IDOT contract 61L05 bid tabulation
Lake Forest, section 19-00093-00-SW. Let by Illinois DOT on March 7, 2025, Lake, District 01. 5 bids received; low bid $2,990,057 by D'Land Construction, LLC.
- Owner
- Illinois DOT
- Letting
- 07 MAR 2025
- Pay items
- 135
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | D'Land Construction, LLC | $2,990,057 | Low |
| 2 | Sjostrom & Sons, Inc. | $3,942,650 | +32% |
| 3 | Alliance Contractors, Inc. | $4,284,536 | +43% |
| 4 | Landmark Contractors, Inc. | $4,642,828 | +55% |
| 5 | Copenhaver Construction, Inc. | $4,748,197 | +59% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. D'Land Construction, LLC | 2. Sjostrom & Sons, Inc. | 3. Alliance Contractors, Inc. | 4. Landmark Contractors, Inc. | 5. Copenhaver Construction, Inc. |
|---|---|---|---|---|---|---|---|---|
| 1 | T-celtis occid 3 (A2002924) | EACH | 4 | $800.00 | $994.32 | $525.00 | $525.00 | $1,000.00 |
| 2 | T-quercus bicol 3 (A2006524) | EACH | 6 | $800.00 | $994.32 | $700.00 | $700.00 | $1,000.00 |
| 3 | T-querc rob long 2 BB (A2007200) | EACH | 1 | $800.00 | $994.32 | $475.00 | $475.00 | $1,000.00 |
| 4 | T-ulmus accol HE 3 (A2008453) | EACH | 2 | $800.00 | $994.32 | $475.00 | $475.00 | $1,100.00 |
| 5 | T-ulmus X FRNTR 3 MH (A2008748) | EACH | 8 | $800.00 | $994.32 | $475.00 | $475.00 | $1,100.00 |
| 6 | S-aronia meln MRT 2.5 (C2000660) | EACH | 46 | $75.00 | $93.21 | $100.00 | $100.00 | $250.00 |
| 7 | S-dier G2X8854 CG 3G (C20023G3) | EACH | 30 | $75.00 | $93.21 | $60.00 | $60.00 | $200.00 |
| 8 | Perennial PLNT bulb T (K0012970) | UNIT | 8 | $1,200.00 | $1,491.47 | $450.00 | $450.00 | $800.00 |
| 9 | P PL ornament T 4" P (K0012975) | UNIT | 5 | $1,200.00 | $1,491.47 | $1,000.00 | $1,000.00 | $700.00 |
| 10 | P PL ornament T gal P (K0012990) | UNIT | 8 | $1,400.00 | $1,740.06 | $2,000.00 | $2,000.00 | $2,000.00 |
| 11 | P PL ornament T 3G P (K0012993) | UNIT | 2 | $3,000.00 | $3,728.69 | $2,750.00 | $2,750.00 | $5,000.00 |
| 12 | Shrub removal (K0026830) | EACH | 25 | $25.00 | $55.93 | $45.00 | $95.00 | $20.00 |
| 13 | Mulch (K1003679) | CY | 26 | $100.00 | $124.29 | $75.00 | $75.00 | $100.00 |
| 14 | Concrete steps (XX000300) | SF | 10 | $350.00 | $288.55 | $500.00 | $750.00 | $600.00 |
| 15 | Trench drain SPL (XX003121) | LF | 24 | $443.00 | $503.84 | $515.00 | $625.00 | $840.00 |
| 16 | Test hole (XX003338) | EACH | 15 | $500.00 | $310.73 | $500.00 | $550.00 | $500.00 |
| 17 | Irrigation system (XX003885) | LS | 1 | $160,490 | $300,000 | $145,900 | $145,900 | $175,000 |
| 18 | Brick wall (XX003915) | LF | 16 | $1,200.00 | $1,909.31 | $2,500.00 | $1,615.00 | $2,000.00 |
| 19 | Recycling receptacle (XX007324) | EACH | 10 | $2,050.00 | $2,879.15 | $2,975.00 | $2,750.00 | $3,300.00 |
| 20 | Column with planter (XX007412) | EACH | 4 | $1,500.00 | $14,255 | $12,000 | $10,800 | $12,000 |
| 21 | Pedestrian ST light (XX007468) | EACH | 18 | $5,870.00 | $6,632.09 | $5,336.00 | $6,731.00 | $6,731.00 |
| 22 | Masonry wall (XX007899) | LF | 76 | $1,200.00 | $1,259.20 | $1,750.00 | $1,325.15 | $1,550.00 |
| 23 | PCC band paver bricks (XX008159) | LF | 1,027 | $45.00 | $57.87 | $91.00 | $133.10 | $43.00 |
| 24 | Temporary ramp SPL (XX008163) | EACH | 25 | $500.00 | $1,638.88 | $1.00 | $650.00 | $1,000.00 |
| 25 | Structural soil (XX008356) | CY | 291 | $265.00 | $350.00 | $400.00 | $350.00 | $220.00 |
| 26 | Planter - 30" dia. (XX008418) | EACH | 38 | $1,280.00 | $2,109.01 | $1,800.00 | $2,225.00 | $3,000.00 |
| 27 | Fill exist vault (XX009047) | CY | 65 | $200.00 | $224.22 | $1,510.00 | $168.00 | $240.00 |
| 28 | Street lighting unit (XX009353) | EACH | 3 | $6,694.00 | $7,563.02 | $6,085.00 | $7,559.00 | $7,559.00 |
| 29 | Landscaping planter (XX009591) | EACH | 4 | $3,320.00 | $4,008.63 | $4,000.00 | $4,450.00 | $4,000.00 |
| 30 | EC C XLP 3-1C#4 1C#6G (XX009704) | LF | 555 | $13.27 | $15.00 | $12.07 | $10.00 | $10.00 |
| 31 | EC C XLP 3-1C#2 1C#6G (XX009705) | LF | 912 | $15.90 | $17.97 | $14.46 | $12.70 | $13.00 |
| 32 | EC C XLP 3-1C#1 1C#6G (XX009706) | LF | 1,199 | $17.00 | $19.18 | $15.43 | $17.20 | $18.00 |
| 33 | Stone curb (X0322983) | LF | 2,278 | $160.00 | $192.65 | $210.00 | $346.00 | $210.00 |
| 34 | Washout basin (X0326806) | LS | 1 | $13,600 | $1,864.34 | $2,500.00 | $3,500.00 | $2,000.00 |
| 35 | Remove exstng BR pav (X0327989) | SF | 1,221 | $5.00 | $6.00 | $10.00 | $2.25 | $3.00 |
| 36 | Trash receptacles (X0327997) | EACH | 10 | $1,850.00 | $2,760.47 | $2,750.00 | $2,375.00 | $3,200.00 |
| 37 | Brick pavers (X0540000) | SF | 6,322 | $25.68 | $36.04 | $23.35 | $29.00 | $38.00 |
| 38 | Conn EX DRG structure (X1200160) | EACH | 4 | $900.00 | $745.74 | $1,425.00 | $1,425.00 | $900.00 |
| 39 | Receptacle outlet (X1400397) | EACH | 21 | $724.00 | $817.82 | $658.00 | $3,188.00 | $3,188.00 |
| 40 | Plant soil mix F & P (X1800003) | CY | 248 | $92.00 | $114.34 | $72.00 | $176.00 | $150.00 |
| 41 | Tree rem < 6 unit dia (X2010106) | UNIT | 21 | $35.00 | $48.47 | $39.00 | $39.00 | $55.00 |
| 42 | Tree grates (X2530008) | EACH | 6 | $5,500.00 | $7,100.00 | $8,480.00 | $6,900.00 | $7,000.00 |
| 43 | Bit matls tack CT SPL (X4060103) | LB | 2,614 | $0.30 | $5.53 | $0.01 | $0.01 | $0.01 |
| 44 | HMA driveway pavt 8 (X4060290) | SY | 34 | $120.00 | $43.50 | $61.99 | $62.00 | $70.00 |
| 45 | PC conc sidewalk 5 SP (X4240430) | SF | 11,094 | $12.00 | $16.00 | $25.50 | $25.70 | $32.00 |
| 46 | Detectable warn SPL (X4240800) | SF | 489 | $40.00 | $37.29 | $60.00 | $55.20 | $48.00 |
| 47 | HMA surf rem var DP (X4401198) | SY | 3,553 | $4.00 | $8.70 | $9.87 | $9.90 | $8.00 |
| 48 | Abandon fill SS (X5509900) | LF | 47 | $145.00 | $105.32 | $125.00 | $125.00 | $65.00 |
