Project Number: S00V-023 / /, section 19-00507-00-BR. Let by Illinois DOT on November 7, 2025, Mchenry, District 01. 4 bids received; low bid $5,134,451 by Dunnet Bay Construction Company.
- Owner
- Illinois DOT
- Letting
- 07 NOV 2025
- Pay items
- 104
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Dunnet Bay Construction Company | $5,134,451 | Low |
| 2 | Herlihy Mid-Continent Company | $5,873,712 | +14% |
| 3 | Lorig Construction Company | $6,038,058 | +18% |
| 4 | Copenhaver Construction, Inc. | $6,712,395 | +31% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Dunnet Bay Construction Company | 2. Herlihy Mid-Continent Company | 3. Lorig Construction Company | 4. Copenhaver Construction, Inc. |
|---|---|---|---|---|---|---|---|
| 1 | Rodent shields (X0322278) | EACH | 5 | $60.00 | $50.00 | $250.00 | $300.00 |
| 2 | Washout basin (X0326806) | LS | 1 | $2,500.00 | $5,000.00 | $250.00 | $2,000.00 |
| 3 | Relocate EX mailbox (X0327301) | EACH | 3 | $350.00 | $500.00 | $750.00 | $300.00 |
| 4 | Temporary fence SPL (X2011000) | LF | 1,453 | $11.33 | $11.33 | $12.00 | $10.00 |
| 5 | Temp access- priv ent (X4021000) | EACH | 3 | $500.00 | $1,750.00 | $1,400.00 | $100.00 |
| 6 | Temp access- FLD ent (X4024000) | EACH | 1 | $750.00 | $1,750.00 | $1,400.00 | $200.00 |
| 7 | BR deck grooving long (X5030250) | SY | 678 | $8.18 | $9.00 | $10.00 | $9.00 |
| 8 | SPBGR (short radius) (X6330725) | LF | 25 | $46.15 | $46.15 | $48.00 | $45.00 |
| 9 | Fence removal (X6640104) | LF | 1,058 | $2.43 | $20.00 | $2.50 | $10.00 |
| 10 | Engr FLD off A mod (X6700405) | CAL MO | 9 | $4,100.00 | $5,500.00 | $4,000.00 | $2,500.00 |
| 11 | Traf cont & prot SPL (X7010216) | LS | 1 | $50,000 | $75,000 | $575,000 | $87,000 |
| 12 | Temp info signing (X7200061) | SF | 55 | $16.00 | $12.00 | $20.00 | $20.00 |
| 13 | Teles STL sin sup SPL (X7280105) | LF | 23 | $35.00 | $22.00 | $36.00 | $30.00 |
| 14 | Steel railing SPL (Z0007124) | LF | 430 | $460.10 | $446.87 | $446.00 | $500.00 |
| 15 | Stab constr entrance (Z0013797) | SY | 100 | $1.00 | $25.00 | $3.00 | $0.01 |
| 16 | Construction layout (Z0013798) | LS | 1 | $100,000 | $150,000 | $240,000 | $32,000 |
| 17 | Permnt bench marks (Z0038700) | EACH | 3 | $180.00 | $750.00 | $950.00 | $1,000.00 |
| 18 | Trainees (Z0076600) | HR | 500 | $0.80 | $0.80 | $0.80 | $0.80 |
| 19 | Trainees TPG (Z0076604) | HR | 500 | $15.00 | $15.00 | $15.00 | $15.00 |
| 20 | Tree remov 6-15 (20100110) | UNIT | 6 | $25.00 | $25.00 | $27.00 | $49.00 |
| 21 | Tree remov over 15 (20100210) | UNIT | 289 | $33.00 | $33.00 | $35.00 | $37.00 |
| 22 | Tree trunk protection (20101100) | EACH | 1 | $250.00 | $250.00 | $350.00 | $170.00 |
| 23 | Tree root pruning (20101200) | EACH | 1 | $350.00 | $350.00 | $400.00 | $100.00 |
| 24 | Tree prun 1-10 (20101300) | EACH | 1 | $85.00 | $85.00 | $100.00 | $100.00 |
| 25 | Earth excavation (20200100) | CY | 5,310 | $0.01 | $26.00 | $1.00 | $40.00 |
| 26 | Rem & disp uns matl (20201200) | CY | 5,310 | $33.00 | $30.00 | $1.00 | $40.00 |
| 27 | Channel excavation (20300100) | CY | 1,935 | $25.00 | $50.00 | $35.00 | $65.00 |
| 28 | Rock excav channel (20300200) | CY | 50 | $75.00 | $120.00 | $100.00 | $85.00 |
| 29 | Furnished excavation (20400800) | CY | 5,805 | $25.00 | $27.50 | $28.00 | $15.00 |
| 30 | Trench backfill (20800150) | CY | 71 | $55.00 | $90.00 | $70.00 | $70.00 |
