IDOT contract 61L07 bid tabulation
Elk Grove Village, section 23-00080-00-RS. Let by Illinois DOT on January 17, 2025, Cook, District 01. 2 bids received; low bid $1,405,063 by Plote Construction, Inc..
- Owner
- Illinois DOT
- Letting
- 17 JAN 2025
- Pay items
- 86
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Plote Construction, Inc. | $1,405,063 | Low |
| 2 | Builders Paving, LLC | $1,577,808 | +12% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Plote Construction, Inc. | 2. Builders Paving, LLC |
|---|---|---|---|---|---|
| 1 | Ped signal post 5 FT (X1400378) | EACH | 2 | $1,648.00 | $1,648.00 |
| 2 | Explor trench SPL (X2130010) | LF | 50 | $50.00 | $50.00 |
| 3 | PC conc sidewalk 5 SP (X4240430) | SF | 1,417 | $17.00 | $13.00 |
| 4 | PC conc sidewalk 8 SP (X4240460) | SF | 1,563 | $18.00 | $13.00 |
| 5 | Detectable warn SPL (X4240800) | SF | 104 | $45.00 | $50.00 |
| 6 | CC&G RMVL repl < = 10 (X4400501) | LF | 91 | $63.00 | $85.00 |
| 7 | CC&G RMVL repl > 10FT (X4400503) | LF | 1,419 | $61.00 | $85.00 |
| 8 | HMA surf rem var DP (X4401198) | SY | 17,783 | $6.40 | $7.00 |
| 9 | CB adjust SPL (X6025300) | EACH | 18 | $485.00 | $485.00 |
| 10 | Man adjust SPL (X6025600) | EACH | 5 | $1,650.00 | $1,650.00 |
| 11 | Sanitary manhole adj (X6026050) | EACH | 3 | $2,050.00 | $2,050.00 |
| 12 | Inlets adjust SPL (X6026200) | EACH | 4 | $485.00 | $485.00 |
| 13 | Valve box adj SPL (X6026624) | EACH | 3 | $450.00 | $450.00 |
| 14 | RCSD refl PVT MKR HMA (X7810301) | EACH | 129 | $35.00 | $45.00 |
| 15 | Junction box adjust (X8130130) | EACH | 2 | $1,280.00 | $1,280.00 |
| 16 | Rebld EX DBL handhole (X8140238) | EACH | 1 | $2,865.00 | $2,865.00 |
| 17 | Accessible ped signal (X8760200) | EACH | 8 | $1,865.00 | $1,865.00 |
| 18 | Conc FDN TY A 12D (X8780012) | LF | 8 | $469.00 | $469.00 |
| 19 | Construction layout (Z0013798) | LS | 1 | $5,000.00 | $15,000 |
| 20 | Drill-grout bars (Z0018905) | EACH | 504 | $9.00 | $15.00 |
| 21 | Temp info signing (Z0030850) | SF | 103 | $15.00 | $16.00 |
| 22 | Temp TR signal timing (Z0073510) | EACH | 1 | $1,840.00 | $1,840.00 |
| 23 | Earth excavation (20200100) | CY | 7 | $250.00 | $150.00 |
| 24 | Geotech fab F/GR stab (21001000) | SY | 600 | $0.50 | $1.00 |
| 25 | Topsoil F & P 4 (21101615) | SY | 371 | $7.00 | $0.10 |
| 26 | Sodding salt tolerant (25200110) | SY | 371 | $20.00 | $23.75 |
| 27 | Supple watering (25200200) | UNIT | 20 | $0.01 | $1.00 |
| 28 | Temp eros contr seed (28000250) | LB | 8 | $3.00 | $198.25 |
| 29 | Inlet filters (28000510) | EACH | 48 | $115.00 | $200.00 |
| 30 | Agg subgrade improve (30300001) | CY | 380 | $1.00 | $10.00 |
| 31 | Bit matls tack CT (40600290) | LB | 1,506 | $4.50 | $4.00 |
| 32 | Long joint sealant (40600370) | LF | 9,508 | $2.80 | $2.96 |
| 33 | Mix CR JTS flangewys (40600400) | TON | 20 | $300.00 | $550.00 |
| 34 | HMA surf rem butt JT (40600982) | SY | 160 | $14.85 | $30.00 |
| 35 | P HMA BC IL19.0 N90 (40603240) | TON | 2,551 | $100.00 | $85.00 |
| 36 | HMA SC IL-9.5 D N50 (40604060) | TON | 308 | $130.00 | $115.00 |
| 37 | P HMA SC SMA 9.5 F N80 (40605026) | TON | 2,045 | $120.00 | $125.00 |
| 38 | HMA surf rem 4 (44000165) | SY | 1,339 | $18.00 | $17.00 |
| 39 | Sidewalk rem (44000600) | SF | 2,920 | $3.00 | $4.50 |
| 40 | Median removal (44003100) | SF | 60 | $7.00 | $30.00 |
| 41 | CL B patch T2 10 (44200970) | SY | 200 | $170.00 | $280.00 |
| 42 | CL B patch T3 10 (44200974) | SY | 200 | $170.00 | $280.00 |
| 43 | CL B patch T4 10 (44200976) | SY | 400 | $170.00 | $280.00 |
| 44 | CL D patch T1 8 (44201737) | SY | 24 | $110.00 | $135.00 |
| 45 | CL D patch T2 8 (44201741) | SY | 62 | $110.00 | $125.00 |
| 46 | CL D patch T1 10 (44201761) | SY | 50 | $120.00 | $165.00 |
| 47 | CL D patch T2 10 (44201765) | SY | 100 | $100.00 | $150.00 |
| 48 | CL D patch T3 10 (44201769) | SY | 100 | $95.00 | $130.00 |
| 49 | CB adj new T24F&G (60251740) | EACH | 1 | $1,150.00 | $1,150.00 |
| 50 | CB recon new T24F&G (60254340) | EACH | 1 | $1,985.00 | $1,985.00 |
| 51 | VV adjust (60265700) | EACH | 1 | $650.00 | $650.00 |
| 52 | Conc med TSB6.12 (60619600) | SF | 60 | $34.00 | $40.00 |
| 53 | Non SPL waste disposl (66900200) | CY | 65 | $125.00 | $95.00 |
| 54 | Soil disposal analy (66900530) | EACH | 4 | $1,475.00 | $1,475.00 |
| 55 | Reg sub P-const plan (66901001) | LS | 1 | $3,400.00 | $10,000 |
| 56 | Reg sub F con report (66901003) | LS | 1 | $500.00 | $500.00 |
| 57 | Reg sub mon (66901006) | CAL DAY | 40 | $500.00 | $70.00 |
| 58 | Mobilization (67100100) | LS | 1 | $84,000 | $87,429 |
| 59 | TR cont & prot 701601 (70102630) | LS | 1 | $32,400 | $1.00 |
| 60 | TR cont & prot 701701 (70102635) | LS | 1 | $1.00 | $86,000 |
| 61 | TR cont & prot 701801 (70102640) | LS | 1 | $1.00 | $1.00 |
| 62 | Changeable message SN (70107025) | CAL DAY | 240 | $35.00 | $25.00 |
| 63 | Short term pavt mking (70300100) | LF | 653 | $3.50 | $5.00 |
| 64 | SHRT TRM pavt MK rem (70300150) | SF | 653 | $0.50 | $3.00 |
| 65 | Temp PVT MK line 4 - paint (70300221) | LF | 9,562 | $0.50 | $0.01 |
| 66 | Temp PVT MK line 6 - paint (70300241) | LF | 1,710 | $0.75 | $0.01 |
| 67 | Temp PVT MK line 12 - paint (70300261) | LF | 618 | $1.50 | $0.01 |
| 68 | Temp PVT MK line 24 - paint (70300281) | LF | 151 | $3.00 | $0.01 |
| 69 | Mod ureth PM LTR-sym (78009000) | SF | 437 | $6.00 | $6.00 |
| 70 | Mod ureth PM line 4 (78009004) | LF | 8,932 | $0.95 | $0.95 |
| 71 | Mod ureth PM line 6 (78009006) | LF | 1,788 | $1.50 | $1.20 |
| 72 | Mod ureth PM line 12 (78009012) | LF | 539 | $3.00 | $3.00 |
| 73 | Mod ureth PM line 24 (78009024) | LF | 162 | $6.00 | $6.00 |
| 74 | Raised ref PVT MK rem (78300200) | EACH | 125 | $17.00 | $14.00 |
| 75 | Undrgrd C galvs 2 (81028200) | LF | 52 | $39.00 | $39.00 |
| 76 | Main EX TR sig instal (85000200) | EACH | 1 | $6,400.00 | $6,400.00 |
| 77 | Elcbl T lead 14 1PR (87300305) | LF | 4,441 | $2.90 | $2.90 |
| 78 | Elcbl C signal 14 2C (87301215) | LF | 767 | $3.20 | $3.20 |
| 79 | Elcbl C egrdc 6 1C (87301900) | LF | 73 | $3.80 | $3.80 |
| 80 | Drill EX handhole (87900200) | EACH | 3 | $657.00 | $657.00 |
| 81 | Ped SH LED 1F PM W CT (88102719) | EACH | 8 | $960.90 | $960.90 |
| 82 | Det loop T1 (88600100) | LF | 794 | $26.40 | $26.40 |
| 83 | Mod EX contr (89502200) | EACH | 1 | $3,135.00 | $3,135.00 |
| 84 | Rem elcbl FR con (89502300) | LF | 4,500 | $0.60 | $0.60 |
| 85 | Remov EX TS equip (89502375) | EACH | 1 | $2,560.00 | $2,560.00 |
| 86 | Rebuild EX handhole (89502376) | EACH | 1 | $3,595.00 | $3,595.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of January 17, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.