Fiber optic connection hardware, f&i, splice tray unit price, Florida

Low bidders on FDOT contracts carried a median of $63.72 per EACH for item 0633-3-12, fiber optic connection hardware, f&i, splice tray, over the 24 months to 28 OCT 2026, across 93 low bids. Half of all 440 bids fell between $60.00 and $75.32.

Owner
Florida DOT
Item
0633-3-12
Unit
EACH
Latest letting
28 OCT 2026
$63.72Low bidder's median, per EACH
$67.00Median of all bids, per EACH
87Contracts in the window

By year of letting

Fiber optic connection hardware, f&i, splice tray, FDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20182227$61.00136$61.00
20192021$62.5092$60.30
20202122$60.00103$59.78
20214144$60.95193$63.19
20224444$68.51152$71.31
20234146$81.63151$74.69
20243540$72.00150$74.92
20254044$63.86189$66.00
20264142$63.72231$68.40
Fiber optic connection hardware, f&i, splice tray, FDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Fiber optic connection hardware, f&i, splice tray, FDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
District 423$63.72137$67.00
District 529$60.00136$64.90
District 711$64.1560$70.88
District 112$73.5344$76.32
District 212$60.5044$60.50
District 35$108.3315$108.33
Fiber optic connection hardware, f&i, splice tray, FDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Fiber optic connection hardware, f&i, splice tray, FDOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
1 to 223$67.00
2 to 423$61.60
4 to 1223$65.00
12 to 14924$64.58
Fiber optic connection hardware, f&i, splice tray, FDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest FDOT contracts carrying Fiber optic connection hardware, f&i, splice tray
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
28 OCT 2026T3A25District 31$108.33$110.003ANDERSON COLUMBIA CO., INC.FDOT
28 OCT 2026T4765District 41$74.90$73.176GENERAL ASPHALT COMPANY, LLCFDOT
28 OCT 2026T5894District 510$75.00$72.605AUM CONSTRUCTION INC.FDOT
28 OCT 2026T7616District 71$59.40$71.845CHINCHOR ELECTRIC INC.FDOT
30 SEP 2026T5893District 56$56.70$60.508MASCI GENERAL CONTRACTORS, INCFDOT
30 SEP 2026T6398District 61$67.00$69.984OHLA USA INCFDOT
26 AUG 2026T4764District 41$53.52$59.109OHLA USA INCFDOT
29 JUL 2026T4745District 41$70.50$76.236FLORIDA ENGINEERING & DEVELOPMENT CORPFDOT
29 JUL 2026T5883District 51$87.90$86.009MASCI GENERAL CONTRACTORS, INCFDOT
29 JUL 2026T5891District 54$57.75$69.564MASCI GENERAL CONTRACTORS, INCFDOT
15 JUN 2026T5885District 54$97.00$78.274C.W. ROBERTS CONTRACTING, INC.FDOT
10 JUN 2026T2A63District 22$88.00$84.004MAER HOMES, LLCFDOT
10 JUN 2026T5884District 539$66.00$58.926C.W. ROBERTS CONTRACTING, INC.FDOT
10 JUN 2026T5888District 58$65.00$59.348C.W. ROBERTS CONTRACTING, INC.FDOT
20 MAY 2026T4666District 411$61.42$70.528OHLA USA INCFDOT
Latest FDOT contracts carrying Fiber optic connection hardware, f&i, splice tray

Filter this item by your own quantity, district and period, or check your price against it, in the FDOT explorer.

How these prices were read

FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are FDOT's own: this item is compared with FDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy