ARDOT contract SA3657 bid tabulation
THE PURPOSE OF THIS PROJECT IS TO SURFACE AND RESEAL APPROXIMATELY 10.49 MILES ON VARIOUS COUNTY ROADS IN JOHNSON COUNTY. THIS PROJECT CONSISTS OF RECONSTRUCTED BASE COURSE, PRIME COAT, SINGLE ASPHALT SURFACE TREATMENT, DOUBLE ASPHALT SURFACE TREATMENT, MAINTENANCE OF TRAFFIC, PAVEMENTS MARKING, AND MISC. ITEMS. Let by Arkansas DOT on March 4, 2026, Johnson. 4 bids received; low bid $509,344 by Emery Sapp & Sons, Inc..
- Owner
- Arkansas DOT
- Letting
- 04 MAR 2026
- Pay items
- 8
- Data through
- 04 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Emery Sapp & Sons, Inc. | $509,344 | Low |
| 2 | Salt Creek Paving & Const. Co., Inc. | $565,778 | +11% |
| 3 | Apac-Central, Inc. | $573,475 | +13% |
| 4 | Vance Brothers, Inc. | $751,656 | +48% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Emery Sapp & Sons, Inc. | 2. Salt Creek Paving & Const. Co., Inc. | 3. Apac-Central, Inc. | 4. Vance Brothers, Inc. |
|---|---|---|---|---|---|---|---|
| 0001 | Reconstructed base course (305001) | STA | 117 | $167.02 | $275.00 | $250.00 | $170.00 |
| 0002 | Prime coat (401001) | GAL | 10,940 | $3.94 | $4.72 | $4.75 | $6.75 |
| 0003 | Mineral aggregate in asphalt surface treatment (class 2) (402112) | TON | 2,688 | $57.72 | $62.95 | $52.00 | $65.00 |
| 0004 | Polymer modified cationic emulsified asphalt (CRS-2P) (solid polymer) (402214) | GAL | 61,430 | $4.12 | $4.28 | $4.95 | $4.60 |
| 0005 | Maintenance of traffic (603009) | LS | 1 | $6,238.35 | $7,585.00 | $10,000 | $105,000 |
| 0006 | Signs (604003) | SF | 994 | $7.93 | $7.00 | $7.55 | $10.84 |
| 0007 | Reflectorized paint pavement marking yellow (4") (718101) | LF | 110,774 | $0.14 | $0.12 | $0.13 | $0.45 |
| 0016 | Mobilization (unit bid amount may not exceed 5% of subtotal) (601001) | LS | 1 | $8,826.65 | $22,000 | $16,500 | $35,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
Every contract let that day: ARDOT letting of March 4, 2026. Compiled by Mirage Metrics.