| 31 | Geotech fab F/GR stab (21001000) | SY | 95 | $11.53 | $6.50 | $4.00 | $10.00 |
| 32 | Topsoil exc & plac (21101505) | CY | 2,210 | $25.00 | $26.00 | $35.00 | $15.00 |
| 33 | Seeding CL 2A (25000210) | ACRE | 3.25 | $2,102.00 | $3,500.00 | $2,500.00 | $3,000.00 |
| 34 | Nitrogen fert nutr (25000400) | LB | 290 | $3.00 | $3.00 | $1.00 | $1.00 |
| 35 | Potassium fert nutr (25000600) | LB | 290 | $3.00 | $3.00 | $1.00 | $1.00 |
| 36 | Wildlife friendly ecb (25100645) | SY | 15,578 | $1.80 | $1.40 | $1.60 | $2.00 |
| 37 | Temp eros contr seed (28000250) | LB | 322 | $3.00 | $8.00 | $1.00 | $0.01 |
| 38 | Temp ditch checks (28000305) | LF | 983 | $4.00 | $12.00 | $8.00 | $14.00 |
| 39 | Perimeter eros bar (28000400) | LF | 2,324 | $2.00 | $3.00 | $2.50 | $3.00 |
| 40 | Temp WLDLF frndly ecb (28001105) | SY | 14,533 | $1.60 | $1.40 | $1.00 | $2.00 |
| 41 | Filter fabric (28200200) | SY | 2,762 | $4.00 | $3.25 | $4.50 | $3.00 |
| 42 | Articul block rev mat (28500400) | SY | 2,762 | $262.00 | $285.30 | $295.00 | $307.00 |
| 43 | Agg subgrade improve (30300001) | CY | 1,021 | $57.00 | $62.50 | $70.00 | $50.00 |
| 44 | Agg subgrade impr 12 (30300112) | SY | 3,407 | $23.00 | $28.00 | $28.00 | $16.00 |
| 45 | Agg base cse B (35101500) | CY | 30 | $105.00 | $150.00 | $200.00 | $59.00 |
| 46 | Agg base cse B 10 (35102200) | SY | 609 | $28.35 | $28.00 | $25.00 | $16.00 |
| 47 | Bit matls PR CT (40600275) | LB | 818 | $0.01 | $0.01 | $0.01 | $2.00 |
| 48 | Bit matls tack CT (40600290) | LB | 1,352 | $0.01 | $0.01 | $0.01 | $2.00 |
| 49 | Long joint sealant (40600370) | LF | 2,365 | $3.60 | $3.60 | $3.75 | $6.00 |
| 50 | HMA BC IL-19.0 N50 (40603080) | TON | 555 | $87.00 | $87.00 | $105.00 | $100.00 |
| 51 | HMA SC IL-9.5 D N50 (40604060) | TON | 255 | $92.00 | $92.00 | $95.00 | $120.00 |
| 52 | Welded wire reinf (42000060) | SY | 190 | $15.00 | $25.00 | $18.00 | $10.00 |
| 53 | PVT con PCC BR app SL (42000080) | SY | 190 | $100.00 | $250.00 | $240.00 | $160.00 |
| 54 | Pavement rem (44000100) | SY | 678 | $32.00 | $12.00 | $10.00 | $17.00 |
| 55 | HMA shoulders 6 3/4 (48203024) | SY | 732 | $40.00 | $40.00 | $48.00 | $46.00 |
| 56 | Rem exist struct (50100100) | EACH | 1 | $1,434,000 | $981,290 | $1,425,000 | $420,000 |
| 57 | Conc rem (50102400) | CY | 10 | $145.00 | $115.00 | $650.00 | $500.00 |
| 58 | Pipe culvert remov (50105220) | LF | 74 | $48.00 | $32.00 | $21.00 | $40.00 |
| 59 | Structure excavation (50200100) | CY | 348 | $0.01 | $113.76 | $5.00 | $60.00 |
| 60 | Cofferdam excavation (50200300) | CY | 778 | $0.01 | $151.51 | $5.00 | $65.00 |
| 61 | Cofferdam typ 2 loc 1 (50201121) | EACH | 1 | $1.00 | $1.00 | $100.00 | $10,000 |
| 62 | Cofferdam typ 2 loc 2 (50201122) | EACH | 1 | $1.00 | $1.00 | $100.00 | $10,000 |
| 63 | Cofferdam typ 2 loc 3 (50201123) | EACH | 1 | $1.00 | $1.00 | $100.00 | $10,000 |
| 64 | Conc struct (50300225) | CY | 253.10 | $650.00 | $1,250.00 | $1,350.00 | $1,900.00 |
| 65 | Conc sup-STR (50300255) | CY | 828.20 | $300.00 | $870.00 | $400.00 | $2,100.00 |
| 66 | Protective coat (50300300) | SY | 820 | $2.75 | $5.00 | $1.50 | $2.00 |
| 67 | Conc supstr app slab (50301350) | CY | 95.80 | $750.00 | $750.00 | $800.00 | $1,200.00 |
| 68 | Reinf bars, epoxy CTD (50800205) | LB | 269,750 | $1.43 | $1.34 | $1.40 | $2.00 |
| 69 | Fur M S pile 14X0.312 (51200959) | LF | 1,679 | $100.00 | $51.97 | $88.00 | $120.00 |
| 70 | Driving piles (51202305) | LF | 1,679 | $1.00 | $1.00 | $1.00 | $1.00 |
| 71 | Test pile met shells (51203200) | EACH | 5 | $15,000 | $25,000 | $8,000.00 | $7,000.00 |
| 72 | Pile shoes (51204650) | EACH | 38 | $380.00 | $362.60 | $400.00 | $350.00 |
| 73 | Name plates (51500100) | EACH | 1 | $607.00 | $1,500.00 | $1,200.00 | $2,000.00 |
| 74 | P cul CL C 1 15 (542C0220) | LF | 192 | $98.00 | $100.00 | $135.00 | $140.00 |
| 75 | SLP MT ES WG 15",1:6 (54260715) | EACH | 6 | $2,380.00 | $1,150.00 | $1,800.00 | $1,600.00 |
| 76 | Storm sew CL B 2 15 (550B0360) | LF | 252 | $92.00 | $120.00 | $70.00 | $140.00 |
| 77 | Granular backfill STR (58600101) | CY | 83 | $54.00 | $75.00 | $190.00 | $63.00 |
| 78 | Geocomposite wall DR (59100100) | SY | 43 | $51.00 | $32.00 | $42.00 | $50.00 |
| 79 | Conc HDWL for P drain (60100060) | EACH | 5 | $660.00 | $1,000.00 | $700.00 | $600.00 |
| 80 | Pipe underdrain 4 SP (60108100) | LF | 127 | $45.00 | $42.00 | $27.00 | $40.00 |
| 81 | Pipe underdr T 2 4 (60108204) | LF | 1,639 | $39.00 | $28.00 | $26.00 | $20.00 |
| 82 | P undr for struct 4 (60146304) | LF | 97 | $75.00 | $75.00 | $45.00 | $25.00 |
| 83 | Inlets TA T1F CL (60235300) | EACH | 3 | $2,582.00 | $2,000.00 | $2,000.00 | $2,000.00 |
| 84 | Inlets TA T8G (60236200) | EACH | 1 | $2,451.00 | $2,000.00 | $2,000.00 | $2,100.00 |
| 85 | SPBGR TY B 9FT posts (63000009) | LF | 75 | $110.30 | $110.30 | $113.00 | $55.00 |
| 86 | Traf bar term T2 (63100045) | EACH | 1 | $1,632.00 | $1,632.00 | $1,700.00 | $1,900.00 |
| 87 | Traf bar term T6 (63100085) | EACH | 4 | $4,511.11 | $4,326.00 | $4,500.00 | $5,000.00 |
| 88 | TR bar TRM T1 SPL tan (63100167) | EACH | 3 | $3,397.00 | $3,397.00 | $3,600.00 | $4,000.00 |
| 89 | Guardrail remov (63200310) | LF | 304 | $7.83 | $7.83 | $8.00 | $10.00 |
| 90 | Fur erect row markers (66600105) | EACH | 21 | $624.70 | $850.00 | $165.00 | $150.00 |
| 91 | RE-erect row markers (66600205) | EACH | 1 | $624.81 | $500.00 | $100.00 | $200.00 |
| 92 | Non SPL waste disposl (66900200) | CY | 840 | $54.45 | $75.00 | $85.00 | $85.00 |
| 93 | Soil disposal analy (66900530) | EACH | 1 | $1,700.00 | $1,700.00 | $1,350.00 | $1,500.00 |
| 94 | Reg sub P-const plan (66901001) | LS | 1 | $3,400.00 | $3,400.00 | $3,600.00 | $4,000.00 |
| 95 | Reg sub F con report (66901003) | LS | 1 | $500.00 | $500.00 | $600.00 | $700.00 |
| 96 | Reg sub mon (66901006) | CAL DAY | 3 | $700.00 | $700.00 | $2,200.00 | $1,100.00 |
| 97 | Mobilization (67100100) | LS | 1 | $308,067 | $358,560 | $300,000 | $441,000 |
| 98 | Sign panel T1 (72000100) | SF | 6 | $50.00 | $20.00 | $50.00 | $50.00 |
| 99 | Remov sin pan assy TA (72400100) | EACH | 5 | $200.00 | $50.00 | $200.00 | $120.00 |
| 100 | Remov sign panel T1 (72400310) | SF | 18 | $20.00 | $10.00 | $20.00 | $10.00 |
| 101 | Terminal marker - DA (72501000) | EACH | 4 | $40.00 | $40.00 | $40.00 | $50.00 |
| 102 | Mod ureth PM line 4 (78009004) | LF | 3,043 | $2.50 | $2.00 | $2.50 | $3.00 |
| 103 | Grdrail ref type A (78200005) | EACH | 8 | $12.00 | $12.00 | $12.00 | $25.00 |
| 104 | Grdrail ref type B (78200006) | EACH | 16 | $12.00 | $12.00 | $12.00 | $25.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of November 7, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.