | $760,727 |
| 5 | Portable decontamination facility (517.6001.S) | EACH | 1 | $2,000.00 | $1,000.00 | $500.00 | $10,000 | $30,000 | $90,000 |
| 6 | Mobilization (619.1000) | EACH | 1 | $100,000 | $205,000 | $70,000 | $130,000 | $150,000 | $550,000 |
| 7 | Field office type B (642.5001) | EACH | 1 | $8,000.00 | $17,500 | $1,000.00 | $3,000.00 | $5,000.00 | $62,630 |
| 8 | Traffic control drums (643.0300) | DAY | 4,369 | $0.25 | $0.25 | $0.25 | $0.18 | $0.15 | $0.20 |
| 9 | Traffic control barricades type III (643.0420) | DAY | 256 | $1.00 | $1.00 | $1.00 | $0.90 | $0.75 | $1.00 |
| 10 | Traffic control warning lights type A (643.0705) | DAY | 512 | $0.15 | $0.15 | $0.15 | $0.24 | $0.20 | $0.25 |
| 11 | Traffic control warning lights type C (643.0715) | DAY | 1,604 | $0.15 | $0.15 | $0.15 | $0.24 | $0.20 | $0.25 |
| 12 | Traffic control connected arrow boards (643.0810) | DAY | 128 | $18.50 | $15.50 | $15.50 | $11.40 | $9.50 | $12.00 |
| 13 | Traffic control signs (643.0900) | DAY | 5,294 | $0.50 | $0.35 | $0.35 | $0.30 | $0.25 | $0.35 |
| 14 | Traffic control signs PCMS (643.1050) | DAY | 14 | $30.00 | $25.00 | $25.00 | $42.00 | $35.00 | $45.00 |
| 15 | Traffic control cones 42-inch (643.1070) | DAY | 2,049 | $0.25 | $0.25 | $0.25 | $0.18 | $0.15 | $0.20 |
| 16 | Traffic control connected work zone start and end location markers (643.1220) | DAY | 128 | $8.25 | $7.25 | $7.25 | $7.80 | $6.50 | $8.25 |
| 17 | Temporary marking line removable tape 6-inch (643.3180) | LF | 625 | $2.00 | $1.25 | $1.25 | $2.70 | $2.25 | $3.00 |
| 18 | Traffic control (643.5000) | EACH | 1 | $10,000 | $16,000 | $64,550 | $44,700 | $37,250 | $60,000 |
| 19 | Temporary pedestrian barricade (644.1810) | LF | 204 | $6.50 | $5.50 | $5.50 | $8.40 | $7.00 | $8.85 |
| 20 | Temporary audible message devices (644.1900.S) | DAY | 1,011 | $5.25 | $4.25 | $4.25 | $2.70 | $2.25 | $2.85 |
| 21 | Marking line epoxy 6-inch (646.2020) | LF | 625 | $16.50 | $13.48 | $13.48 | $13.17 | $10.97 | $17.00 |
| 22 | Marking removal line 4-inch (646.9000) | LF | 625 | $2.00 | $1.00 | $1.00 | $3.54 | $2.95 | $3.75 |
| 23 | Special 01. removing and reinstall camera assembly (SPV.0060) | EACH | 2 | $2,500.00 | $2,000.00 | $2,000.00 | $2,400.00 | $2,000.00 | $2,400.00 |
| 24 | Special 02. traffic gate replacement (SPV.0060) | EACH | 4 | $30,000 | $25,000 | $25,000 | $30,000 | $25,000 | $2,839.00 |
| 25 | Special 03. traffic gate electrical work (SPV.0060) | EACH | 4 | $65,000 | $55,000 | $55,000 | $66,000 | $55,000 | $57,401 |
| 26 | Special 04. anchor assemblies for traffic gates (SPV.0060) | EACH | 4 | $12,000 | $10,000 | $10,000 | $12,000 | $10,000 | $1,000.00 |
| 27 | Special 05. balance bascule bridge leaves (SPV.0060) | EACH | 1 | $50,000 | $80,000 | $80,000 | $96,000 | $80,000 | $122,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of May 12, 2026. Compiled by Mirage Metrics.