Fiber optic connection hardware, f&i, splice unit price, Florida
Low bidders on FDOT contracts carried a median of $1,596.00 per EACH for item 0633-3-11, fiber optic connection hardware, f&i, splice, over the 24 months to 28 OCT 2026, across 59 low bids. Half of all 250 bids fell between $1,500.00 and $1,898.51.
- Owner
- Florida DOT
- Item
- 0633-3-11
- Unit
- EACH
- Latest letting
- 29 APR 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 25 | 32 | $905.03 | 161 | $875.00 |
| 2019 | 28 | 29 | $858.00 | 130 | $871.43 |
| 2020 | 18 | 17 | $852.35 | 86 | $867.63 |
| 2021 | 47 | 50 | $987.50 | 212 | $950.00 |
| 2022 | 36 | 36 | $1,129.51 | 128 | $1,125.61 |
| 2023 | 35 | 39 | $1,302.00 | 134 | $1,250.00 |
| 2024 | 36 | 39 | $1,550.00 | 152 | $1,526.98 |
| 2025 | 36 | 38 | $1,597.50 | 163 | $1,617.00 |
| 2026 | 17 | 17 | $1,706.24 | 76 | $1,743.77 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| District 4 | 15 | $1,600.00 | 82 | $1,760.00 |
| District 5 | 14 | $1,510.50 | 53 | $1,565.00 |
| District 7 | 8 | $1,591.59 | 39 | $1,663.04 |
| District 1 | 9 | $1,635.71 | 35 | $1,655.00 |
| District 2 | 9 | $1,440.00 | 30 | $1,555.80 |
| District 3 | 4 | $2,250.00 | 11 | $2,000.00 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 1 | 14 | $1,547.21 |
| 1 to 3 | 15 | $1,706.24 |
| 3 to 5 | 15 | $1,700.00 |
| 5 to 52 | 15 | $1,595.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 29 APR 2026 | T5880 | District 5 | 7 | $1,536.00 | $1,729.00 | 3 | HALIFAX PAVING, INC. | FDOT |
| 29 APR 2026 | T5881 | District 5 | 5 | $1,749.00 | $1,799.50 | 2 | MASCI GENERAL CONTRACTORS, INC | FDOT |
| 29 APR 2026 | T7562 | District 7 | 5 | $1,460.00 | $1,684.00 | 7 | WATSON CIVIL CONSTRUCTION, INC. | FDOT |
| 29 APR 2026 | T7611 | District 7 | 2 | $1,803.01 | $1,768.79 | 9 | PREFERRED MATERIALS INC. | FDOT |
| 29 APR 2026 | T7615 | District 7 | 1 | $1,706.24 | $1,608.90 | 4 | PREFERRED MATERIALS INC. | FDOT |
| 31 MAR 2026 | T3845 | District 3 | 6 | $1,458.00 | $1,605.00 | 4 | PHOENIX CONSTRUCTION SERVICES, INC. | FDOT |
| 25 MAR 2026 | T1920 | District 1 | 3 | $2,000.00 | $2,068.24 | 6 | SEMA CONSTRUCTION, INC. | FDOT |
| 25 MAR 2026 | T1925 | District 1 | 1 | $1,877.70 | $1,880.00 | 3 | AJAX PAVING INDUSTRIES OF FLORIDA LLC | FDOT |
| 25 MAR 2026 | T2A65 | District 2 | 1 | $1,477.00 | $1,561.37 | 2 | AMERICAN LIGHTING AND SIGNALIZATION, LLC. | FDOT |
| 25 MAR 2026 | T3962 | District 3 | 1 | $2,000.00 | $2,564.50 | 2 | INGRAM SIGNALIZATION, INC. | FDOT |
| 25 MAR 2026 | T4740 | District 4 | 1 | $4,151.16 | $3,950.00 | 9 | GENERAL ASPHALT COMPANY, LLC | FDOT |
| 25 MAR 2026 | T5878 | District 5 | 1 | $1,477.00 | $1,477.00 | 3 | TRAFFIC CONTROL DEVICES, LLC | FDOT |
| 25 FEB 2026 | T1916 | District 1 | 8 | $1,719.64 | $1,719.64 | 5 | PREFERRED MATERIALS INC. | FDOT |
| 25 FEB 2026 | T2A36 | District 2 | 2 | $1,401.66 | $1,450.83 | 2 | CHINCHOR ELECTRIC INC. | FDOT |
| 25 FEB 2026 | T7583 | District 7 | 1 | $1,476.93 | $1,706.60 | 5 | PREFERRED MATERIALS INC. | FDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the FDOT explorer.
How these prices were read
FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are FDOT's own: this item is compared with FDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.