IDOT contract 78B23 bid tabulation
. Let by Illinois DOT on November 7, 2025, Franklin, District 09. 3 bids received; low bid $758,456 by Samron Midwest Contracting, Inc..
- Owner
- Illinois DOT
- Letting
- 07 NOV 2025
- Pay items
- 65
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Samron Midwest Contracting, Inc. | $758,456 | Low |
| 2 | Sierra Bravo Contractors, LLC | $913,006 | +20% |
| 3 | E. T. Simonds Construction Company | $1,177,619 | +55% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Samron Midwest Contracting, Inc. | 2. Sierra Bravo Contractors, LLC | 3. E. T. Simonds Construction Company |
|---|---|---|---|---|---|---|
| 1 | Memb WTRPRF sys B STR (X5810103) | SY | 160 | $18.00 | $37.87 | $42.81 |
| 2 | Traf cont-prot BLR 21 (X7011800) | LS | 1 | $1,500.00 | $7,043.30 | $6,461.80 |
| 3 | Detour signing (X7200203) | LS | 1 | $6,500.00 | $9,345.00 | $10,046 |
| 4 | Construction layout (Z0013798) | LS | 1 | $11,500 | $14,280 | $12,966 |
| 5 | Rock fill - foundatn (Z0054517) | TON | 150 | $35.00 | $53.37 | $71.05 |
| 6 | Tree remov acres (20100500) | ACRE | 0.02 | $78,000 | $96,512 | $414,902 |
| 7 | Earth excavation (20200100) | CY | 53 | $20.00 | $41.04 | $47.98 |
| 8 | Channel excavation (20300100) | CY | 20 | $50.00 | $70.43 | $63.58 |
| 9 | Furnished excavation (20400800) | CY | 323 | $45.00 | $23.60 | $69.84 |
| 10 | Porous gran embank (20700220) | CY | 389 | $50.00 | $74.31 | $130.62 |
| 11 | Trench backfill (20800150) | CY | 4 | $55.00 | $130.01 | $140.83 |
| 12 | Seeding CL 2A (25000210) | ACRE | 0.14 | $20,000 | $25,153 | $32,938 |
| 13 | Seeding CL 7 (25000350) | ACRE | 0.14 | $3,500.00 | $1,380.79 | $1,808.14 |
| 14 | Nitrogen fert nutr (25000400) | LB | 13 | $5.00 | $1.73 | $2.27 |
| 15 | Phosphorus fert nutr (25000500) | LB | 13 | $5.00 | $1.73 | $2.27 |
| 16 | Potassium fert nutr (25000600) | LB | 13 | $5.00 | $1.73 | $2.27 |
| 17 | Agr ground limestone (25000700) | TON | 0.30 | $2,280.00 | $372.77 | $488.13 |
| 18 | Mulch method 2 (25100115) | ACRE | 0.14 | $750.00 | $6,877.50 | $9,006.29 |
| 19 | Erosion contr blanket (25100630) | SY | 695 | $3.00 | $2.36 | $3.09 |
| 20 | Temp eros contr seed (28000250) | LB | 14 | $0.01 | $4.70 | $8.03 |
| 21 | Temp ditch checks (28000305) | LF | 36 | $15.00 | $15.83 | $26.38 |
| 22 | Perimeter eros bar (28000400) | LF | 392 | $7.00 | $6.41 | $12.60 |
| 23 | Stone riprap CL A4 (28100107) | SY | 106 | $65.00 | $56.15 | $59.35 |
| 24 | Filter fabric (28200200) | SY | 106 | $5.00 | $4.31 | $5.36 |
| 25 | Sub gran mat B 4 (31101200) | SY | 514 | $9.00 | $12.67 | $15.87 |
| 26 | Agg surf course TY B (40200800) | TON | 48 | $45.00 | $64.52 | $44.74 |
| 27 | Bit matls tack CT (40600290) | LB | 702 | $0.01 | $0.01 | $0.01 |
| 28 | Long joint sealant (40600370) | LF | 327 | $10.00 | $34.22 | $10.29 |
| 29 | HMA BC IL-9.5FG N70 (40602970) | TON | 96 | $200.00 | $309.50 | $294.76 |
| 30 | HMA SC IL-9.5 D N70 (40604062) | TON | 90 | $215.00 | $334.58 | $318.65 |
| 31 | Welded wire reinf (42000060) | SY | 499 | $5.00 | $17.97 | $21.85 |
| 32 | PCC PVT 10 (42000500) | SY | 374 | $125.00 | $182.37 | $193.43 |
| 33 | Protective coat (42001300) | SY | 499 | $0.01 | $2.22 | $0.99 |
| 34 | Pavement rem (44000100) | SY | 363 | $35.00 | $50.17 | $36.94 |
| 35 | HMA surf rem 1 1/2 (44000155) | SY | 1,038 | $8.50 | $16.28 | $15.50 |
| 36 | Paved SHLD removal (44004250) | SY | 101 | $8.00 | $28.45 | $31.47 |
| 37 | Agg wedge SHLD type B (48102100) | TON | 17 | $145.00 | $94.89 | $72.65 |
| 38 | PCC shoulders 10 (48300500) | SY | 126 | $180.00 | $156.78 | $238.39 |
| 39 | Rem exist struct (50100100) | EACH | 1 | $15,000 | $20,031 | $18,088 |
| 40 | Pipe culvert remov (50105220) | LF | 117 | $15.00 | $19.68 | $36.37 |
| 41 | Structure excavation (50200100) | CY | 1,022 | $0.01 | $21.59 | $28.52 |
| 42 | Rem/disp uns matl-STR (50200450) | CY | 146.90 | $25.00 | $21.09 | $46.26 |
| 43 | Reinf bars, epoxy CTD (50800205) | LB | 15,700 | $2.00 | $1.62 | $1.94 |
| 44 | Temp soil reten systm (52200020) | SF | 544 | $185.00 | $237.02 | $255.36 |
| 45 | Conc box cul (54003000) | CY | 92.30 | $1,200.00 | $1,553.12 | $2,288.60 |
| 46 | PCBC 12X6 (54011206) | LF | 56 | $2,000.00 | $1,398.01 | $1,977.75 |
| 47 | P cul CL A 1 30 (542A0235) | LF | 112 | $125.00 | $141.60 | $156.27 |
| 48 | PRC flar end sec 30 (54213675) | EACH | 1 | $2,350.00 | $2,618.78 | $2,637.00 |
| 49 | Geocomposite wall DR (59100100) | SY | 160 | $8.00 | $19.58 | $22.92 |
| 50 | Man TA 5 dia T1F CL (60221100) | EACH | 1 | $6,455.00 | $5,444.54 | $8,338.77 |
| 51 | Guardrail remov (63200310) | LF | 310 | $6.50 | $20.18 | $16.03 |
| 52 | Fur erect row markers (66600105) | EACH | 8 | $387.00 | $229.06 | $321.27 |
| 53 | Mobilization (67100100) | LS | 1 | $44,000 | $53,771 | $145,638 |
| 54 | Traf cont-prot 701316 (70100100) | EACH | 1 | $40,000 | $16,671 | $17,521 |
| 55 | Traf cont-prot 701306 (70100460) | LS | 1 | $0.01 | $1,200.00 | $8,947.30 |
| 56 | TR cont surveillance (70103815) | CAL DAY | 7 | $0.01 | $2,399.72 | $0.01 |
| 57 | Temp BR traf signals (70106500) | EACH | 1 | $24,000 | $27,038 | $22,403 |
| 58 | Temp rumble strips (70106700) | EACH | 6 | $900.00 | $787.50 | $1,464.61 |
| 59 | Changeable message SN (70107025) | CAL DAY | 28 | $95.00 | $89.99 | $84.75 |
| 60 | Short term pavt mking (70300100) | LF | 68 | $0.01 | $2.85 | $2.71 |
| 61 | SHRT TRM pavt MK rem (70300150) | SF | 23 | $0.01 | $23.83 | $4.48 |
| 62 | Sign panel T1 (72000100) | SF | 2 | $195.00 | $80.80 | $96.82 |
| 63 | Remov sign panel T1 (72400310) | SF | 2 | $0.01 | $34.26 | $69.48 |
| 64 | Mod ureth PM line 4 (78009004) | LF | 1,517 | $6.40 | $5.81 | $6.08 |
| 65 | Raised ref PVT MK rem (78300200) | EACH | 2 | $0.01 | $114.97 | $16.80 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of November 7, 2025. Compiled by Mirage Metrics.