18" reinforced concrete pipe culverts (class iii) unit price, Arkansas
Low bidders on ARDOT contracts carried a median of $90.00 per LF for item 605601, 18" reinforced concrete pipe culverts (class iii), over the 24 months to 04 NOV 2026, across 31 low bids. Half of all 115 bids fell between $88.00 and $155.00.
- Owner
- Arkansas DOT
- Item
- 605601
- Unit
- LF
- Latest letting
- 04 NOV 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2022 | 4 | 7 | $116.00 | 13 | $131.25 |
| 2023 | 10 | 14 | $173.57 | 31 | $117.00 |
| 2024 | 6 | 8 | $112.47 | 18 | $114.97 |
| 2025 | 14 | 20 | $86.59 | 76 | $118.06 |
| 2026 | 10 | 11 | $108.65 | 39 | $107.53 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Clark | 3 | $83.14 | 16 | $128.50 |
| Benton | 4 | $94.50 | 16 | $119.45 |
| Lonoke | 3 | $108.65 | 11 | $108.66 |
| Crawford | 3 | $54.00 | 8 | $83.90 |
Countys with at least three low bids, over the last 24 months.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 3 to 54 | 7 | $105.00 |
| 82 to 280 | 8 | $88.00 |
| 304 to 947 | 8 | $95.00 |
| 1,219 to 7,110 | 8 | $87.42 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 04 NOV 2026 | 040904 | Crawford | 134 | $69.88 | $85.99 | 4 | CROSSLAND CONSTRUCTION CO., INC. | ARDOT |
| 04 NOV 2026 | 061922 | Garland | 3 | $165.00 | $580.00 | 2 | TI-ZACK CONCRETE, LLC | ARDOT |
| 04 NOV 2026 | 101141 | Mississippi | 304 | $191.00 | $183.26 | 4 | BLUFF CITY CONSTRUCTION CO., LLC | ARDOT |
| 04 NOV 2026 | FA0314 | Baxter | 16 | $105.00 | $105.00 | 3 | ROBERTSON CONTRACTORS, INC. | ARDOT |
| 12 AUG 2026 | 030531 | Little River | 280 | $78.30 | $101.27 | 6 | MCGEORGE CONTRACTING CO., INC. | ARDOT |
| 24 JUN 2026 | 020853 | Desha | 36 | $150.00 | $125.00 | 2 | PINE BLUFF SAND & GRAVEL CO. | ARDOT |
| 04 MAR 2026 | A00096 | Craighead, Greene | 10 | $577.63 | $203.28 | 4 | ATLAS ASPHALT, INC. | ARDOT |
| 21 JAN 2026 | 061371 | Lonoke | 1,435 | $108.66 | $109.33 | 4 | WEAVER-BAILEY CONTRACTORS, INC. | ARDOT |
| 21 JAN 2026 | 061371 | Lonoke | 3,845 | $108.65 | $104.12 | 4 | WEAVER-BAILEY CONTRACTORS, INC. | ARDOT |
| 21 JAN 2026 | 100881 | Craighead | 1,992 | $70.00 | $68.48 | 2 | ROGERS GROUP, INC. | ARDOT |
| 21 JAN 2026 | C10008 | Clark | 24 | $80.00 | $254.34 | 4 | SALT CREEK PAVING & CONST. CO., INC. | ARDOT |
| 05 NOV 2025 | 090433 | Benton | 180 | $86.00 | $134.67 | 4 | GRANT GARRETT EXCAVATING, INC. | ARDOT |
| 05 NOV 2025 | 090433 | Benton | 4,442 | $79.50 | $91.00 | 4 | GRANT GARRETT EXCAVATING, INC. | ARDOT |
| 05 NOV 2025 | 090651 | Benton | 126 | $150.00 | $135.00 | 4 | GRANT GARRETT EXCAVATING, INC. | ARDOT |
| 05 NOV 2025 | 090651 | Benton | 871 | $103.00 | $111.50 | 4 | GRANT GARRETT EXCAVATING, INC. | ARDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the ARDOT explorer.
How these prices were read
ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are ARDOT's own: this item is compared with ARDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.