A Lamp Concrete Contractors, Inc.: IDOT bid record
A Lamp Concrete Contractors, Inc. submitted 153 bids on Illinois DOT contracts in the data, from 15 JAN 2021 to 31 JUL 2026, and was the low bidder on 40 of them (26%). When it was not low, its total sat a median +11% above the low bid.
- Owner
- Illinois DOT
- Low bid volume
- $80,054,303
- Latest bid
- 31 JUL 2026
- Data through
- 18 SEP 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2021 | 19 | 3 | 16% |
| 2022 | 21 | 6 | 29% |
| 2023 | 19 | 5 | 26% |
| 2024 | 31 | 9 | 29% |
| 2025 | 36 | 9 | 25% |
| 2026 | 27 | 8 | 30% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Bit matls tack CT | 40600290 | LB | 134 | 128 (96%) | $0.01 | $0.01 |
| Inlet filters | 28000510 | EACH | 124 | 108 (87%) | $15.00 | $180.20 |
| Sidewalk rem | 44000600 | SF | 131 | 88 (67%) | $1.50 | $3.00 |
| Trainees TPG | Z0076604 | HR | 84 | 84 (100%) | $15.00 | $15.00 |
| Trainees | Z0076600 | HR | 83 | 83 (100%) | $0.80 | $0.80 |
| Detectable warnings | 42400800 | SF | 119 | 73 (61%) | $27.00 | $37.00 |
| Reg sub mon | 66901006 | CAL DAY | 106 | 63 (59%) | $700.00 | $820.00 |
| Rem & disp uns matl | 20201200 | CY | 103 | 62 (60%) | $20.00 | $44.80 |
| Comb curb gutter rem | 44000500 | LF | 107 | 61 (57%) | $6.60 | $11.61 |
| Bit matls PR CT | 40600275 | LB | 60 | 58 (97%) | $0.01 | $0.01 |
| Perimeter eros bar | 28000400 | LF | 79 | 51 (65%) | $1.00 | $3.50 |
| Agg subgrade improve | 30300001 | CY | 83 | 50 (60%) | $25.00 | $55.00 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| R. W. Dunteman Company | 86 | 43 of 86 |
| Plote Construction, Inc. | 66 | 28 of 66 |
| Schroeder Asphalt Services, Inc. | 61 | 23 of 61 |
| Alliance Contractors, Inc. | 59 | 21 of 59 |
| K-Five Construction Corporation | 56 | 32 of 56 |
| Builders Paving, LLC | 54 | 27 of 54 |
| Martam Construction Incorporated | 51 | 20 of 51 |
| Acura Inc. | 30 | 12 of 30 |
| Copenhaver Construction, Inc. | 24 | 4 of 24 |
| J. A. Johnson Paving Company | 23 | 9 of 23 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 31 JUL 2026 | 61K85 | District 01 | Rolling Meadows, section 21-00126-00-PV | 2 of 10 | $2,888,000 | +3.0% |
| 12 JUN 2026 | 61M44 | District 01 | West Dundee, section 24-00059-00-RS | 3 of 3 | $928,973 | +23% |
| 12 JUN 2026 | 61M53 | District 01 | Wheeling, section 23-00095-00-RS | 3 of 3 | $549,446 | +15% |
| 12 JUN 2026 | 80C48 | District 01 | Section 2025-2105-RS | 2 of 2 | $3,269,937 | +57% |
| 24 APR 2026 | 61L84 | District 01 | Carol Stream, section 24-00071-00-RS | 6 of 7 | $2,744,970 | +18% |
| 24 APR 2026 | 61M11 | District 01 | Kane, section 20-00335-00-FL | 2 of 2 | $364,964 | +70% |
| 24 APR 2026 | 61M17 | District 01 | Algonquin, section 22-00093-00-PV | 5 of 6 | $4,297,973 | +16% |
| 24 APR 2026 | 61M34 | District 01 | Hawthormne Woods, section 22-00019-00-RS | 5 of 5 | $704,854 | +36% |
| 24 APR 2026 | 61M36 | District 01 | Glendale Heights, section 23-00077-00-RS | 3 of 6 | $1,052,526 | +7.0% |
| 24 APR 2026 | 61M37 | District 01 | Lombard, section 24-00170-00-RS | 4 of 4 | $2,078,943 | +23% |
| 24 APR 2026 | 62L85 | District 01 | Section 2020-107-RS&SW | 2 of 2 | $1,038,972 | +22% |
| 24 APR 2026 | 62X57 | District 01 | Section 2024-1024-RS | 4 of 4 | $1,865,888 | +22% |
| 27 FEB 2026 | 61L66 | District 01 | East Dundee, section 24-00050-00-RS | 2 of 5 | $394,073 | 0.0% |
| 27 FEB 2026 | 61M16 | District 01 | Hoffman Estates, section 23-00114-00-CH | 1 of 6 | $838,719 | Low, 13% under the second |
| 27 FEB 2026 | 61M26 | District 01 | Schaumburg, section 23-00146-00-PV | 1 of 4 | $12,659,993 | Low, 3.0% under the second |
| 27 FEB 2026 | 61M27 | District 01 | Schaumburg, section 25-00149-01-RS | 1 of 6 | $3,554,124 | Low, 4.0% under the second |
| 27 FEB 2026 | 61M28 | District 01 | Schaumburg, section 25-00149-02-RS | 1 of 7 | $3,964,130 | Low, 3.0% under the second |
| 27 FEB 2026 | 61M31 | District 01 | Hoffman Estates, section 22-00111-00-RS | 1 of 6 | $631,786 | Low, 3.0% under the second |
| 27 FEB 2026 | 61M32 | District 01 | Harwood Heights, section 22-00069-00-RS | 1 of 6 | $839,740 | Low, 2.0% under the second |
| 16 JAN 2026 | 61K16 | District 01 | Franklin Park, section 17-00083-02-PV | 6 of 10 | $4,084,957 | +7.0% |
| 16 JAN 2026 | 61L36 | District 01 | Downers Grove, section 23-00121-00-CH | 6 of 10 | $2,274,925 | +8.0% |
| 16 JAN 2026 | 61L44 | District 01 | Wood Dale, section 23-00057-00-RS | 2 of 7 | $964,678 | +8.0% |
| 16 JAN 2026 | 61L75 | District 01 | Maywood, section 24-00145-00-RS | 1 of 6 | $424,594 | Low, 19% under the second |
| 16 JAN 2026 | 61L89 | District 01 | Brookfield, section 25-00138-00-RS | 7 of 7 | $2,428,977 | +26% |
| 16 JAN 2026 | 61L90 | District 01 | Forest Park, section 25-00121-00-RS | 1 of 1 | $3,554,981 | Low |
How this record was read
IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
- Every bid counted here matched its published total to within one dollar; IDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.