IDOT contract 61L62 bid tabulation
Morton Grove, section 21-00111-00-RS. Let by Illinois DOT on June 13, 2025, Cook, District 01. 4 bids received; low bid $1,660,324 by Peter Baker & Son Co..
- Owner
- Illinois DOT
- Letting
- 13 JUN 2025
- Pay items
- 87
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Peter Baker & Son Co. | $1,660,324 | Low |
| 2 | Plote Construction, Inc. | $1,676,589 | +1.0% |
| 3 | K-Five Construction Corporation | $1,683,392 | +1.0% |
| 4 | Builders Paving, LLC | $1,795,198 | +8.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Peter Baker & Son Co. | 2. Plote Construction, Inc. | 3. K-Five Construction Corporation | 4. Builders Paving, LLC |
|---|---|---|---|---|---|---|---|
| 1 | Bike path rem (X0327036) | SY | 18 | $20.00 | $80.00 | $50.00 | $65.00 |
| 2 | HMA driveway pavt 3 (X4060280) | SY | 26 | $68.00 | $113.00 | $236.00 | $55.00 |
| 3 | CC&G RMVL repl < = 10 (X4400501) | LF | 364 | $95.75 | $60.00 | $50.00 | $105.00 |
| 4 | CC&G RMVL repl > 10FT (X4400503) | LF | 1,770 | $77.75 | $60.00 | $50.00 | $95.00 |
| 5 | FR & lids adjust SPL (X6030310) | EACH | 73 | $1,310.00 | $1,250.00 | $1,250.00 | $1,300.00 |
| 6 | Temp info signing (X7200061) | SF | 102 | $35.00 | $20.00 | $35.00 | $18.50 |
| 7 | Drainage STR adj (Z0018400) | EACH | 33 | $250.00 | $450.00 | $450.00 | $470.00 |
| 8 | Drainage STR reconst (Z0018600) | EACH | 5 | $1,910.00 | $1,450.00 | $1,450.00 | $1,500.00 |
| 9 | Tree trunk protection (20101100) | EACH | 8 | $130.00 | $130.00 | $250.00 | $270.00 |
| 10 | Nitrogen fert nutr (20101400) | LB | 9 | $1.00 | $1.00 | $1.00 | $2.00 |
| 11 | Potassium fert nutr (20101600) | LB | 9 | $1.00 | $1.00 | $1.00 | $2.00 |
| 12 | Earth excavation (20200100) | CY | 26 | $20.00 | $90.00 | $65.00 | $50.00 |
| 13 | Rem & disp uns matl (20201200) | CY | 213 | $67.00 | $0.50 | $10.00 | $75.00 |
| 14 | Topsoil F & P 4 (21101615) | SY | 701 | $0.10 | $0.10 | $6.00 | $5.50 |
| 15 | Sodding salt tolerant (25200110) | SY | 701 | $27.50 | $27.50 | $20.00 | $20.00 |
| 16 | Supple watering (25200200) | UNIT | 38 | $0.10 | $0.10 | $1.00 | $10.00 |
| 17 | Inlet filters (28000510) | EACH | 46 | $200.00 | $185.00 | $185.00 | $200.00 |
| 18 | Agg subgrade improve (30300001) | CY | 213 | $68.00 | $0.50 | $15.00 | $70.00 |
| 19 | Sub gran mat B 2 (31101180) | SY | 833 | $3.10 | $10.00 | $3.00 | $3.50 |
| 20 | Sub gran mat B 8 (31101600) | SY | 145 | $31.00 | $24.00 | $3.00 | $13.00 |
| 21 | Bit matls tack CT (40600290) | LB | 25,790 | $0.01 | $0.01 | $0.01 | $0.01 |
| 22 | Long joint sealant (40600370) | LF | 24,732 | $3.40 | $2.65 | $2.60 | $3.50 |
| 23 | Mix CR JTS flangewys (40600400) | TON | 38 | $75.00 | $200.00 | $80.00 | $600.00 |
| 24 | HMA surf rem butt JT (40600982) | SY | 540 | $1.00 | $9.00 | $16.00 | $15.00 |
| 25 | P HMA BC IL-4.75 N50 (40603200) | TON | 1,605 | $110.00 | $120.00 | $130.00 | $108.00 |
| 26 | HMA SC IL-9.5 D N50 (40604060) | TON | 3,210 | $86.50 | $95.00 | $96.00 | $85.00 |
| 27 | PCC driveway pavt 6 (42300200) | SY | 75 | $89.25 | $140.00 | $81.00 | $95.00 |
| 28 | PCC driveway pavt 8 (42300400) | SY | 44 | $102.75 | $145.00 | $90.00 | $105.00 |
| 29 | PC conc sidewalk 5 (42400200) | SF | 4,113 | $10.75 | $15.00 | $11.00 | $11.00 |
| 30 | Detectable warnings (42400800) | SF | 433 | $40.00 | $32.00 | $40.00 | $41.00 |
| 31 | HMA surf rem 2 1/4 (44000158) | SY | 37,667 | $4.25 | $3.75 | $3.19 | $4.70 |
| 32 | Drive pavement rem (44000200) | SY | 145 | $20.00 | $33.00 | $18.00 | $21.00 |
| 33 | Sidewalk rem (44000600) | SF | 6,912 | $2.00 | $3.00 | $6.00 | $2.10 |
| 34 | CL D patch T2 6 (44201717) | SY | 53 | $60.00 | $60.00 | $18.00 | $60.00 |
| 35 | CL D patch T3 6 (44201721) | SY | 41 | $60.00 | $55.00 | $18.00 | $60.00 |
| 36 | CL D patch T4 6 (44201723) | SY | 71 | $60.00 | $55.00 | $18.00 | $60.00 |
| 37 | CL D patch T2 8 (44201741) | SY | 283 | $70.00 | $65.00 | $24.00 | $80.00 |
| 38 | CL D patch T3 8 (44201745) | SY | 268 | $70.00 | $60.00 | $24.00 | $80.00 |
| 39 | CL D patch T4 8 (44201747) | SY | 328 | $70.00 | $60.00 | $24.00 | $80.00 |
| 40 | CL D patch T1 9 (44201749) | SY | 3 | $80.00 | $70.00 | $27.00 | $90.00 |
| 41 | CL D patch T2 9 (44201753) | SY | 13 | $80.00 | $65.00 | $27.00 | $90.00 |
| 42 | CL D patch T3 9 (44201757) | SY | 76 | $80.00 | $65.00 | $27.00 | $90.00 |
| 43 | CL D patch T4 9 (44201759) | SY | 385 | $80.00 | $65.00 | $27.00 | $90.00 |
| 44 | CL D patch T1 10 (44201761) | SY | 3 | $90.00 | $75.00 | $30.00 | $100.00 |
| 45 | CL D patch T2 10 (44201765) | SY | 44 | $90.00 | $70.00 | $30.00 | $100.00 |
| 46 | CL D patch T3 10 (44201769) | SY | 32 | $90.00 | $70.00 | $30.00 | $100.00 |
| 47 | CL D patch T4 10 (44201771) | SY | 37 | $90.00 | $70.00 | $30.00 | $100.00 |
| 48 | CL D patch T1 11 (44201773) | SY | 11 | $100.00 | $80.00 | $33.00 | $110.00 |
| 49 | CL D patch T2 11 (44201777) | SY | 52 | $100.00 | $75.00 | $33.00 | $110.00 |
| 50 | CL D patch T3 11 (44201781) | SY | 254 | $100.00 | $75.00 | $33.00 | $110.00 |
| 51 | CL D patch T4 11 (44201783) | SY | 491 | $100.00 | $75.00 | $33.00 | $110.00 |
| 52 | CL D patch T1 14 (44201811) | SY | 13 | $110.00 | $85.00 | $42.00 | $140.00 |
| 53 | CL D patch T2 14 (44201815) | SY | 16 | $110.00 | $80.00 | $42.00 | $140.00 |
| 54 | CL D patch T3 14 (44201819) | SY | 17 | $110.00 | $80.00 | $42.00 | $140.00 |
| 55 | CL D patch T4 14 (44201821) | SY | 62 | $110.00 | $80.00 | $42.00 | $140.00 |
| 56 | Man adjust (60255500) | EACH | 2 | $650.00 | $550.00 | $550.00 | $600.00 |
| 57 | VV adjust (60265700) | EACH | 2 | $650.00 | $550.00 | $550.00 | $600.00 |
| 58 | FR & grates T11 (60404800) | EACH | 5 | $590.00 | $685.00 | $685.00 | $750.00 |
| 59 | FR & lids T1 OL (60406000) | EACH | 1 | $410.00 | $450.00 | $450.00 | $500.00 |
| 60 | FR & lids T1 CL (60406100) | EACH | 5 | $410.00 | $450.00 | $450.00 | $500.00 |
| 61 | Comb CC&G TB6.12 (60603800) | LF | 15 | $70.20 | $55.00 | $100.00 | $82.00 |
| 62 | Non SPL waste disposl (66900200) | CY | 54 | $175.00 | $380.00 | $99.74 | $120.00 |
| 63 | Soil disposal analy (66900530) | EACH | 6 | $670.00 | $670.00 | $670.00 | $680.00 |
| 64 | Reg sub P-const plan (66901001) | LS | 1 | $6,400.00 | $6,400.00 | $6,400.00 | $6,500.00 |
| 65 | Reg sub F con report (66901003) | LS | 1 | $2,300.00 | $2,300.00 | $2,300.00 | $2,300.00 |
| 66 | Reg sub mon (66901006) | CAL DAY | 7 | $700.00 | $700.00 | $700.00 | $700.00 |
| 67 | Mobilization (67100100) | LS | 1 | $167,776 | $99,500 | $100,000 | $100,000 |
| 68 | TR cont & prot 701501 (70102620) | LS | 1 | $4,000.00 | $164,300 | $285,443 | $25,000 |
| 69 | TR cont & prot 701502 (70102622) | LS | 1 | $4,000.00 | $1.00 | $4,000.00 | $1,015.35 |
| 70 | TR cont & prot 701701 (70102635) | LS | 1 | $1,250.00 | $1.00 | $1,250.00 | $1,000.00 |
| 71 | TR cont & prot 701801 (70102640) | LS | 1 | $8,000.00 | $1,000.00 | $8,000.00 | $5,700.00 |
| 72 | Short term pavt mking (70300100) | LF | 9,129 | $1.10 | $0.01 | $0.01 | $1.50 |
| 73 | SHRT TRM pavt MK rem (70300150) | SF | 3,043 | $0.01 | $0.01 | $0.01 | $1.00 |
| 74 | Temp PVT MK LTR & sym paint (70300211) | SF | 930 | $0.01 | $0.01 | $0.01 | $2.00 |
| 75 | Temp PVT MK line 4 - paint (70300221) | LF | 103,236 | $0.01 | $0.01 | $0.01 | $0.35 |
| 76 | Temp PVT MK line 6 - paint (70300241) | LF | 6,306 | $0.01 | $0.01 | $0.01 | $0.53 |
| 77 | Temp PVT MK line 12 - paint (70300261) | LF | 4,029 | $0.01 | $0.01 | $0.01 | $1.05 |
| 78 | Temp PVT MK line 24 - paint (70300281) | LF | 1,482 | $0.01 | $0.01 | $0.01 | $2.10 |
| 79 | THPL PVT MK LTR & sym (78000100) | SF | 310 | $5.25 | $5.50 | $5.50 | $9.00 |
| 80 | THPL PVT MK line 4 (78000200) | LF | 34,412 | $0.80 | $0.90 | $0.90 | $0.71 |
| 81 | THPL PVT MK line 6 (78000400) | LF | 2,102 | $1.30 | $1.00 | $1.00 | $1.10 |
| 82 | THPL PVT MK line 12 (78000600) | LF | 1,343 | $2.50 | $2.75 | $2.75 | $4.50 |
| 83 | THPL PVT MK line 24 (78000650) | LF | 494 | $5.25 | $5.50 | $5.50 | $9.00 |
| 84 | Pref THPL PM LTR-sym (78006100) | SF | 265 | $25.00 | $22.00 | $22.00 | $35.00 |
| 85 | Raised refl pavt MKR (78100100) | EACH | 398 | $42.50 | $35.00 | $35.50 | $41.50 |
| 86 | Raised ref PVT MK rem (78300200) | EACH | 308 | $15.00 | $13.00 | $13.39 | $21.00 |
| 87 | PVT MKG rem WTR blast (78300202) | SF | 15,163 | $0.01 | $0.01 | $0.95 | $1.50 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of June 13, 2025. Compiled by Mirage Metrics.