IDOT contract 74B78 bid tabulation
. Let by Illinois DOT on November 7, 2025, Wayne, District 07. 4 bids received; low bid $1,592,673 by C-Hill Civil Contractors, Inc..
- Owner
- Illinois DOT
- Letting
- 07 NOV 2025
- Pay items
- 38
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | C-Hill Civil Contractors, Inc. | $1,592,673 | Low |
| 2 | Samron Midwest Contracting, Inc. | $1,616,369 | +1.0% |
| 3 | E. T. Simonds Construction Company | $1,790,602 | +12% |
| 4 | Sangamo Construction Company | $1,904,922 | +20% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. C-Hill Civil Contractors, Inc. | 2. Samron Midwest Contracting, Inc. | 3. E. T. Simonds Construction Company | 4. Sangamo Construction Company |
|---|---|---|---|---|---|---|---|
| 1 | BR deck grooving long (X5030250) | SY | 3,058 | $10.50 | $9.50 | $10.15 | $8.55 |
| 2 | Drainage scuppers adj (X5230172) | EACH | 56 | $735.00 | $625.00 | $1,165.58 | $1,709.19 |
| 3 | BRD flyash/slag 2 1/2 (Z0012111) | SY | 3,986 | $90.00 | $83.00 | $84.81 | $115.98 |
| 4 | BR deck scar 3/4 (Z0012130) | SY | 3,986 | $43.50 | $58.00 | $59.85 | $42.02 |
| 5 | STR rep con DP = < 5 (Z0012754) | SF | 84 | $225.00 | $200.00 | $292.05 | $404.70 |
| 6 | Deck slab rep (FD-T1) (Z0016001) | SY | 38 | $1,700.00 | $2,000.00 | $2,134.06 | $1,385.54 |
| 7 | Deck slab rep (FD-T2) (Z0016002) | SY | 20 | $1,600.00 | $2,000.00 | $2,153.24 | $997.95 |
| 8 | Diamond grind BR sec (Z0029090) | SY | 3,598 | $14.35 | $12.00 | $12.09 | $12.20 |
| 9 | PCC base cse W 8 (35400300) | SY | 186 | $250.00 | $150.00 | $192.23 | $142.29 |
| 10 | Bit matls tack CT (40600290) | LB | 180 | $10.25 | $0.01 | $0.01 | $10.32 |
| 11 | HMA surf rem butt JT (40600982) | SY | 400 | $33.00 | $25.00 | $40.04 | $33.35 |
| 12 | Temporary ramp (40600990) | SY | 33.40 | $46.00 | $75.00 | $87.30 | $185.06 |
| 13 | HMA SC IL-9.5 C N70 (40604052) | TON | 39.20 | $470.00 | $470.00 | $580.52 | $473.96 |
| 14 | Paved SHLD removal (44004250) | SY | 186 | $94.00 | $60.00 | $59.89 | $71.50 |
| 15 | Agg wedge SHLD type B (48102100) | TON | 8.50 | $315.00 | $190.00 | $67.50 | $265.63 |
| 16 | Conc rem (50102400) | CY | 41.20 | $2,915.00 | $3,250.00 | $3,606.81 | $3,264.24 |
| 17 | Conc struct (50300225) | CY | 8.60 | $7,900.00 | $5,100.00 | $9,793.81 | $13,282 |
| 18 | Conc sup-STR (50300255) | CY | 45.90 | $4,640.00 | $3,575.00 | $4,230.89 | $3,719.17 |
| 19 | Protective coat (50300300) | SY | 4,132 | $2.25 | $2.00 | $2.62 | $3.68 |
| 20 | Reinf bars, epoxy CTD (50800205) | LB | 7,250 | $2.12 | $2.50 | $2.93 | $5.54 |
| 21 | Bar splicers (50800515) | EACH | 134 | $48.00 | $37.00 | $42.25 | $41.65 |
| 22 | Pref JT strip seal (52000110) | LF | 241 | $298.00 | $250.00 | $385.88 | $256.08 |
| 23 | Mobilization (67100100) | LS | 1 | $49,000 | $95,000 | $60,757 | $112,390 |
| 24 | Traf cont-prot 701321 (70100405) | EACH | 1 | $35,000 | $50,000 | $30,171 | $71,393 |
| 25 | Traf cont-prot 701201 (70100450) | LS | 1 | $0.10 | $4,500.00 | $11,844 | $1.00 |
| 26 | Traf cont-prot 701326 (70100500) | LS | 1 | $1.48 | $0.01 | $15,077 | $1.00 |
| 27 | Temp BR traf signals (70106500) | EACH | 1 | $26,000 | $30,500 | $53,020 | $27,617 |
| 28 | Temp rumble strips (70106700) | EACH | 6 | $900.00 | $1,300.00 | $1,254.96 | $1,394.94 |
| 29 | Pavt MK blkout tape 5 (70107005) | LF | 3,138 | $2.90 | $4.00 | $4.31 | $5.20 |
| 30 | Changeable message SN (70107025) | CAL DAY | 28 | $140.00 | $110.00 | $84.75 | $234.48 |
| 31 | Short term pavt mking (70300100) | LF | 668 | $0.90 | $1.00 | $3.23 | $1.92 |
| 32 | SHRT TRM pavt MK rem (70300150) | SF | 1,530 | $1.75 | $0.50 | $5.63 | $1.24 |
| 33 | Temp conc barrier (70400100) | LF | 1,800 | $33.00 | $37.00 | $30.13 | $48.43 |
| 34 | Rel temp conc barrier (70400200) | LF | 1,800 | $4.15 | $3.00 | $4.54 | $9.26 |
| 35 | Imp attn temp NRD TL3 (70600250) | EACH | 2 | $5,560.00 | $11,500 | $2,917.22 | $9,292.28 |
| 36 | Imp attn rel NRD TL3 (70600350) | EACH | 2 | $379.00 | $2,500.00 | $468.62 | $3,056.46 |
| 37 | Paint PVT MK line 4 (78001110) | LF | 2,877 | $1.40 | $1.50 | $1.47 | $1.42 |
| 38 | Raised ref PVT MK rem (78300200) | EACH | 4 | $17.00 | $20.00 | $24.85 | $61.79 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of November 7, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.