WisDOT contract 20260512016 bid tabulation
Drummond - USH 2; Mill Pond Dam (USH 063, Bayfield County Drummond - USH 2). Let by Wisconsin DOT on May 12, 2026, Bayfield. 2 bids received; low bid $4,587,415 by Northern Interstate Construction, Inc..
- Owner
- Wisconsin DOT
- Letting
- 12 MAY 2026
- Pay items
- 116
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Northern Interstate Construction, Inc. | $4,587,415 | Low |
| 2 | Musson Bros., Inc. | $4,968,118 | +8.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Northern Interstate Construction, Inc. | 2. Musson Bros., Inc. |
|---|---|---|---|---|---|
| 1 | Clearing (201.0105) | STA | 6 | $1,730.82 | $20,750 |
| 2 | Grubbing (201.0205) | STA | 6 | $813.41 | $20,750 |
| 3 | Removing small pipe culverts (203.0100) | EACH | 1 | $1,213.24 | $1,500.00 |
| 4 | Removing structure (structure) 01. 72" CPRC sta 1490+47 (203.0220) | EACH | 1 | $2,200.66 | $20,000 |
| 5 | Removing structure (structure) 01. C-4-20 (203.0220) | EACH | 1 | $18,202 | $40,000 |
| 6 | Removing guardrail (204.0165) | LF | 982 | $7.80 | $2.50 |
| 7 | Excavation common (205.0100) | CY | 16,435 | $41.22 | $21.00 |
| 8 | Excavation for structures bridges (structure) 01. B-4-128 (206.1001) | EACH | 1 | $14,658 | $200,000 |
| 9 | Borrow (208.0100) | CY | 5,332 | $25.17 | $26.00 |
| 10 | Backfill structure type A (210.1500) | TON | 1,040 | $24.36 | $30.00 |
| 11 | Finishing roadway (project) 01. 1560-02-74 (213.0100) | EACH | 1 | $100.00 | $500.00 |
| 12 | Base aggregate dense 3/4-inch (305.0110) | TON | 271 | $37.68 | $41.00 |
| 13 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 2,429 | $36.82 | $30.00 |
| 14 | Subbase (350.0102) | CY | 586 | $46.64 | $22.00 |
| 15 | Concrete pavement approach slab (415.0410) | SY | 84 | $294.82 | $294.82 |
| 16 | Tack coat (455.0605) | GAL | 101 | $2.44 | $2.44 |
| 17 | Asphaltic surface (465.0105) | TON | 359 | $148.50 | $148.50 |
| 18 | Asphaltic surface driveways and field entrances (465.0120) | TON | 35 | $177.57 | $177.57 |
| 19 | Asphaltic surface temporary (465.0125) | TON | 289 | $131.88 | $385.00 |
| 20 | Concrete masonry bridges (502.0100) | CY | 482 | $800.00 | $800.00 |
| 21 | Protective surface treatment (502.3200) | SY | 525 | $5.00 | $5.00 |
| 22 | Pigmented surface sealer (502.3210) | SY | 130 | $7.50 | $7.50 |
| 23 | Prestressed girder type I 45W-inch (503.0146) | LF | 352 | $350.00 | $350.00 |
| 24 | Bar steel reinforcement HS structures (505.0400) | LB | 5,800 | $1.55 | $1.55 |
| 25 | Bar steel reinforcement HS coated structures (505.0600) | LB | 50,760 | $1.70 | $1.70 |
| 26 | Bar steel reinforcement HS stainless structures (505.0800.S) | LB | 1,460 | $4.00 | $4.00 |
| 27 | Bearing pads elastomeric non- laminated (506.2605) | EACH | 8 | $150.00 | $150.00 |
| 28 | Steel diaphragms (structure) 01. B- 4-128 (506.4000) | EACH | 6 | $1,000.00 | $1,000.00 |
| 29 | Temporary shoring (511.1100) | SF | 2,200 | $48.00 | $40.00 |
| 30 | Rubberized membrane waterproofing (516.0500) | SY | 18 | $25.00 | $25.00 |
| 31 | Apron endwalls for culvert pipe 15- inch (520.1015) | EACH | 2 | $848.32 | $430.00 |
| 32 | Culvert pipe temporary 36-inch (520.2036) | LF | 733 | $230.58 | $400.00 |
| 33 | Culvert pipe temporary 72-inch (520.2072) | LF | 102 | $392.09 | $287.00 |
| 34 | Culvert pipe class III-A 15-inch (520.3315) | LF | 62 | $124.88 | $97.00 |