| 49 | Trench drain (X6010302) | LF | 89 | $247.00 | $280.96 | $350.00 | $550.00 | $652.00 |
| 50 | FR & lids adjust SPL (X6030310) | EACH | 13 | $950.00 | $1,538.91 | $1,650.00 | $1,650.00 | $800.00 |
| 51 | Comb CC&G TM SPL (X6061815) | LF | 217 | $40.00 | $55.35 | $60.00 | $68.61 | $39.00 |
| 52 | Engrs FLD ofc TY A D1 (X6700407) | CAL MO | 8 | $4,500.00 | $4,000.00 | $500.00 | $3,700.00 | $3,500.00 |
| 53 | Traf cont & prot SPL (X7010216) | LS | 1 | $84,500 | $55,000 | $43,250 | $43,250 | $540,000 |
| 54 | Temp info signing (X7200061) | SF | 288 | $13.00 | $27.34 | $22.00 | $22.00 | $30.00 |
| 55 | Sign support SPL (X7330064) | EACH | 5 | $3,025.00 | $3,417.96 | $2,750.00 | $2,750.00 | $2,400.00 |
| 56 | Maint lighting systm (X8000003) | CAL MO | 8 | $2,079.00 | $2,349.07 | $1,890.00 | $1,980.00 | $1,980.00 |
| 57 | Rem EX junction box (X8130125) | EACH | 16 | $495.00 | $559.31 | $450.00 | $660.00 | $660.00 |
| 58 | Handhole SPL (X8140105) | EACH | 23 | $3,850.00 | $4,350.14 | $3,500.00 | $11,047 | $11,047 |
| 59 | Remov EX LTG cont sal (X8950075) | EACH | 1 | $4,950.00 | $5,593.03 | $4,500.00 | $1,320.00 | $1,320.00 |
| 60 | Benches (Z0003850) | EACH | 9 | $3,000.00 | $8,815.38 | $3,520.00 | $3,300.00 | $3,400.00 |
| 61 | Bicycle racks (Z0003855) | EACH | 3 | $1,200.00 | $1,344.17 | $1,350.00 | $3,500.00 | $1,400.00 |
| 62 | Bollards (Z0004002) | EACH | 7 | $500.00 | $527.92 | $2,600.00 | $1,825.00 | $500.00 |
| 63 | Construction layout (Z0013798) | LS | 1 | $20,000 | $21,005 | $16,900 | $16,900 | $49,000 |
| 64 | Drainage STR removed (Z0018700) | EACH | 2 | $500.00 | $430.61 | $350.00 | $350.00 | $500.00 |
| 65 | Dust control watering (Z0019600) | UNIT | 200 | $15.00 | $12.43 | $1.00 | $50.00 | $100.00 |
| 66 | RR prot liability ins (Z0048665) | LS | 1 | $20,000 | $7,208.79 | $500.00 | $2,500.00 | $22,000 |
| 67 | Trainees (Z0076600) | HR | 1,000 | $0.80 | $0.80 | $0.80 | $0.80 | $0.80 |
| 68 | Trainees TPG (Z0076604) | HR | 1,000 | $15.00 | $15.00 | $15.00 | $15.00 | $15.00 |
| 69 | Tree remov 6-15 (20100110) | UNIT | 32 | $45.00 | $58.41 | $47.00 | $47.00 | $45.00 |
| 70 | Temporary fence (20101000) | LF | 150 | $6.00 | $17.53 | $6.50 | $15.00 | $10.00 |
| 71 | Earth excavation (20200100) | CY | 750 | $46.00 | $88.94 | $40.00 | $112.00 | $65.00 |
| 72 | Rem & disp uns matl (20201200) | CY | 50 | $55.00 | $88.94 | $60.00 | $94.00 | $65.00 |
| 73 | Trench backfill (20800150) | CY | 405 | $50.00 | $33.60 | $23.00 | $23.00 | $51.00 |
| 74 | Geotech fab F/GR stab (21001000) | SY | 150 | $4.00 | $2.49 | $3.00 | $2.15 | $4.00 |
| 75 | Inlet filters (28000510) | EACH | 16 | $180.00 | $236.15 | $250.00 | $250.00 | $200.00 |
| 76 | Agg subgrade improve (30300001) | CY | 50 | $95.00 | $68.65 | $63.00 | $89.15 | $50.00 |
| 77 | Sub gran mat B 2 (31101180) | SY | 565 | $5.00 | $14.94 | $4.00 | $11.50 | $10.00 |
