IDOT contract 61L75 bid tabulation
Maywood, section 24-00145-00-RS. Let by Illinois DOT on January 16, 2026, Cook, District 01. 6 bids received; low bid $424,594 by A Lamp Concrete Contractors, Inc..
- Owner
- Illinois DOT
- Letting
- 16 JAN 2026
- Pay items
- 49
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | A Lamp Concrete Contractors, Inc. | $424,594 | Low |
| 2 | Lindahl Brothers, Inc. | $505,990 | +19% |
| 3 | Schroeder Asphalt Services, Inc. | $515,963 | +22% |
| 4 | Everlast Blacktop Inc. | $518,161 | +22% |
| 5 | K-Five Construction Corporation | $522,629 | +23% |
| 6 | Alliance Contractors, Inc. | $783,302 | +84% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. A Lamp Concrete Contractors, Inc. | 2. Lindahl Brothers, Inc. | 3. Schroeder Asphalt Services, Inc. | 4. Everlast Blacktop Inc. | 5. K-Five Construction Corporation | 6. Alliance Contractors, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 1 | PVC CS pipe repl 10" (XX006448) | LF | 60 | $450.00 | $290.00 | $615.00 | $291.00 | $290.00 | $1,080.00 |
| 2 | Washout basin (X0326806) | LS | 1 | $1,000.00 | $2,500.00 | $1,200.00 | $900.00 | $2,500.00 | $500.00 |
| 3 | Detectable warn SPL (X4240800) | SF | 60 | $45.00 | $60.00 | $92.00 | $94.00 | $60.00 | $50.00 |
| 4 | HMA surf rem var DP (X4401198) | SY | 4,600 | $5.25 | $13.00 | $6.00 | $5.90 | $8.50 | $9.00 |
| 5 | Connect EX manhole (X6020399) | EACH | 1 | $1,250.00 | $1,875.00 | $2,800.00 | $3,500.00 | $1,875.00 | $2,340.00 |
| 6 | FR & lids adjust SPL (X6030310) | EACH | 11 | $825.00 | $1,250.00 | $1,275.00 | $1,100.00 | $1,250.00 | $1,176.00 |
| 7 | Temp info signing (X7200061) | SF | 51.40 | $25.00 | $16.00 | $20.00 | $40.00 | $15.00 | $35.00 |
| 8 | Temp pavement (Z0062456) | SY | 710 | $5.00 | $36.00 | $25.00 | $74.00 | $42.91 | $1.00 |
| 9 | Tree trunk protection (20101100) | EACH | 8 | $50.00 | $221.95 | $245.00 | $180.00 | $125.00 | $100.00 |
| 10 | Tree root pruning (20101200) | EACH | 8 | $50.00 | $101.75 | $125.00 | $180.00 | $125.00 | $100.00 |
| 11 | Trench backfill (20800150) | CY | 60 | $66.00 | $42.00 | $67.00 | $70.00 | $42.00 | $127.00 |
| 12 | Topsoil F & P 4 (21101615) | SY | 200 | $7.15 | $4.00 | $6.00 | $8.00 | $22.00 | $2.00 |
| 13 | Sodding salt tolerant (25200110) | SY | 200 | $25.50 | $35.00 | $42.00 | $20.00 | $40.00 | $45.00 |
| 14 | Supple watering (25200200) | UNIT | 10 | $0.01 | $50.00 | $58.00 | $1.00 | $40.00 | $300.00 |
| 15 | Inlet filters (28000510) | EACH | 18 | $15.00 | $200.00 | $250.00 | $170.00 | $200.00 | $70.00 |
| 16 | Bit matls tack CT (40600290) | LB | 3,100 | $0.01 | $0.01 | $0.01 | $0.01 | $1.17 | $0.01 |
| 17 | Long joint sealant (40600370) | LF | 975 | $10.65 | $10.65 | $12.50 | $10.00 | $13.32 | $13.00 |
| 18 | Mix CR JTS flangewys (40600400) | TON | 20 | $100.00 | $385.00 | $300.00 | $600.00 | $650.00 | $700.00 |
| 19 | HMA surf rem butt JT (40600982) | SY | 35 | $69.00 | $20.00 | $15.00 | $67.00 | $130.00 | $75.00 |
| 20 | HMA BC IL-9.5 N50 (40602978) | TON | 400 | $110.00 | $137.00 | $105.00 | $113.75 | $138.00 | $130.00 |
| 21 | HMA SC IL-9.5 D N50 (40604060) | TON | 525 | $105.00 | $137.00 | $98.00 | $132.45 | $125.00 | $120.00 |
| 22 | Protective coat (42101300) | SY | 160 | $0.01 | $1.00 | $1.20 | $7.00 | $1.00 | $0.01 |
| 23 | PCC driveway pavt 7 (42300300) | SY | 10 | $285.00 | $114.00 | $230.00 | $250.00 | $114.00 | $180.00 |
| 24 | PC conc sidewalk 5 (42400200) | SF | 1,600 | $9.50 | $12.50 | $12.30 | $15.00 | $12.50 | $17.00 |
| 25 | PC conc sidewalk 8 (42400410) | SF | 500 | $15.00 | $14.50 | $16.00 | $16.50 | $14.50 | $20.00 |
| 26 | Drive pavement rem (44000200) | SY | 10 | $55.00 | $20.00 | $50.00 | $18.00 | $20.00 | $120.00 |
| 27 | Comb curb gutter rem (44000500) | LF | 150 | $12.25 | $16.00 | $12.00 | $13.00 | $16.00 | $50.00 |
| 28 | Sidewalk rem (44000600) | SF | 2,150 | $1.75 | $3.50 | $2.95 | $2.00 | $3.50 | $12.00 |
| 29 | CL B patch T1 8 (44200929) | SY | 120 | $115.00 | $185.00 | $285.00 | $270.00 | $185.00 | $290.00 |
| 30 | CL B patch T2 8 (44200934) | SY | 235 | $80.00 | $172.00 | $230.00 | $140.00 | $172.00 | $290.00 |
| 31 | CL B patch T3 8 (44200942) | SY | 235 | $75.00 | $168.00 | $230.00 | $140.00 | $168.00 | $290.00 |
| 32 | CL B patch T4 8 (44200944) | SY | 120 | $90.00 | $168.00 | $230.00 | $175.00 | $168.00 | $290.00 |
| 33 | VV reconst (60266100) | EACH | 1 | $3,350.00 | $2,300.00 | $3,050.00 | $2,000.00 | $2,300.00 | $3,125.00 |
| 34 | FR & lids adjust (60300305) | EACH | 2 | $750.00 | $850.00 | $825.00 | $900.00 | $850.00 | $516.00 |
| 35 | FR & lids T1 OL (60406000) | EACH | 1 | $475.00 | $500.00 | $625.00 | $850.00 | $500.00 | $516.00 |
| 36 | FR & lids T1 CL (60406100) | EACH | 1 | $475.00 | $500.00 | $625.00 | $850.00 | $500.00 | $516.00 |
| 37 | Comb CC&G TB6.12 mod (60604100) | LF | 150 | $45.25 | $55.00 | $62.00 | $58.00 | $55.00 | $70.00 |
| 38 | Mobilization (67100100) | LS | 1 | $25,000 | $30,000 | $18,000 | $20,532 | $32,000 | $90,000 |
| 39 | TR cont & prot 701501 (70102620) | LS | 1 | $92,750 | $4,600.00 | $14,000 | $30,000 | $19,800 | $93,300 |
| 40 | TR cont & prot 701701 (70102635) | LS | 1 | $1.00 | $1.00 | $1.00 | $400.00 | $1.00 | $100.00 |
| 41 | TR cont & prot 701801 (70102640) | LS | 1 | $1.00 | $1.00 | $1.00 | $400.00 | $1.00 | $100.00 |
| 42 | Short term pavt mking (70300100) | LF | 1,700 | $0.01 | $1.00 | $3.00 | $2.00 | $1.00 | $1.00 |
| 43 | SHRT TRM pavt MK rem (70300150) | SF | 575 | $0.01 | $1.00 | $4.00 | $2.00 | $2.00 | $2.00 |
| 44 | Temp PVT MK L24 T4 tape (70307210) | LF | 150 | $0.10 | $8.00 | $9.00 | $15.00 | $17.00 | $8.00 |
| 45 | THPL PVT MK LTR & sym (78000100) | SF | 40 | $6.00 | $6.10 | $7.00 | $7.00 | $6.10 | $6.00 |
| 46 | THPL PVT MK line 4 (78000200) | LF | 3,100 | $0.95 | $1.05 | $2.25 | $1.40 | $1.05 | $0.95 |
| 47 | THPL PVT MK line 6 (78000400) | LF | 900 | $2.00 | $1.55 | $2.25 | $2.40 | $1.55 | $2.00 |
| 48 | THPL PVT MK line 12 (78000600) | LF | 20 | $4.00 | $3.10 | $4.50 | $5.00 | $3.10 | $4.00 |
| 49 | THPL PVT MK line 24 (78000650) | LF | 150 | $6.00 | $6.10 | $8.00 | $8.00 | $6.10 | $6.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of January 16, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way