| 35 | Concrete collars for pipe (520.8000) | EACH | 1 | $1,395.85 | $3,411.00 |
| 36 | Piling steel HP 10-inch X 42 LB (550.1100) | LF | 1,020 | $50.00 | $50.00 |
| 37 | Concrete curb & gutter 4-inch sloped 36-inch type TBT (601.0588) | LF | 74 | $85.47 | $85.47 |
| 38 | Concrete surface drains (602.3010) | CY | 4 | $1,527.59 | $1,527.59 |
| 39 | Concrete barrier temporary precast delivered (603.8000) | LF | 577 | $19.13 | $19.13 |
| 40 | Concrete barrier temporary precast installed (603.8125) | LF | 577 | $13.03 | $13.03 |
| 41 | Riprap light (606.0100) | CY | 993 | $145.17 | $160.00 |
| 42 | Riprap heavy (606.0300) | CY | 55 | $129.30 | $109.00 |
| 43 | Riprap extra-heavy (606.0400) | CY | 1,606 | $157.05 | $83.00 |
| 44 | Cover plates temporary (611.8120.S) | EACH | 1 | $500.00 | $976.00 |
| 45 | Pipe underdrain wrapped 6-inch (612.0406) | LF | 220 | $28.77 | $9.00 |
| 46 | Anchor assemblies for steel plate beam guard (614.0150) | EACH | 4 | $250.00 | $250.00 |
| 47 | Steel thrie beam structure approach (614.0200) | LF | 20.60 | $131.50 | $93.00 |
| 48 | Steel plate beam guard short radius (614.0345) | LF | 56.25 | $39.65 | $27.00 |
| 49 | Steel plate beam guard short radius terminal (614.0390) | EACH | 1 | $1,100.00 | $2,133.00 |
| 50 | Crash cushions temporary (614.0905) | EACH | 2 | $4,750.00 | $4,750.00 |
| 51 | MGS guardrail 3 (614.2300) | LF | 125 | $32.65 | $26.00 |
| 52 | MGS thrie beam transition (614.2500) | LF | 112.50 | $138.88 | $95.00 |
| 53 | MGS guardrail terminal eat (614.2610) | EACH | 3 | $4,005.00 | $3,233.00 |
| 54 | Maintenance and repair of haul roads (project) 01. 1560-02-74 (618.0100) | EACH | 1 | $100.00 | $1.00 |
| 55 | Mobilization (619.1000) | EACH | 1 | $632,500 | $752,824 |
| 56 | Water (624.0100) | MGAL | 90 | $89.30 | $0.01 |
| 57 | Salvaged topsoil (625.0500) | SY | 27,419 | $5.54 | $1.00 |
| 58 | Mulching (627.0200) | SY | 32,600 | $0.82 | $0.30 |
| 59 | Silt fence (628.1504) | LF | 2,550 | $2.38 | $2.50 |
| 60 | Silt fence maintenance (628.1520) | LF | 2,550 | $0.25 | $0.03 |
| 61 | Mobilizations erosion control (628.1905) | EACH | 3 | $700.00 | $203.00 |
| 62 | Mobilizations emergency erosion control (628.1910) | EACH | 4 | $500.00 | $293.00 |
| 63 | Erosion mat class II type C (628.2027) | SY | 2,140 | $5.65 | $4.13 |
| 64 | Culvert pipe checks (628.7555) | EACH | 2 | $250.00 | $50.00 |
| 65 | Fertilizer type B (629.0210) | CWT | 5 | $127.20 | $125.00 |
| 66 | Seeding mixture no. 20 (630.0120) | LB | 215 | $4.16 | $9.00 |
| 67 | Seeding mixture no. 70 (630.0170) | LB | 95 | $138.65 | $150.00 |
| 68 | Seeding temporary (630.0200) | LB | 110 | $3.18 | $7.00 |
| 69 | Seeding nurse crop (630.0400) | LB | 190 | $3.18 | $5.00 |
| 70 | Seed water (630.0500) | MGAL | 180 | $1.27 | $5.00 |
| 71 | Moving signs type II (638.2102) | EACH | 8 | $31.50 | $125.00 |
| 72 | Removing signs type II (638.2602) | EACH | 1 | $31.50 | $50.00 |
| 73 | Removing small sign supports (638.3000) | EACH | 1 | $50.00 | $50.00 |
| 74 | Moving small sign supports (638.4000) | EACH | 8 | $50.00 | $125.00 |
| 75 | Field office type C (642.5201) | EACH | 1 | $35,000 | $40,000 |
| 76 | Traffic control drums (643.0300) | DAY | 8,400 | $1.00 | $1.00 |
| 77 | Traffic control barricades type III (643.0420) | DAY | 1,800 | $3.00 | $3.00 |
| 78 | Traffic control warning lights type A (643.0705) | DAY | 3,600 | $0.20 | $0.20 |
| 79 | Traffic control warning lights type C (643.0715) | DAY | 600 | $0.25 | $0.25 |
| 80 | Traffic control signs (643.0900) | DAY | 6,140 | $1.95 | $1.95 |
| 81 | Traffic control covering signs type II (643.0920) | EACH | 5 | $35.00 | $35.00 |
| 82 | Temporary marking line paint 6- inch (643.3165) | LF | 1,585 | $3.80 | $3.25 |
| 83 | Temporary marking stop line removable tape 18-inch (643.3850) | LF | 24 | $6.50 | $20.00 |
| 84 | Traffic control (643.5000) | EACH | 1 | $6,400.00 | $6,400.00 |
| 85 | Geotextile type DF schedule A (645.0111) | SY | 140 | $2.68 | $8.00 |
| 86 | Geotextile type HR (645.0120) | SY | 1,720 | $2.99 | $5.00 |
| 87 | Geotextile type R (645.0130) | SY | 17 | $3.63 | $24.00 |
| 88 | Marking line epoxy 6-inch (646.2020) | LF | 1,600 | $2.38 | $2.38 |
| 89 | Marking line grooved wet ref epoxy 6-inch (646.2040) | LF | 1,550 | $4.00 | $4.00 |
| 90 | Marking removal line 4-inch (646.9000) | LF | 538 | $3.00 | $3.00 |
| 91 | Construction staking storm sewer (650.4000) | EACH | 1 | $3,500.00 | $2,000.00 |
| 92 | Construction staking subgrade (650.4500) | LF | 1,240 | $1.00 | $0.01 |
| 93 | Construction staking base (650.5000) | LF | 1,240 | $1.00 | $3.33 |
| 94 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 74 | $8.00 | $30.00 |
| 95 | Construction staking pipe culverts (650.6000) | EACH | 3 | $650.00 | $1,500.00 |
| 96 | Construction staking structure layout (structure) 01. B-04-0128 (650.6501) | EACH | 1 | $3,500.00 | $9,000.00 |
| 97 | Construction staking supplemental control (project) 01. 1560-02-74 (650.9911) | EACH | 1 | $2,500.00 | $2,500.00 |
| 98 | Construction staking slope stakes (650.9920) | LF | 1,240 | $1.50 | $3.33 |
| 99 | Temporary traffic signals for bridges (structure) 01. B-04-0128 (661.0101) | EACH | 1 | $18,500 | $17,100 |
| 100 | Sawing asphalt (690.0150) | LF | 723 | $1.99 | $1.99 |
| 101 | Incentive strength concrete structures (715.0502) | DOL | 2,892 | $1.00 | $1.00 |
| 102 | Incentive compressive strength concrete pavement (715.0720) | DOL | 500 | $1.00 | $1.00 |
| 103 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 800 | $5.00 | $5.00 |
| 104 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 600 | $5.00 | $5.00 |
| 105 | Special 01. habitat boulders (SPV.0035) | CY | 30 | $576.63 | $282.00 |
| 106 | Special 01. upper cofferdam (SPV.0060) | EACH | 1 | $285,000 | $155,039 |
| 107 | Special 02. lower cofferdam (SPV.0060) | EACH | 1 | $287,500 | $750,000 |
| 108 | Special 03. manhole temporary 60- inch (SPV.0060) | EACH | 1 | $3,122.38 | $25,004 |
| 109 | Special 04. wood floodplain roughness feature (SPV.0060) | EACH | 9 | $6,500.00 | $2,464.00 |
| 110 | Special 05. embedded large wood floodplain roughness feature (SPV.0060) | EACH | 17 | $6,500.00 | $3,527.00 |
| 111 | Special 06. standard riffles (SPV.0060) | EACH | 8 | $6,500.00 | $3,560.00 |
| 112 | Special 07. standard pools (SPV.0060) | EACH | 8 | $6,500.00 | $2,670.00 |
| 113 | Special 08. willow stakes (SPV.0060) | EACH | 1,200 | $20.00 | $28.25 |
| 114 | Special 09. excess cut native material (SPV.0060) | EACH | 8 | $3,224.22 | $995.00 |
| 115 | Special 10. driveway assistance device (SPV.0060) | EACH | 1 | $3,000.00 | $3,000.00 |
| 116 | Special 01. bank wood revetment (SPV.0090) | LF | 190 | $200.00 | $422.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of May 12, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.