ARDOT contract A20031 bid tabulation

THE PURPOSE OF THIS PROJECT IS TO MILL, INLAY, AND OVERLAY APPROXIMATELY 4.795 MILES OF HIGHWAY 278 IN DREW COUNTY. THIS PROJECT CONSISTS OF AGGREGATE BASE COURSE, ACHM SURFACE COURSE, COLD MILLING ASPHALT PAVEMENT, ACHM PATCHING OF EXISTING ROADWAY, MAINTENANCE OF TRAFFIC, RUMBLE STRIPS, PAVEMENT MARKING, AND MISC. ITEMS. Let by Arkansas DOT on January 15, 2025, Drew. 1 bid received; low bid $4,630,121 by Pine Bluff Sand & Gravel Co..

Owner
Arkansas DOT
Letting
15 JAN 2025
Pay items
17
Data through
04 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Pine Bluff Sand & Gravel Co.$4,630,121Low
ARDOT contract A20031: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Pine Bluff Sand & Gravel Co.
0001Aggregate base course (class 7) (303117)TON447$65.00
0002Tack coat (401011)GAL32,136$6.00
0003Mineral aggregate in achm surface course (1/2") (407162)TON19,527$86.22
0004Asphalt binder (PG 70-22) in achm surface course (1/2") (minimum bid $120.00) (407442)TON1,202$1,000.00
0005Cold milling asphalt pavement (412002)SY188,449$3.70
0006Asphalt concrete patching for maintenance of traffic (414011)TON50$300.00
0007Achm patching of existing roadway (415011)TON500$300.00
0008Maintenance of traffic (603009)LS1$178,000
0009Signs (604003)SF468$10.00
0010Construction pavement markings (604041)LF214,580$0.42
0011Roadway construction control (635001)LS1$60,000
0012Rumble strips in asphalt shoulders (642001)LF24,077$0.50
0013Thermoplastic pavement marking white (6") (719002)LF43,666$0.90
0014Thermoplastic pavement marking yellow (6") (719102)LF63,624$0.90
0015Thermoplastic pavement marking (railroad emblems) (719203)EACH4$1,000.00
0016Raised pavement markers (type II) (721002)EACH1,272$5.00
0017Mobilization (unit bid amount may not exceed 5% of subtotal) (601001)LS1$208,608
ARDOT contract A20031: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.

Every contract let that day: ARDOT letting of January 15, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy