A Lamp Concrete Contractors, Inc.: IDOT bid record

A Lamp Concrete Contractors, Inc. submitted 153 bids on Illinois DOT contracts in the data, from 15 JAN 2021 to 31 JUL 2026, and was the low bidder on 40 of them (26%). When it was not low, its total sat a median +11% above the low bid.

Owner
Illinois DOT
Low bid volume
$80,054,303
Latest bid
31 JUL 2026
Data through
18 SEP 2026
153Bids
40Low bids
26Win rate, percent
+11%Median gap to the low bid when not low, 113 bids

By year

YearBidsLow bidsWin rate
202119316%
202221629%
202319526%
202431929%
202536925%
202627830%
A Lamp Concrete Contractors, Inc., IDOT: bids and low bids by year of letting

Pay items where it is most often lowest

Pay itemCodeUnitLines bidLowest on the lineIts median priceAll bidders' median
Bit matls tack CT40600290LB134128 (96%)$0.01$0.01
Inlet filters28000510EACH124108 (87%)$15.00$180.20
Sidewalk rem44000600SF13188 (67%)$1.50$3.00
Trainees TPGZ0076604HR8484 (100%)$15.00$15.00
TraineesZ0076600HR8383 (100%)$0.80$0.80
Detectable warnings42400800SF11973 (61%)$27.00$37.00
Reg sub mon66901006CAL DAY10663 (59%)$700.00$820.00
Rem & disp uns matl20201200CY10362 (60%)$20.00$44.80
Comb curb gutter rem44000500LF10761 (57%)$6.60$11.61
Bit matls PR CT40600275LB6058 (97%)$0.01$0.01
Perimeter eros bar28000400LF7951 (65%)$1.00$3.50
Agg subgrade improve30300001CY8350 (60%)$25.00$55.00
A Lamp Concrete Contractors, Inc., IDOT: pay items where its unit price was the lowest on the line

A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.

Who it meets most

A Lamp Concrete Contractors, Inc., IDOT: the firms on the same contracts most often

Latest bids

LetContractDistrictProjectRankIts bidAgainst the low bid
31 JUL 202661K85District 01Rolling Meadows, section 21-00126-00-PV2 of 10$2,888,000+3.0%
12 JUN 202661M44District 01West Dundee, section 24-00059-00-RS3 of 3$928,973+23%
12 JUN 202661M53District 01Wheeling, section 23-00095-00-RS3 of 3$549,446+15%
12 JUN 202680C48District 01Section 2025-2105-RS2 of 2$3,269,937+57%
24 APR 202661L84District 01Carol Stream, section 24-00071-00-RS6 of 7$2,744,970+18%
24 APR 202661M11District 01Kane, section 20-00335-00-FL2 of 2$364,964+70%
24 APR 202661M17District 01Algonquin, section 22-00093-00-PV5 of 6$4,297,973+16%
24 APR 202661M34District 01Hawthormne Woods, section 22-00019-00-RS5 of 5$704,854+36%
24 APR 202661M36District 01Glendale Heights, section 23-00077-00-RS3 of 6$1,052,526+7.0%
24 APR 202661M37District 01Lombard, section 24-00170-00-RS4 of 4$2,078,943+23%
24 APR 202662L85District 01Section 2020-107-RS&SW2 of 2$1,038,972+22%
24 APR 202662X57District 01Section 2024-1024-RS4 of 4$1,865,888+22%
27 FEB 202661L66District 01East Dundee, section 24-00050-00-RS2 of 5$394,0730.0%
27 FEB 202661M16District 01Hoffman Estates, section 23-00114-00-CH1 of 6$838,719Low, 13% under the second
27 FEB 202661M26District 01Schaumburg, section 23-00146-00-PV1 of 4$12,659,993Low, 3.0% under the second
27 FEB 202661M27District 01Schaumburg, section 25-00149-01-RS1 of 6$3,554,124Low, 4.0% under the second
27 FEB 202661M28District 01Schaumburg, section 25-00149-02-RS1 of 7$3,964,130Low, 3.0% under the second
27 FEB 202661M31District 01Hoffman Estates, section 22-00111-00-RS1 of 6$631,786Low, 3.0% under the second
27 FEB 202661M32District 01Harwood Heights, section 22-00069-00-RS1 of 6$839,740Low, 2.0% under the second
16 JAN 202661K16District 01Franklin Park, section 17-00083-02-PV6 of 10$4,084,957+7.0%
16 JAN 202661L36District 01Downers Grove, section 23-00121-00-CH6 of 10$2,274,925+8.0%
16 JAN 202661L44District 01Wood Dale, section 23-00057-00-RS2 of 7$964,678+8.0%
16 JAN 202661L75District 01Maywood, section 24-00145-00-RS1 of 6$424,594Low, 19% under the second
16 JAN 202661L89District 01Brookfield, section 25-00138-00-RS7 of 7$2,428,977+26%
16 JAN 202661L90District 01Forest Park, section 25-00121-00-RS1 of 1$3,554,981Low
A Lamp Concrete Contractors, Inc.: latest IDOT bids in the data

How this record was read

IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

  • Every bid counted here matched its published total to within one dollar; IDOT's rank decides who was low.
  • The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
  • A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.

A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy