24" flared end sections for reinforced concrete pipe culverts unit price, Arkansas

Low bidders on ARDOT contracts carried a median of $2,035.73 per EACH for item 605858, 24" flared end sections for reinforced concrete pipe culverts, over the 24 months to 04 NOV 2026, across 28 low bids. Half of all 97 bids fell between $1,826.01 and $3,200.00.

Owner
Arkansas DOT
Item
605858
Unit
EACH
Latest letting
04 NOV 2026
$2,035.73Low bidder's median, per EACH
$2,326.45Median of all bids, per EACH
28Contracts in the window

By year of letting

24" flared end sections for reinforced concrete pipe culverts, ARDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20221313$2,329.8131$2,329.81
20231213$2,150.0027$2,217.00
20241918$2,036.8740$2,049.36
20251313$2,225.7744$2,386.07
20261313$2,020.1748$2,358.93
24" flared end sections for reinforced concrete pipe culverts, ARDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By quantity

24" flared end sections for reinforced concrete pipe culverts, ARDOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
1 to 17$2,700.00
1 to 27$2,200.00
2 to 67$1,771.15
7 to 417$1,744.09
24" flared end sections for reinforced concrete pipe culverts, ARDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest ARDOT contracts carrying 24" flared end sections for reinforced concrete pipe culverts
LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
04 NOV 2026040904Crawford24$806.00$2,231.014CROSSLAND CONSTRUCTION CO., INC.ARDOT
04 NOV 2026A90050Baxter41$1,744.09$1,997.052ATLAS ASPHALT, INC.ARDOT
04 NOV 2026101141Mississippi2$2,391.40$2,108.204BLUFF CITY CONSTRUCTION CO., LLCARDOT
23 SEP 2026070458Columbia2$2,020.17$2,435.647MOBLEY CONTRACTORS, INC.ARDOT
12 AUG 2026030531Little River6$1,771.15$1,771.155MCGEORGE CONTRACTING CO., INC.ARDOT
20 MAY 2026020802Jefferson2$1,760.00$2,600.0051911 CONSTRUCTION COMPANY, INC.ARDOT
08 APR 2026110832Cross1$2,262.22$4,162.418WHITE RIVER MATERIALS, INC.ARDOT
04 MAR 2026A90038Searcy18$2,057.29$2,450.862APAC-CENTRAL, INC.ARDOT
04 MAR 2026A90039Baxter14$1,708.34$2,402.432APAC-CENTRAL, INC.ARDOT
04 MAR 2026101003Randolph2$2,200.00$2,200.001ROBERTSON CONTRACTORS, INC.ARDOT
21 JAN 2026061371Lonoke7$2,166.65$2,246.554WEAVER-BAILEY CONTRACTORS, INC.ARDOT
21 JAN 2026A80046Faulkner4$1,500.00$1,550.002ROGERS GROUP, INC.ARDOT
21 JAN 2026100881Craighead1$2,800.00$3,871.382ROGERS GROUP, INC.ARDOT
05 NOV 2025090651Benton1$1,950.00$3,193.504GRANT GARRETT EXCAVATING, INC.ARDOT
05 NOV 2025A00094Randolph6$1,200.00$1,724.464RICHARD BAUGHN CONSTRUCTION, INC.ARDOT
Latest ARDOT contracts carrying 24" flared end sections for reinforced concrete pipe culverts

Filter this item by your own quantity, county and period, or check your price against it, in the ARDOT explorer.

How these prices were read

ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ARDOT's own: this item is compared with ARDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy