IDOT contract 61L75 bid tabulation

Maywood, section 24-00145-00-RS. Let by Illinois DOT on January 16, 2026, Cook, District 01. 6 bids received; low bid $424,594 by A Lamp Concrete Contractors, Inc..

Owner
Illinois DOT
Letting
16 JAN 2026
Pay items
49
Data through
18 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bid
1A Lamp Concrete Contractors, Inc.$424,594Low
2Lindahl Brothers, Inc.$505,990+19%
3Schroeder Asphalt Services, Inc.$515,963+22%
4Everlast Blacktop Inc.$518,161+22%
5K-Five Construction Corporation$522,629+23%
6Alliance Contractors, Inc.$783,302+84%
IDOT contract 61L75: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. A Lamp Concrete Contractors, Inc.2. Lindahl Brothers, Inc.3. Schroeder Asphalt Services, Inc.4. Everlast Blacktop Inc.5. K-Five Construction Corporation6. Alliance Contractors, Inc.
1PVC CS pipe repl 10" (XX006448)LF60$450.00$290.00$615.00$291.00$290.00$1,080.00
2Washout basin (X0326806)LS1$1,000.00$2,500.00$1,200.00$900.00$2,500.00$500.00
3Detectable warn SPL (X4240800)SF60$45.00$60.00$92.00$94.00$60.00$50.00
4HMA surf rem var DP (X4401198)SY4,600$5.25$13.00$6.00$5.90$8.50$9.00
5Connect EX manhole (X6020399)EACH1$1,250.00$1,875.00$2,800.00$3,500.00$1,875.00$2,340.00
6FR & lids adjust SPL (X6030310)EACH11$825.00$1,250.00$1,275.00$1,100.00$1,250.00$1,176.00
7Temp info signing (X7200061)SF51.40$25.00$16.00$20.00$40.00$15.00$35.00
8Temp pavement (Z0062456)SY710$5.00$36.00$25.00$74.00$42.91$1.00
9Tree trunk protection (20101100)EACH8$50.00$221.95$245.00$180.00$125.00$100.00
10Tree root pruning (20101200)EACH8$50.00$101.75$125.00$180.00$125.00$100.00
11Trench backfill (20800150)CY60$66.00$42.00$67.00$70.00$42.00$127.00
12Topsoil F & P 4 (21101615)SY200$7.15$4.00$6.00$8.00$22.00$2.00
13Sodding salt tolerant (25200110)SY200$25.50$35.00$42.00$20.00$40.00$45.00
14Supple watering (25200200)UNIT10$0.01$50.00$58.00$1.00$40.00$300.00
15Inlet filters (28000510)EACH18$15.00$200.00$250.00$170.00$200.00$70.00
16Bit matls tack CT (40600290)LB3,100$0.01$0.01$0.01$0.01$1.17$0.01
17Long joint sealant (40600370)LF975$10.65$10.65$12.50$10.00$13.32$13.00
18Mix CR JTS flangewys (40600400)TON20$100.00$385.00$300.00$600.00$650.00$700.00
19HMA surf rem butt JT (40600982)SY35$69.00$20.00$15.00$67.00$130.00$75.00
20HMA BC IL-9.5 N50 (40602978)TON400$110.00$137.00$105.00$113.75$138.00$130.00
21HMA SC IL-9.5 D N50 (40604060)TON525$105.00$137.00$98.00$132.45$125.00$120.00
22Protective coat (42101300)SY160$0.01$1.00$1.20$7.00$1.00$0.01
23PCC driveway pavt 7 (42300300)SY10$285.00$114.00$230.00$250.00$114.00$180.00
24PC conc sidewalk 5 (42400200)SF1,600$9.50$12.50$12.30$15.00$12.50$17.00
25PC conc sidewalk 8 (42400410)SF500$15.00$14.50$16.00$16.50$14.50$20.00
26Drive pavement rem (44000200)SY10$55.00$20.00$50.00$18.00$20.00$120.00
27Comb curb gutter rem (44000500)LF150$12.25$16.00$12.00$13.00$16.00$50.00
28Sidewalk rem (44000600)SF2,150$1.75$3.50$2.95$2.00$3.50$12.00
29CL B patch T1 8 (44200929)SY120$115.00$185.00$285.00$270.00$185.00$290.00
30CL B patch T2 8 (44200934)SY235$80.00$172.00$230.00$140.00$172.00$290.00
31CL B patch T3 8 (44200942)SY235$75.00$168.00$230.00$140.00$168.00$290.00
32CL B patch T4 8 (44200944)SY120$90.00$168.00$230.00$175.00$168.00$290.00
33VV reconst (60266100)EACH1$3,350.00$2,300.00$3,050.00$2,000.00$2,300.00$3,125.00
34FR & lids adjust (60300305)EACH2$750.00$850.00$825.00$900.00$850.00$516.00
35FR & lids T1 OL (60406000)EACH1$475.00$500.00$625.00$850.00$500.00$516.00
36FR & lids T1 CL (60406100)EACH1$475.00$500.00$625.00$850.00$500.00$516.00
37Comb CC&G TB6.12 mod (60604100)LF150$45.25$55.00$62.00$58.00$55.00$70.00
38Mobilization (67100100)LS1$25,000$30,000$18,000$20,532$32,000$90,000
39TR cont & prot 701501 (70102620)LS1$92,750$4,600.00$14,000$30,000$19,800$93,300
40TR cont & prot 701701 (70102635)LS1$1.00$1.00$1.00$400.00$1.00$100.00
41TR cont & prot 701801 (70102640)LS1$1.00$1.00$1.00$400.00$1.00$100.00
42Short term pavt mking (70300100)LF1,700$0.01$1.00$3.00$2.00$1.00$1.00
43SHRT TRM pavt MK rem (70300150)SF575$0.01$1.00$4.00$2.00$2.00$2.00
44Temp PVT MK L24 T4 tape (70307210)LF150$0.10$8.00$9.00$15.00$17.00$8.00
45THPL PVT MK LTR & sym (78000100)SF40$6.00$6.10$7.00$7.00$6.10$6.00
46THPL PVT MK line 4 (78000200)LF3,100$0.95$1.05$2.25$1.40$1.05$0.95
47THPL PVT MK line 6 (78000400)LF900$2.00$1.55$2.25$2.40$1.55$2.00
48THPL PVT MK line 12 (78000600)LF20$4.00$3.10$4.50$5.00$3.10$4.00
49THPL PVT MK line 24 (78000650)LF150$6.00$6.10$8.00$8.00$6.10$6.00
IDOT contract 61L75: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

Every contract let that day: IDOT letting of January 16, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy