ARDOT contract A70049 bid tabulation
THE PURPOSE OF THIS PROJECT IS TO MILL AND OVERLAY APPROXIMATELY 3.373 MILES OF HIGHWAY 167 IN CALHOUN COUNTY. THIS PROJECT CONSISTS OF FOG SEAL, ACHM SURFACE COURSE, COLD MILLING ASPHALT PAVEMENT, MAINTENANCE OF TRAFFIC, RUMBLE STRIPS AND STRIPES, PAVEMENT MARKING, AND MISC. ITEMS. Let by Arkansas DOT on November 4, 2026, Calhoun. 1 bid received; low bid $2,223,118 by Jet Asphalt & Rock Co., Inc..
- Owner
- Arkansas DOT
- Letting
- 04 NOV 2026
- Pay items
- 15
- Data through
- 04 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Jet Asphalt & Rock Co., Inc. | $2,223,118 | Low |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Jet Asphalt & Rock Co., Inc. |
|---|---|---|---|---|
| 0001 | Fog seal (type 2) (401005) | GAL | 4,454 | $5.67 |
| 0002 | Tack coat (401011) | GAL | 9,699 | $0.01 |
| 0003 | Mineral aggregate in achm surface course (1/2") (407162) | TON | 10,061 | $145.28 |
| 0004 | Asphalt binder (PG 70-22) in achm surface course (1/2") (minimum bid $120.00) (407442) | TON | 608 | $195.00 |
| 0005 | Cold milling asphalt pavement (412002) | SY | 96,991 | $2.77 |
| 0006 | Maintenance of traffic (603009) | LS | 1 | $144,000 |
| 0007 | Signs (604003) | SF | 231 | $10.00 |
| 0008 | Construction pavement markings (604041) | LF | 166,000 | $0.12 |
| 0009 | Roadway construction control (635011) | LS | 1 | $5,100.00 |
| 0010 | Rumble strips in asphalt shoulders (642001) | LF | 35,629 | $0.16 |
| 0011 | Centerline rumble stripes in asphalt roadways (642102) | LF | 17,814 | $0.18 |
| 0012 | Thermoplastic pavement marking white (6") (719002) | LF | 46,032 | $1.27 |
| 0013 | Thermoplastic pavement marking yellow (6") (719102) | LF | 36,818 | $0.83 |
| 0014 | Raised pavement markers (type II) (721002) | EACH | 690 | $6.50 |
| 0015 | Mobilization (unit bid amount may not exceed 5% of subtotal) (601001) | LS | 1 | $75,138 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
Every contract let that day: ARDOT letting of November 4, 2026. Compiled by Mirage Metrics.