IDOT contract 61M16 bid tabulation

Hoffman Estates, section 23-00114-00-CH. Let by Illinois DOT on February 27, 2026, Cook, District 01. 6 bids received; low bid $838,719 by A Lamp Concrete Contractors, Inc..

Owner
Illinois DOT
Letting
27 FEB 2026
Pay items
98
Data through
18 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bid
1A Lamp Concrete Contractors, Inc.$838,719Low
2Landmark Contractors, Inc.$946,799+13%
3D'Land Construction, LLC$958,224+14%
4K-Five Construction Corporation$982,954+17%
5Schroeder Asphalt Services, Inc.$994,781+19%
6Alliance Contractors, Inc.$1,158,005+38%
IDOT contract 61M16: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. A Lamp Concrete Contractors, Inc.2. Landmark Contractors, Inc.3. D'Land Construction, LLC4. K-Five Construction Corporation5. Schroeder Asphalt Services, Inc.6. Alliance Contractors, Inc.
1T-acer miy mor 2-1/2 (A2000320)EACH3$500.00$525.00$603.75$525.00$589.00$525.00
2T-carp carol 2-1/2 (A2002520)EACH4$500.00$550.00$632.50$550.00$615.00$550.00
3T-celtis occid 2-1/2 (A2002920)EACH4$600.00$550.00$632.50$550.00$615.00$550.00
4T-ulmus X FRNTR 2.5 (A2008745)EACH2$600.00$500.00$575.00$500.00$575.00$500.00
5T-syring ret TF 2-1/2 (B2006220)EACH2$600.00$500.00$575.00$500.00$575.00$500.00
6Temp access- com ent (X4022000)EACH9$250.00$670.72$300.00$550.00$200.00$1.00
7Temporary sidewalk (X4240114)SF300$5.00$10.50$15.00$20.00$20.00$9.50
8CC&G RMVL repl > 10FT (X4400503)LF868$36.00$78.15$45.00$45.00$51.50$80.00
9CB TA 4 dia W/SPL F&G (X6022712)EACH3$3,750.00$5,172.00$5,400.00$4,950.00$3,750.00$8,000.00
10Inlets TA T3F&G SPL (X6023206)EACH3$2,075.00$2,500.00$3,800.00$2,550.00$2,075.00$7,000.00
11San MH adj new T1F CL (X6026056)EACH6$1,365.00$1,155.15$1,250.00$1,550.00$1,365.00$1,500.00
12Comb CC&G TB6.12 SPL (X6064200)LF1,549$31.00$42.70$36.00$40.00$44.00$50.00
13Traf cont & prot SPL (X7010216)LS1$82,000$16,000$56,000$137,678$32,000$16,000
14Temp info signing (X7200061)SF192$12.00$15.00$17.25$15.00$15.00$15.00
15Rebld EX DBL handhole (X8140238)EACH1$4,014.00$4,010.00$4,625.00$4,014.00$4,500.00$9,155.00
16Temp TR signal timing (X8900104)EACH2$680.00$680.00$785.00$680.00$800.00$2,123.00
17Tree remov 6-15 (20100110)UNIT23$31.00$30.00$40.00$30.00$50.00$30.00
18Tree remov over 15 (20100210)UNIT34$41.00$40.00$50.00$40.00$79.00$40.00
19Temporary fence (20101000)LF25$10.00$5.00$5.75$5.00$6.50$5.00
20Earth excavation (20200100)CY460$44.00$47.20$30.00$62.10$55.00$40.00
21Rem & disp uns matl (20201200)CY260$5.00$53.65$45.00$69.31$60.00$40.00
22Furnished excavation (20400800)CY430$5.00$64.70$45.00$58.10$48.00$10.00
23Trench backfill (20800150)CY5$200.00$58.35$75.00$60.00$220.00$100.00
24Geotech fab F/GR stab (21001000)SY500$2.00$3.70$4.00$0.01$2.50$1.00
25Topsoil F & P var DP (21101600)SY912$18.00$5.00$5.75$5.00$5.75$5.00
26Topsoil F & P 6 (21101625)SY1,465$6.50$5.00$5.75$5.00$5.75$5.00
27Seeding CL 1 (25000100)ACRE0.50$4,840.00$3,500.00$4,025.00$3,500.00$4,300.00$3,500.00
28Nitrogen fert nutr (25000400)LB49$1.00$1.00$1.15$1.00$2.00$1.00
29Phosphorus fert nutr (25000500)LB49$1.00$1.00$1.15$1.00$2.00$1.00
30Potassium fert nutr (25000600)LB49$1.00$1.00$1.15$1.00$2.00$1.00
31Erosion contr blanket (25100630)SY2,377$2.00$2.00$2.30$2.00$2.40$2.00
32Supple watering (25200200)UNIT2$200.00$0.01$0.01$0.01$1.00$0.01
33Temp eros contr seed (28000250)LB53$0.10$1.00$1.15$1.00$2.00$1.00
34Perimeter eros bar (28000400)LF1,959$1.00$2.75$3.16$2.75$3.50$2.75
35Inlet filters (28000510)EACH14$15.00$233.30$250.00$175.00$250.00$50.00
36Temp eros contr blank (28001100)SY2,377$0.10$1.00$1.15$1.00$2.00$1.00
37Agg base cse B 4 (35101600)SY2,363$7.50$9.95$8.00$5.50$9.60$5.75
38Agg base cse B 6 (35101800)SY815$10.25$11.75$12.00$6.50$11.25$8.75
39PCC bse cse 7 1/2 (35300210)SY193$68.25$58.50$20.00$90.00$123.00$90.00
40Bit matls tack CT (40600290)LB2,857$0.01$0.10$0.01$0.01$0.01$0.01
41HMA surf rem butt JT (40600982)SY45$20.00$50.00$28.75$25.00$20.00$25.00
42P HMA BC IL-4.75 N50 (40603200)TON176$138.00$140.00$172.50$174.00$130.00$150.00
43HMA SC IL-9.5 D N50 (40604060)TON357$100.00$125.00$130.00$108.00$95.00$113.00
44Protective coat (42001300)SY3,035$0.01$1.80$0.50$0.01$1.40$0.01
45PCC driveway pavt 8 (42300400)SY815$110.00$85.70$95.00$90.00$123.00$97.00
46PC conc sidewalk 5 (42400200)SF14,943$8.25$8.60$9.50$7.65$10.30$9.50
47Detectable warnings (42400800)SF366$27.00$31.50$35.00$24.00$41.00$20.00
48Pavement rem (44000100)SY1,338$15.00$13.10$16.00$15.00$16.00$40.00
49HMA surf rem 2 1/4 (44000158)SY3,992$4.85$6.00$7.00$5.31$5.00$6.00
50Drive pavement rem (44000200)SY523$12.00$13.75$15.00$15.50$17.00$30.00
51Comb curb gutter rem (44000500)LF2,320$6.50$12.65$8.00$9.50$9.00$30.00
52Sidewalk rem (44000600)SF8,941$1.35$1.50$1.15$1.60$2.90$3.00
53CL D patch T1 8 (44201737)SY50$40.00$160.00$114.00$42.00$90.00$99.00
54CL D patch T2 8 (44201741)SY50$40.00$150.00$114.00$42.00$90.00$99.00
55CL D patch T3 8 (44201745)SY50$40.00$130.00$114.00$42.00$90.00$99.00
56CL D patch T4 8 (44201747)SY50$40.00$120.00$114.00$42.00$90.00$99.00
57Storm sew CL A 1 12 (550A0050)LF10$78.00$311.30$115.00$150.00$78.00$500.00
58Storm sewer rem 12 (55100500)LF53$58.00$20.30$15.00$10.00$58.00$10.00
59CB adjust (60250200)EACH1$450.00$270.15$450.00$395.00$450.00$500.00
60CB adj new T1F OL (60250400)EACH2$895.00$707.90$750.00$705.00$900.00$750.00
61CB adj new T1F CL (60250500)EACH2$895.00$707.90$750.00$705.00$900.00$750.00
62CB adj new T3F&G (60250600)EACH2$1,030.00$906.20$950.00$725.00$1,030.00$750.00
63Man adj new T1F CL (60255800)EACH5$915.00$707.80$750.00$705.00$915.00$750.00
64Man recon new T1F CL (60258200)EACH1$1,575.00$1,507.00$1,850.00$1,750.00$1,575.00$2,000.00
65VV adj new T1F CL (60265900)EACH4$915.00$707.80$750.00$705.00$915.00$1,000.00
66FR & grates adjust (60300105)EACH1$450.00$270.15$450.00$395.00$450.00$500.00
67Remov catch bas (60500050)EACH1$1,400.00$500.00$500.00$450.00$450.00$500.00
68Remov inlets (60500060)EACH4$1,285.00$335.00$500.00$250.00$1,285.00$300.00
69Non SPL waste disposl (66900200)CY35$100.00$117.20$105.00$139.75$105.00$171.00
70Soil disposal analy (66900530)EACH2$865.00$850.00$1,668.00$1,450.00$950.00$1,450.00
71Reg sub P-const plan (66901001)LS1$5,200.00$5,000.00$3,565.00$3,100.00$5,700.00$3,100.00
72Reg sub F con report (66901003)LS1$500.00$500.00$1,380.00$1,200.00$565.00$1,200.00
73Reg sub mon (66901006)CAL DAY30$100.00$750.00$782.00$680.00$850.00$680.00
74Mobilization (67100100)LS1$50,000$55,500$55,000$51,000$32,000$48,389
75Changeable message SN (70107025)CAL DAY120$1.00$35.00$34.50$35.00$32.00$35.00
76Short term pavt mking (70300100)LF1,534$0.01$1.00$3.00$0.01$3.00$1.00
77SHRT TRM pavt MK rem (70300150)SF385$0.01$3.00$2.00$8.16$3.00$1.00
78Temp PVT MK LTR & sym paint (70300211)SF126$0.01$1.75$2.00$1.75$1.45$1.75
79Temp PVT MK line 4 - paint (70300221)LF4,331$0.01$0.50$0.40$0.50$0.45$0.50
80Temp PVT MK line 6 - paint (70300241)LF294$0.01$0.75$0.61$0.75$0.50$0.75
81Temp PVT MK line 24 - paint (70300281)LF44$0.01$3.00$1.84$3.00$2.40$3.00
82Temp PVT MK L4 T4 tape (70307120)LF1,534$0.01$1.30$1.38$1.30$3.00$1.30
83Sign panel T1 (72000100)SF29$25.00$37.50$34.50$37.50$32.00$37.50
84Sign panel T2 (72000200)SF20$30.00$45.00$51.75$45.00$40.00$45.00
85Remov sin pan assy TA (72400100)EACH3$150.00$175.00$120.75$175.00$60.00$175.00
86Remov sin pan assy TB (72400200)EACH2$150.00$175.00$120.75$175.00$138.00$175.00
87Remov sign panel T2 (72400320)SF10$20.00$25.00$31.62$25.00$25.00$25.00
88Teles STL sin support (72800100)LF92$20.00$25.00$21.00$25.00$23.00$25.00
89Mod ureth PM LTR-sym (78009000)SF352$6.25$6.00$7.00$8.50$8.00$6.95
90Mod ureth PM line 4 (78009004)LF3,179$0.95$0.90$1.04$1.05$1.25$1.05
91Mod ureth PM line 6 (78009006)LF703$1.50$1.50$3.50$1.57$2.00$1.75
92Mod ureth PM line 12 (78009012)LF372$3.00$3.00$5.75$4.25$3.85$3.45
93Mod ureth PM line 24 (78009024)LF72$6.25$6.00$11.00$8.50$7.90$6.95
94PVT MKG rem grinding (78300201)SF2,509$1.00$1.12$1.73$1.25$1.00$1.25
95PVT MKG rem WTR blast (78300202)SF1,268$5.00$3.85$4.31$2.40$1.00$2.40
96Det loop T1 (88600100)LF536$29.76$29.76$34.25$29.76$35.00$85.20
97Temp TR sig install (89000100)EACH2$16,397$16,397$18,950$16,397$19,250$58,625
98Rebuild EX handhole (89502376)EACH1$3,650.00$3,650.00$4,198.00$3,650.00$4,250.00$8,327.00
IDOT contract 61M16: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

Every contract let that day: IDOT letting of February 27, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy