IDOT letting results, November 7, 2025

74 contracts let by Illinois DOT on November 7, 2025, $200,738,010 in low bids, a median of 3 bidders per contract.

Owner
Illinois DOT
Contracts
74
Low bids, total
$200,738,010
Data through
18 SEP 2026

Contracts let that day

ContractProjectDistrictBidsLow bidderLow bidSecond bidGapSource
68B60District 041Gunther Construction, a div of UCM, Inc.$35,946,274IDOT
62U41District 011Lorig Construction Company$22,596,336IDOT
62R63District 016Dunnet Bay Construction Company$15,646,955$16,247,516+4.0%IDOT
70F19District 051Rowe Construction, a div of UCM, Inc.$8,303,728IDOT
61J54Project Number: Whf6-372 / /, section 16-F3000-15-BTDistrict 013Lorig Construction Company$6,927,969$7,233,472+4.0%IDOT
74595District 074Samron Midwest Contracting, Inc.$6,831,745$7,045,980+3.0%IDOT
61L43Schaumburg, section 20-00134-00-RSDistrict 017K-Five Construction Corporation$5,837,039$5,998,937+3.0%IDOT
61L92Lincolnwood, section 16-00061-00-LSDistrict 015Capitol Cement Co., Inc.$5,462,909$5,488,0480.0%IDOT
93847Pittsfield, section 24-00037-00-RSDistrict 062Rees Construction Company of Quincy$5,451,649$7,038,260+29%IDOT
61L88Project Number: S00V-023 / /, section 19-00507-00-BRDistrict 014Dunnet Bay Construction Company$5,134,451$5,873,712+14%IDOT
85785Moline, section 23-00291-00-BTDistrict 026Gensini Excavating, Inc.$5,092,254$5,105,6590.0%IDOT
68F45District 042R. A. Cullinan and Son, a div of UCM, Inc.$5,074,396$6,170,000+22%IDOT
80B69District 011 of 2$4,622,500$4,623,1150.0%IDOT
61L21Rosemont, section 19-00035-00-SPDistrict 012H & H Electric Co.$4,177,932$4,409,000+6.0%IDOT
80B71District 011Central Sweeping of Illinois, LLC$4,010,755IDOT
62R51District 014Iroquois Paving Corporation$3,192,530$3,368,001+5.0%IDOT
64U98District 022Industrial Steel Construction, Inc.$2,988,100$3,203,000+7.0%IDOT
78813District 093Samron Midwest Contracting, Inc.$2,731,937$3,045,603+11%IDOT
61K01Elmhurst, section 17-00188-00-SWDistrict 017Martam Construction Incorporated$2,649,349$2,669,368+1.0%IDOT
61L82Broadview, section 22-00086-00-BRDistrict 015Dunnet Bay Construction Company$2,582,436$2,898,784+12%IDOT
78209District 092Samron Midwest Contracting, Inc.$2,526,591$2,820,826+12%IDOT
89832Project Number: Tkui-239 / /, section 21-00000-00-SPDistrict 042Lovewell Fencing, Inc.$2,498,941$2,749,916+10%IDOT
93843Project Number: 8Llm-141 / /, section 21-00056-09-PVDistrict 064L. W. Rouland Trucking Service, Inc.$2,121,212$2,214,003+4.0%IDOT
78B82District 094Eagle Painting & Maintenance Company, Inc.$2,044,033$2,173,045+6.0%IDOT
80B70District 011Central Sweeping of Illinois, LLC$2,013,220IDOT
61L57Aurora, section 24-00370-00-RSDistrict 013K-Five Construction Corporation$1,786,248$2,172,535+22%IDOT
61L98Mount Prospect, section 23-00179-00-RSDistrict 016PirTano Construction Co., LLC$1,778,510$1,780,5970.0%IDOT
61L79Glen Ellyn, section 24-00086-00-RSDistrict 016K-Five Construction Corporation$1,759,309$1,932,776+10%IDOT
85779Rock Falls, section 19-00137-00-BRDistrict 023Martin & Company Excavating$1,699,166$1,859,068+9.0%IDOT
74B78District 074C-Hill Civil Contractors, Inc.$1,592,673$1,616,369+1.0%IDOT
87843Project Number:, section 21-P4006-03-BTDistrict 034Martin & Company Excavating$1,580,482$1,696,862+7.0%IDOT
87889Sandwich, section 21-00048-00-BRDistrict 032D. Construction, Inc.$1,441,346$1,561,444+8.0%IDOT
78B42District 092Samron Midwest Contracting, Inc.$1,423,409$1,424,2210.0%IDOT
61L78Elmhurst, section 22-00204-00-RSDistrict 016A Lamp Concrete Contractors, Inc.$1,308,888$1,365,675+4.0%IDOT
80B72District 011Central Sweeping of Illinois, LLC$1,303,855IDOT
80B53District 013Eagle Painting & Maintenance Company, Inc.$1,180,528$1,529,442+30%IDOT
80B73District 011ERA-Valdivia Contractors, Inc.$1,110,000IDOT
46944District 023Martin & Company Excavating$1,029,566$1,193,271+16%IDOT
72A62District 062William Charles Construction Company, LLC$1,014,537$1,157,627+14%IDOT
61J94Schaumburg, section 19-00133-00-BTDistrict 019A Lamp Concrete Contractors, Inc.$997,000$1,106,434+11%IDOT
62Y36District 014Fence Masters, Inc.$857,222$937,440+9.0%IDOT
61L83Libertyville, section 23-00127-00-RSDistrict 014Peter Baker & Son Co.$774,012$1,089,048+41%IDOT
72523District 062Freesen, a div of UCM, Inc.$765,687$872,502+14%IDOT
61L97South Elgin, section 24-00059-00-RSDistrict 014Everlast Blacktop Inc.$763,936$810,576+6.0%IDOT
78B23District 093Samron Midwest Contracting, Inc.$758,456$913,006+20%IDOT
64R26District 022Civil Constructors, Inc. d/b/a/ Helm Civil$732,334$997,600+36%IDOT
87890Project Number: Hb68-016 / /, section 21-00145-00-BRDistrict 033Tobey's Construction & Cartage, Inc.$679,036$695,786+2.0%IDOT
87891Project Number: 0Fcr-005 / /, section 22-00146-00-BRDistrict 032Tobey's Construction & Cartage, Inc.$637,458$802,684+26%IDOT
61L80Glen Ellyn, section 24-00087-00-RSDistrict 016Schroeder Asphalt Services, Inc.$603,175$611,004+1.0%IDOT
85783Kewanee, section 22-00111-00-SWDistrict 028Advanced Asphalt Company$535,939$598,981+12%IDOT
64U82District 024Advanced Asphalt Company$529,895$722,406+36%IDOT
74D31District 072Homer Tree Service, Inc.$526,741$805,568+53%IDOT
62Y33District 011RoadSafe Traffic Systems, Inc.$484,900IDOT
93846Project Number: Hs17-651 / /, section 22-00103-02-BRDistrict 065County Contractors, Inc.$474,620$488,885+3.0%IDOT
78B64District 093M & M Concrete, Inc.$396,418$429,369+8.0%IDOT
61L77Hanover Park, section 23-00079-00-SWDistrict 019Triggi Construction, Inc.$359,832$374,008+4.0%IDOT
64U87District 025Phoenix Corporation of the Quad Cities$355,924$389,894+10%IDOT
61L73Project Number:, section 21-P4015-00-BTDistrict 016D. Construction, Inc.$352,856$395,907+12%IDOT
62Y00District 016C & D Recycling Services, Inc.$346,900$398,798+15%IDOT
64U80District 024Advanced Asphalt Company$342,730$529,098+54%IDOT
61L76Maywood, section 24-00144-00-MSDistrict 015Davis Concrete Construction Co.$298,167$332,590+12%IDOT
76U48District 082All States Painting, Inc.$274,243$334,379+22%IDOT
87884Dwight, section 24-00056-00-SWDistrict 036D. Construction, Inc.$230,453$273,187+19%IDOT
72508District 061Homer Tree Service, Inc.$190,542IDOT
78B54District 092E. T. Simonds Construction Company$175,469$178,335+2.0%IDOT
64V05District 023Interstate Maintenance, Incorporated$138,300$145,000+5.0%IDOT
78994District 092Samron Midwest Contracting, Inc.$124,571$297,736+139%IDOT
78B74District 094E. T. Simonds Construction Company$118,588$124,033+5.0%IDOT
64V07District 023M & M Concrete, Inc.$112,000$134,300+20%IDOT
72688District 064Freesen, a div of UCM, Inc.$97,470$136,368+40%IDOT
76U64District 084The Final Connection, Inc.$76,044$80,616+6.0%IDOT
76U50District 082All States Painting, Inc.$56,364$68,401+21%IDOT
64V06District 023All States Painting, Inc.$53,333$56,000+5.0%IDOT
76U47District 082M & M Concrete, Inc.$43,640$44,859+3.0%IDOT
IDOT contracts let on November 7, 2025, largest low bid first

Gap is the second bid over the low bid. Where a contract shows fewer bids than IDOT received, the others did not match their published totals and are left out. Each contract number opens its full bid tabulation.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy