ARDOT contract SA2139 bid tabulation
THE PURPOSE OF THIS PROJECT IS TO OVERLAY AND SURFACE APPROXIMATELY 0.25 MILE OF COUNTY ROAD 264 & 0.50 MILE OF BAXTER RD. IN DESHA COUNTY. THIS PROJECT CONSISTS OF AGGREGATE BASE COURSE, RECONSTRUCTED BASE COURSE, ASPHALT SURFACE COURSE, ACHM PATCHING OF EXISTING ROADWAY, MAINTENANCE OF TRAFFIC, AND MISC. ITEMS. Let by Arkansas DOT on April 8, 2026, Desha. 1 bid received; low bid $262,956 by Pine Bluff Sand & Gravel Co..
- Owner
- Arkansas DOT
- Letting
- 08 APR 2026
- Pay items
- 10
- Data through
- 04 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Pine Bluff Sand & Gravel Co. | $262,956 | Low |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Pine Bluff Sand & Gravel Co. |
|---|---|---|---|---|
| 0001 | Scarifying and recompacting roadway (216201) | STA | 6 | $1,000.00 |
| 0002 | Aggregate base course (class 7) (303117) | TON | 66 | $100.00 |
| 0003 | Reconstructed base course (305001) | STA | 26 | $1,000.00 |
| 0004 | Tack coat (401011) | GAL | 449 | $8.00 |
| 0005 | Mineral aggregate in achm surface course (1/2") (407162) | TON | 1,226 | $143.63 |
| 0006 | Asphalt binder (PG 64-22) in achm surface course (1/2") (minimum bid $120.00) (407432) | TON | 77 | $120.00 |
| 0007 | Achm patching of existing roadway (415011) | TON | 25 | $350.00 |
| 0008 | Maintenance of traffic (603009) | LS | 1 | $11,550 |
| 0009 | Signs (604003) | SF | 288 | $10.00 |
| 0010 | Mobilization (unit bid amount may not exceed 5% of subtotal) (601001) | LS | 1 | $12,254 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
Every contract let that day: ARDOT letting of April 8, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.