IDOT contract 61M36 bid tabulation

Glendale Heights, section 23-00077-00-RS. Let by Illinois DOT on April 24, 2026, Dupage, District 01. 6 bids received; low bid $979,958 by Builders Paving, LLC.

Owner
Illinois DOT
Letting
24 APR 2026
Pay items
68
Data through
18 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Builders Paving, LLC$979,958Low
2K-Five Construction Corporation$980,7510.0%
3A Lamp Concrete Contractors, Inc.$1,052,526+7.0%
4Schroeder Asphalt Services, Inc.$1,058,591+8.0%
5R. W. Dunteman Company$1,115,950+14%
6D'Land Construction, LLC$1,296,738+32%
IDOT contract 61M36: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Builders Paving, LLC2. K-Five Construction Corporation3. A Lamp Concrete Contractors, Inc.4. Schroeder Asphalt Services, Inc.5. R. W. Dunteman Company6. D'Land Construction, LLC
1PCC drive rem & repl (XX003435)SY1,065$90.00$90.00$102.00$133.00$99.50$98.00
2HMA drive rem & rep (XX006947)SY250$90.00$55.00$35.00$45.00$32.00$98.00
3Sodding salt toler SP (X2520650)SY1,016$26.00$27.75$19.75$30.00$28.00$32.00
4Temp access- priv ent (X4021000)EACH37$50.00$1.00$250.00$85.00$260.00$50.00
5Temp access- road (X4023000)EACH8$150.00$50.00$500.00$300.00$350.00$500.00
6Driveway remov & repl (X4400080)SY47$155.00$100.00$100.00$175.00$180.00$100.00
7CC&G RMVL repl < = 10 (X4400501)LF200$72.50$79.00$59.00$72.50$92.20$65.00
8CC&G RMVL repl > 10FT (X4400503)LF2,300$42.50$50.00$43.00$46.50$70.50$48.00
9CB TA 4 dia W/SPL F&G (X6022712)EACH5$4,500.00$4,500.00$4,500.00$5,100.00$4,500.00$4,612.00
10Sanitary manhole adj (X6026050)EACH5$1,370.00$1,370.00$1,370.00$1,525.00$1,370.00$950.00
11CB TC W/SPL F&G (X6029510)EACH1$2,100.00$2,100.00$2,100.00$2,350.00$2,100.00$2,744.00
12Frames & lids special (X6040205)EACH8$700.00$700.00$700.00$785.00$700.00$645.00
13Temp info signing (X7200061)SF104$15.00$104.00$25.00$21.00$15.00$21.00
14Construction layout (Z0013798)LS1$6,500.00$20,000$5,000.00$9,000.00$6,500.00$12,100
15Drain util STR adj (Z0017400)EACH10$530.00$530.00$530.00$590.00$530.00$650.00
16Drain util STR adj SP (Z0017500)EACH2$1,100.00$1,100.00$1,100.00$1,225.00$1,100.00$1,250.00
17Drainage STR removed (Z0018700)EACH5$2,200.00$2,200.00$2,200.00$2,425.00$2,200.00$500.00
18Tree trunk protection (20101100)EACH2$250.00$100.00$250.00$220.00$250.00$288.00
19Tree root pruning (20101200)EACH2$100.00$100.00$150.00$120.00$300.00$345.00
20Tree prun 1-10 (20101300)EACH2$250.00$50.00$275.00$120.00$250.00$288.00
21Tree prun over 10 (20101350)EACH9$300.00$100.00$275.00$120.00$300.00$345.00
22Rem & disp uns matl (20201200)CY36$50.00$45.00$45.00$65.00$67.50$40.00
23Trench backfill (20800150)CY218$97.00$97.00$97.00$107.00$97.00$44.00
24Geotech fab F/GR stab (21001000)SY1,076$1.00$0.01$0.01$2.00$3.00$4.00
25Supple watering (25200200)UNIT55$25.00$1.00$1.00$22.00$40.00$46.00
26Inlet filters (28000510)EACH18$160.00$160.00$15.00$185.00$160.00$290.00
27Agg subgrade improve (30300001)CY36$50.00$20.00$45.00$70.00$56.25$95.00
28Bit matls tack CT (40600290)LB7,737$0.01$0.01$0.01$0.01$0.01$0.01
29Long joint sealant (40600370)LF2,800$6.00$2.65$4.77$6.00$5.85$6.90
30Mix CR JTS flangewys (40600400)TON50$200.00$50.00$100.00$300.00$332.00$345.00
31HMA surf rem butt JT (40600982)SY164$10.00$5.00$13.75$15.00$26.75$9.20
32HMA BC IL-19.0 N50 (40603080)TON1,581$90.00$75.00$92.25$88.00$85.80$103.00
33HMA SC IL-9.5 D N50 (40604060)TON963$90.00$87.00$94.00$92.50$93.80$103.00
34PC conc sidewalk 5 (42400200)SF4,299$12.00$12.00$8.50$10.00$9.60$11.50
35Detectable warnings (42400800)SF224$30.00$30.00$30.00$44.00$50.50$40.00
36HMA surf rem 4 (44000165)SY10,752$8.00$5.00$5.25$4.30$4.90$11.50
37Sidewalk rem (44000600)SF4,253$1.50$1.50$1.65$2.35$2.55$1.50
38CL D patch T1 8 (44201737)SY275$40.00$28.00$20.00$90.00$26.75$57.50
39CL D patch T2 8 (44201741)SY275$40.00$28.00$20.00$88.00$26.75$57.50
40CL D patch T3 8 (44201745)SY275$40.00$28.00$20.00$85.00$26.75$57.50
41CL D patch T4 8 (44201747)SY275$40.00$28.00$20.00$85.00$26.75$57.50
42Storm sew CL A 1 12 (550A0050)LF280$70.00$70.00$70.00$78.00$70.00$107.00
43Storm sew CL A 1 15 (550A0070)LF63$110.00$110.00$110.00$123.00$110.00$136.00
44Storm sew CL A 1 18 (550A0090)LF60$100.00$100.00$100.00$112.00$100.00$116.00
45Storm sew CL A 1 24 (550A0120)LF148$120.00$120.00$120.00$132.00$120.00$166.00
46Storm sewer rem 10 (55100400)LF77$52.00$52.00$52.00$58.00$52.00$15.00
47Storm sewer rem 12 (55100500)LF138$53.00$53.00$53.00$59.00$53.00$16.00
48Storm sewer rem 15 (55100700)LF63$55.00$55.00$55.00$62.00$55.00$20.00
49Storm sewer rem 18 (55100900)LF60$90.00$90.00$90.00$103.00$90.00$22.00
50Storm sewer rem 24 (55101200)LF148$90.00$90.00$90.00$102.00$90.00$26.00
51Pipe underdrain 4 SP (60108100)LF45$30.00$30.00$30.00$35.00$30.00$45.00
52CB reconst (60252800)EACH4$1,200.00$1,200.00$1,200.00$1,350.00$1,200.00$1,850.00
53Mobilization (67100100)LS1$51,500$54,000$60,000$10,000$66,000$75,000
54TR cont & prot 701501 (70102620)LS1$5,000.00$70,000$151,000$12,000$22,499$73,655
55TR cont & prot 701701 (70102635)LS1$100.00$1.00$1.00$1.00$64,000$575.00
56TR cont & prot 701801 (70102640)LS1$5,000.00$1.00$1.00$12,000$2.16$94,000
57Short term pavt mking (70300100)LF552$5.00$0.01$0.01$2.50$1.15$3.00
58SHRT TRM pavt MK rem (70300150)SF2,433$1.00$0.01$0.01$3.00$1.50$0.50
59Temp PVT MK LTR & sym T4 tape (70307100)SF73$0.01$1.75$0.01$15.00$1.75$9.20
60Temp PVT MK L4 T4 tape (70307120)LF2,904$0.01$1.30$0.01$2.00$1.30$1.55
61Temp PVT MK L6 T4 tape (70307130)LF140$0.01$1.90$0.01$2.30$1.90$2.30
62Temp PVT MK L12 T4 tape (70307160)LF764$0.01$3.80$0.01$4.25$3.80$4.60
63Temp PVT MK L24 T4 tape (70307210)LF187$0.01$7.60$0.01$9.00$7.60$9.20
64THPL PVT MK LTR & sym (78000100)SF73$5.75$7.00$7.00$6.50$5.75$7.75
65THPL PVT MK line 4 (78000200)LF2,904$0.85$1.10$1.10$1.00$0.85$1.67
66THPL PVT MK line 6 (78000400)LF140$1.35$1.75$1.75$1.55$1.35$2.30
67THPL PVT MK line 12 (78000600)LF764$2.50$3.50$3.50$2.85$2.50$4.32
68THPL PVT MK line 24 (78000650)LF187$5.75$7.00$7.00$6.25$5.75$7.75
IDOT contract 61M36: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

Every contract let that day: IDOT letting of April 24, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy