Herlihy Mid-Continent Company: IDOT bid record

Herlihy Mid-Continent Company submitted 121 bids on Illinois DOT contracts in the data, from 15 JAN 2021 to 18 SEP 2026, and was the low bidder on 16 of them (13%). When it was not low, its total sat a median +16% above the low bid.

Owner
Illinois DOT
Low bid volume
$46,890,593
Latest bid
18 SEP 2026
Data through
18 SEP 2026
121Bids
16Low bids
13Win rate, percent
+16%Median gap to the low bid when not low, 105 bids

By year

YearBidsLow bidsWin rate
202139513%
202227415%
202323417%
202413323%
20251000%
2026900%
Herlihy Mid-Continent Company, IDOT: bids and low bids by year of letting

By district

DistrictBidsLow bidsWin rate
District 011031313%
District 0317318%
District 02100%
Herlihy Mid-Continent Company, IDOT: bids and low bids by district

Pay items where it is most often lowest

Pay itemCodeUnitLines bidLowest on the lineIts median priceAll bidders' median
Trainees TPGZ0076604HR8181 (100%)$15.00$15.00
TraineesZ0076600HR7777 (100%)$0.80$0.80
Bit matls tack CT40600290LB9061 (68%)$0.01$0.01
Temp info signingZ0030850SF8154 (67%)$17.00$18.00
Perimeter eros bar28000400LF7843 (55%)$3.00$3.50
Temp conc barrier70400100LF7843 (55%)$21.50$31.73
Changeable message SN70107025CAL DAY6143 (70%)$30.00$55.00
Guardrail remov63200310LF6742 (63%)$7.16$8.00
TR bar TRM T1 SPL tan63100167EACH5741 (72%)$3,480.00$3,800.00
THPL PVT MK line 478000200LF6938 (55%)$1.25$0.88
Terminal marker - DA72501000EACH4536 (80%)$35.00$47.85
Reinf bars, epoxy CTD50800205LB11335 (31%)$1.75$2.50
Herlihy Mid-Continent Company, IDOT: pay items where its unit price was the lowest on the line

A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.

Who it meets most

Herlihy Mid-Continent Company, IDOT: the firms on the same contracts most often

Latest bids

LetContractDistrictProjectRankIts bidAgainst the low bid
18 SEP 202661L85District 01Project Number: 50B4-000 / /, section 18-00488-00-BR4 of 5$5,859,962+23%
31 JUL 202661M13District 01Project Number: Qnyf-462 / /, section 12-00192-04-BR5 of 6$42,975,040+17%
31 JUL 202662W20District 01Section FAI5 of 6$9,121,359+27%
12 JUN 202662X28District 01Section (FXB-1R)2 of 3$331,246+33%
12 JUN 202662X52District 01Section 2024-1015-SCR4 of 4$419,836+58%
27 FEB 202661M25District 01Project Number: H406-985 / /, section 16-11107-01-BR4 of 7$1,944,577+25%
16 JAN 202661M01District 01Shorewood, section 21-00047-00-WR3 of 3$11,910,697+33%
16 JAN 202662K65District 01Section 2019-192-B-R5 of 7$15,470,888+16%
16 JAN 202662R76District 01Section FAI5 of 5$968,132+50%
07 NOV 202561J54District 01Project Number: Whf6-372 / /, section 16-F3000-15-BT3 of 3$7,369,000+6.0%
07 NOV 202561L82District 01Broadview, section 22-00086-00-BR2 of 5$2,898,784+12%
07 NOV 202561L88District 01Project Number: S00V-023 / /, section 19-00507-00-BR2 of 4$5,873,712+14%
07 NOV 202562R63District 015 of 6$19,554,223+25%
19 SEP 202561L69District 01Elmhurst, section 19-00197-00-BT6 of 6$4,908,000+35%
13 JUN 202560R76District 01Section 99-1HB-2-BR2 of 3$5,537,000+34%
25 APR 202561K44District 01Project Number: L7Md-600 / /, section 20-F3000-06-BT2 of 2$4,913,365+34%
25 APR 202562X25District 01Section (7HB-K(86)BR2 of 4$356,580+48%
17 JAN 202561K84District 01Channahon, section 15-00024-02-BT2 of 2$3,343,667+34%
17 JAN 202587840District 03Minooka, section 21-00058-00-BT3 of 3$2,512,800+47%
08 NOV 202462W30District 01Section (531-2-HB)BR4 of 4$14,457,000+34%
20 SEP 202461G80District 01Hanover Park, section 15-00066-00-BR5 of 7$2,929,283+29%
20 SEP 202462T94District 01Section FAU4 of 9$1,930,826+33%
20 SEP 202462W80District 01Section (22-2-3HB)BR-246 of 7$335,511+52%
26 APR 202461J14District 01Project Number: 26Xm-359 / /, section 14-00124-04-BR2 of 3$9,040,309+7.0%
08 MAR 202461J30District 01Project Number: Tzsu-571 / /, section 18-00206-10-BR1 of 5$7,867,988Low, 2.0% under the second
Herlihy Mid-Continent Company: latest IDOT bids in the data

How this record was read

IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

  • Every bid counted here matched its published total to within one dollar; IDOT's rank decides who was low.
  • The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
  • A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.

A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy