D'Land Construction, LLC: IDOT bid record
D'Land Construction, LLC submitted 24 bids on Illinois DOT contracts in the data, from 15 JAN 2021 to 24 APR 2026, and was the low bidder on 4 of them (17%). When it was not low, its total sat a median +16% above the low bid.
- Owner
- Illinois DOT
- Low bid volume
- $7,124,834
- Latest bid
- 24 APR 2026
- Data through
- 18 SEP 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2021 | 3 | 0 | 0% |
| 2022 | 1 | 0 | 0% |
| 2024 | 4 | 0 | 0% |
| 2025 | 9 | 3 | 33% |
| 2026 | 7 | 1 | 14% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Sidewalk rem | 44000600 | SF | 24 | 10 (42%) | $2.00 | $3.00 |
| Bit matls tack CT | 40600290 | LB | 17 | 8 (47%) | $0.10 | $0.01 |
| Supple watering | 25200200 | UNIT | 16 | 6 (38%) | $23.55 | $10.00 |
| Trainees TPG | Z0076604 | HR | 6 | 6 (100%) | $15.00 | $15.00 |
| Trainees | Z0076600 | HR | 6 | 6 (100%) | $0.80 | $0.80 |
| Pavement rem | 44000100 | SY | 13 | 5 (38%) | $18.00 | $20.30 |
| Drive pavement rem | 44000200 | SY | 18 | 4 (22%) | $15.00 | $20.00 |
| Trench backfill | 20800150 | CY | 13 | 4 (31%) | $45.00 | $55.00 |
| Agg base cse B 4 | 35101600 | SY | 9 | 4 (44%) | $7.00 | $10.00 |
| Bit matls PR CT | 40600275 | LB | 6 | 4 (67%) | $0.01 | $0.01 |
| Earth excavation | 20200100 | CY | 20 | 3 (15%) | $55.00 | $48.00 |
| Comb curb gutter rem | 44000500 | LF | 16 | 3 (19%) | $9.00 | $11.61 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Alliance Contractors, Inc. | 20 | 7 of 20 |
| A Lamp Concrete Contractors, Inc. | 10 | 8 of 10 |
| Triggi Construction, Inc. | 9 | 6 of 9 |
| Schroeder Asphalt Services, Inc. | 8 | 4 of 8 |
| Landmark Contractors, Inc. | 8 | 2 of 8 |
| R. W. Dunteman Company | 8 | 4 of 8 |
| K-Five Construction Corporation | 7 | 4 of 7 |
| Martam Construction Incorporated | 7 | 0 of 7 |
| Acura Inc. | 7 | 5 of 7 |
| Plote Construction, Inc. | 6 | 4 of 6 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 24 APR 2026 | 61L84 | District 01 | Carol Stream, section 24-00071-00-RS | 3 of 7 | $2,508,636 | +8.0% |
| 24 APR 2026 | 61M35 | District 01 | Harvard, section 21-00067-00-SW | 5 of 5 | $373,812 | +12% |
| 24 APR 2026 | 61M36 | District 01 | Glendale Heights, section 23-00077-00-RS | 6 of 6 | $1,296,738 | +32% |
| 27 FEB 2026 | 61M16 | District 01 | Hoffman Estates, section 23-00114-00-CH | 3 of 6 | $958,224 | +14% |
| 16 JAN 2026 | 61K16 | District 01 | Franklin Park, section 17-00083-02-PV | 8 of 10 | $4,388,175 | +14% |
| 16 JAN 2026 | 61L36 | District 01 | Downers Grove, section 23-00121-00-CH | 3 of 10 | $2,183,127 | +4.0% |
| 16 JAN 2026 | 61L42 | District 01 | Lake Forest, section 13-00095-00-CH | 1 of 5 | $3,663,043 | Low, 1.0% under the second |
| 07 NOV 2025 | 61J94 | District 01 | Schaumburg, section 19-00133-00-BT | 5 of 9 | $1,213,796 | +22% |
| 07 NOV 2025 | 61L98 | District 01 | Mount Prospect, section 23-00179-00-RS | 2 of 6 | $1,780,597 | 0.0% |
| 13 JUN 2025 | 61L34 | District 01 | Skokie, section 13-00295-00-BT | 4 of 7 | $2,325,644 | +10% |
| 25 APR 2025 | 61L29 | District 01 | Bloomingdale, section 20-00073-00-RS | 6 of 10 | $1,698,791 | +11% |
| 07 MAR 2025 | 61L05 | District 01 | Lake Forest, section 19-00093-00-SW | 1 of 5 | $2,990,057 | Low, 32% under the second |
| 07 MAR 2025 | 61L10 | District 01 | Bloomingdale, section 23-00080-00-SW | 1 of 5 | $225,598 | Low, 3.0% under the second |
| 07 MAR 2025 | 61L16 | District 01 | Lake Forest, section 23-00099-00-SW | 1 of 6 | $246,136 | Low, 9.0% under the second |
| 07 MAR 2025 | 61L23 | District 01 | Hoffman Estates, section 22-00112-00-RS | 4 of 7 | $1,364,048 | +17% |
| 17 JAN 2025 | 61K98 | District 01 | Batavia, section 22-00088-00-SW | 3 of 8 | $498,956 | +20% |
| 08 NOV 2024 | 61K58 | District 01 | Berkeley, section 18-00036-00-SW | 6 of 6 | $404,683 | +18% |
| 08 NOV 2024 | 61K59 | District 01 | Berkeley, section 20-00038-00-SW | 2 of 6 | $1,557,372 | +6.0% |
| 20 SEP 2024 | 61J71 | District 01 | Crystal Lake, section 21-00131-00-SW | 3 of 5 | $755,528 | +25% |
| 20 SEP 2024 | 62P38 | District 01 | Section 2021-125-SW | 2 of 5 | $1,096,996 | +3.0% |
| 21 JAN 2022 | 61H48 | District 01 | Aurora, section 21-00338-00-RS | 7 of 8 | $1,818,175 | +26% |
| 15 JAN 2021 | 62K93 | District 01 | Section 2020-022-SW | 3 of 3 | $665,445 | +60% |
| 15 JAN 2021 | 62L38 | District 01 | Section 2020-060-SW | 5 of 5 | $578,921 | +83% |
| 15 JAN 2021 | 62L39 | District 01 | Section 2020-061-SW | 2 of 2 | $882,835 | +59% |
How this record was read
IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
- Every bid counted here matched its published total to within one dollar; IDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.