| 78 | Sub gran mat B 4 (31101200) | SY | 2,149 | $7.00 | $16.34 | $7.00 | $17.70 | $11.00 |
| 79 | PCC base course 4" (35300060) | SY | 315 | $50.00 | $83.99 | $162.00 | $128.70 | $90.00 |
| 80 | Hes PCC bse cse 8 (35301100) | SY | 333 | $65.00 | $68.18 | $177.00 | $138.30 | $120.00 |
| 81 | Hes PCC bse cse 10 (35301300) | SY | 116 | $75.00 | $82.92 | $211.00 | $380.00 | $125.00 |
| 82 | PCC bse cse var DP (35301400) | SY | 565 | $160.00 | $206.06 | $160.00 | $270.15 | $100.00 |
| 83 | Long joint sealant (40600370) | LF | 2,025 | $5.00 | $13.17 | $4.00 | $4.00 | $13.00 |
| 84 | Temporary ramp (40600990) | SY | 347 | $35.00 | $11.19 | $55.00 | $55.00 | $20.00 |
| 85 | P HMA BC IL-4.75 N50 (40603200) | TON | 217 | $100.00 | $188.93 | $187.90 | $187.90 | $170.00 |
| 86 | HMA SC IL-9.5 D N70 (40604062) | TON | 326 | $110.00 | $161.58 | $149.36 | $149.40 | $150.00 |
| 87 | Welded wire reinf (42000060) | SY | 333 | $25.00 | $8.70 | $5.00 | $4.85 | $10.00 |
| 88 | PC conc sidewalk 5 (42400200) | SF | 1,400 | $11.00 | $12.17 | $12.25 | $12.75 | $17.00 |
| 89 | Pavement rem (44000100) | SY | 1,000 | $15.00 | $24.95 | $40.00 | $18.85 | $17.00 |
| 90 | Drive pavement rem (44000200) | SY | 20 | $45.00 | $41.88 | $40.00 | $33.25 | $20.00 |
| 91 | Curb rem (44000300) | LF | 243 | $10.00 | $9.60 | $40.00 | $19.15 | $10.00 |
| 92 | Comb curb gutter rem (44000500) | LF | 424 | $10.00 | $20.55 | $40.00 | $19.20 | $10.00 |
| 93 | Sidewalk rem (44000600) | SF | 14,836 | $1.20 | $3.25 | $4.00 | $2.70 | $3.00 |
| 94 | CL D patch T1 6 (44201713) | SY | 39 | $70.00 | $157.84 | $157.95 | $157.95 | $150.00 |
| 95 | CL D patch T2 6 (44201717) | SY | 78 | $70.00 | $125.53 | $151.20 | $151.20 | $120.00 |
| 96 | CL D patch T3 6 (44201721) | SY | 117 | $60.00 | $116.83 | $161.00 | $161.00 | $110.00 |
| 97 | CL D patch T4 6 (44201723) | SY | 533 | $50.00 | $62.14 | $117.00 | $117.00 | $60.00 |
| 98 | Storm sew CL B 1 10 (550B0040) | LF | 201 | $107.00 | $140.05 | $285.00 | $285.00 | $89.00 |
| 99 | Storm sewer rem 10 (55100400) | LF | 62 | $15.00 | $27.14 | $25.00 | $25.00 | $15.00 |
| 100 | Dom wat ser box adj (56500600) | EACH | 2 | $250.00 | $208.69 | $250.00 | $250.00 | $300.00 |
| 101 | Pipe underdr T 2 4 (60108204) | LF | 870 | $25.00 | $34.13 | $40.00 | $65.00 | $20.00 |
| 102 | CB TA 4 dia T1F OL (60200105) | EACH | 1 | $4,561.00 | $4,500.00 | $5,950.00 | $5,950.00 | $5,100.00 |
| 103 | CB TC T1F OL (60206905) | EACH | 4 | $2,447.00 | $3,613.47 | $4,785.00 | $4,785.00 | $2,800.00 |
| 104 | Inlets TB T1F OL (60240210) | EACH | 1 | $1,486.00 | $200.00 | $4,550.00 | $4,550.00 | $3,000.00 |
| 105 | CB adjust (60250200) | EACH | 4 | $550.00 | $170.67 | $450.00 | $450.00 | $800.00 |
| 106 | CB adj new T1F OL (60250400) | EACH | 1 | $950.00 | $559.87 | $1,050.00 | $1,050.00 | $850.00 |
| 107 | CB adj new T8G (60251200) | EACH | 3 | $900.00 | $477.00 | $850.00 | $850.00 | $700.00 |
| 108 | Valve box adj (60266600) | EACH | 5 | $250.00 | $205.58 | $425.00 | $425.00 | $300.00 |
| 109 | Non SPL waste disposl (66900200) | CY | 815 | $95.00 | $139.11 | $82.50 | $133.10 | $100.00 |
| 110 | Soil disposal analy (66900530) | EACH | 5 | $1,375.00 | $1,267.75 | $1,300.00 | $1,300.00 | $1,500.00 |
| 111 | Reg sub P-const plan (66901001) | LS | 1 | $4,620.00 | $5,742.17 | $3,000.00 | $3,000.00 | $3,900.00 |
| 112 | Reg sub F con report (66901003) | LS | 1 | $1,100.00 | $652.52 | $1,500.00 | $1,500.00 | $2,000.00 |
| 113 | Reg sub mon (66901006) | CAL DAY | 15 | $1,100.00 | $913.52 | $700.00 | $700.00 | $200.00 |
| 114 | Mobilization (67100100) | LS | 1 | $169,100 | $230,000 | $712,789 | $243,340 | $328,000 |
| 115 | Changeable message SN (70107025) | CAL DAY | 480 | $31.00 | $37.29 | $30.00 | $30.00 | $45.00 |
| 116 | SHRT TRM pavt MK rem (70300150) | SF | 181 | $0.44 | $0.50 | $0.40 | $2.00 | $1.00 |
| 117 | Temp PVT MK L4 T4 tape (70307120) | LF | 548 | $1.20 | $1.74 | $1.40 | $1.40 | $2.00 |
| 118 | Sign panel T1 (72000100) | SF | 102 | $85.25 | $32.31 | $26.00 | $26.00 | $40.00 |
| 119 | Remov sin pan assy TA (72400100) | EACH | 8 | $55.00 | $155.36 | $125.00 | $125.00 | $85.00 |
| 120 | Remov sign panel T1 (72400310) | SF | 68 | $13.00 | $24.86 | $20.00 | $20.00 | $20.00 |
| 121 | THPL PVT MK LTR & sym (78000100) | SF | 49 | $7.00 | $8.08 | $6.50 | $6.50 | $10.00 |
| 122 | THPL PVT MK line 4 (78000200) | LF | 3,267 | $2.31 | $1.49 | $1.20 | $1.20 | $2.00 |
| 123 | THPL PVT MK line 6 (78000400) | LF | 1,059 | $2.86 | $1.86 | $1.50 | $1.50 | $3.00 |
| 124 | THPL PVT MK line 24 (78000650) | LF | 159 | $6.05 | $8.08 | $6.50 | $6.50 | $10.00 |
| 125 | PVT MKG rem WTR blast (78300202) | SF | 323 | $14.00 | $12.43 | $10.00 | $10.00 | $15.00 |
| 126 | Undrgrd C galvs 4 (81028240) | LF | 605 | $75.00 | $84.76 | $68.20 | $90.30 | $91.00 |
| 127 | Undrgrd C PVC 1 (81028320) | LF | 652 | $16.00 | $18.10 | $14.56 | $20.70 | $21.00 |
| 128 | Undrgrd C PVC 1 1/2 (81028340) | LF | 4,915 | $9.53 | $10.78 | $8.67 | $21.30 | $22.00 |
| 129 | EC C XLP use 3-1C 6 (81702415) | LF | 586 | $9.54 | $11.57 | $9.31 | $7.00 | $7.00 |
| 130 | EC C XLP 3-1C#6 1C#6G (81702417) | LF | 1,512 | $12.45 | $14.07 | $11.32 | $7.80 | $8.00 |
| 131 | EC C XLP use 3-1C 10 (81702450) | LF | 1,352 | $7.62 | $8.61 | $6.93 | $4.30 | $5.00 |
| 132 | LT cont basem 240V200 (82500370) | EACH | 1 | $23,210 | $26,225 | $21,100 | $36,430 | $36,430 |
| 133 | Light pole FDN 24D (83600200) | LF | 105 | $495.00 | $559.31 | $450.00 | $345.30 | $346.00 |
| 134 | Rem LT unit salv (84200500) | EACH | 17 | $303.00 | $341.80 | $275.00 | $660.00 | $660.00 |
| 135 | Rem pole FDN (84200804) | EACH | 17 | $545.00 | $615.24 | $495.00 | $660.00 | $660.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of March 7, 2025. Compiled by Mirage Metrics.