ARDOT contract SA4656 bid tabulation
THE PURPOSE OF THIS PROJECT IS TO LEVEL AND RESEAL APPROXIMATELY 15.69 MILES OF COUNTY ROAD 10 IN MILLER COUNTY. THIS PROJECT CONSISTS OF ASPHALT SURFACE TREATMENT, ACHM SURFACE COURSE, PATCHING OF EXISTING ROADWAY, MAINTENANCE OF TRAFFIC, PAVEMENT MARKING AND MISC ITEMS. Let by Arkansas DOT on June 25, 2025, Miller. 2 bids received; low bid $1,026,029 by Sidney E Young DBA Sid and Sons.
- Owner
- Arkansas DOT
- Letting
- 25 JUN 2025
- Pay items
- 10
- Data through
- 04 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Sidney E Young DBA Sid and Sons | $1,026,029 | Low |
| 2 | Salt Creek Paving & Const. Co., Inc. | $1,184,738 | +15% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Sidney E Young DBA Sid and Sons | 2. Salt Creek Paving & Const. Co., Inc. |
|---|---|---|---|---|---|
| 0001 | Tack coat (401011) | GAL | 870 | $0.01 | $6.00 |
| 0002 | Mineral aggregate in asphalt surface treatment (class 2) (402112) | TON | 3,204 | $125.00 | $119.00 |
| 0003 | Polymer modified cationic emulsified asphalt (CRS-2P) (solid polymer) (402204) | GAL | 82,391 | $4.50 | $4.97 |
| 0004 | Mineral aggregate in achm surface course (3/8") (407161) | TON | 545 | $180.00 | $275.00 |
| 0005 | Asphalt binder (PG 64-22) in achm surface course (3/8") (minimum bid $120.00) (407431) | TON | 35 | $180.00 | $275.00 |
| 0006 | Achm patching of existing roadway (415011) | TON | 175 | $368.00 | $550.00 |
| 0007 | Maintenance of traffic (603009) | LS | 1 | $20,000 | $45,000 |
| 0008 | Signs (604003) | SF | 550 | $5.00 | $7.00 |
| 0009 | Reflectorized paint pavement marking yellow (4") (718101) | LF | 165,792 | $0.14 | $0.20 |
| 0010 | Mobilization (unit bid amount may not exceed 5% of subtotal) (601001) | LS | 1 | $40,000 | $51,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
Every contract let that day: ARDOT letting of June 25, 2025. Compiled by Mirage Metrics.