IDOT letting results, July 31, 2026
74 contracts let by Illinois DOT on July 31, 2026, $190,855,087 in low bids, a median of 2 bidders per contract.
- Owner
- Illinois DOT
- Contracts
- 74
- Low bids, total
- $190,855,087
- Data through
- 18 SEP 2026
Contracts let that day
| Contract | Project | District | Bids | Low bidder | Low bid | Second bid | Gap | Source |
|---|---|---|---|---|---|---|---|---|
| 61M13 | Project Number: Qnyf-462 / /, section 12-00192-04-BR | District 01 | 6 | Dunnet Bay Construction Company | $36,611,206 | $37,919,789 | +4.0% | IDOT |
| 92621 | Section (S,W)R-2,W-2,PB | District 06 | 4 | Illinois Valley Paving, a div of UCM, Inc. | $36,568,681 | $37,845,077 | +3.0% | IDOT |
| 78520 | Section (41-8,1,2)RS-5;1B-1 | District 09 | 2 | E. T. Simonds Construction Company | $9,952,613 | $10,360,275 | +4.0% | IDOT |
| 66M85 | Section [(37,101)BVB]BR | District 03 | 3 | ICC Group Inc. | $9,933,000 | $10,443,322 | +5.0% | IDOT |
| 72J44 | Section 122(RS-10,BDR-1,I-1) | District 06 | 1 | Illinois Valley Paving, a div of UCM, Inc. | $8,178,851 | IDOT | ||
| 62W20 | Section FAI | District 01 | 6 | D. Construction, Inc. | $7,166,048 | $7,530,587 | +5.0% | IDOT |
| 85781 | East Moline, section 22-00159-04-PV | District 02 | 4 | Miller Trucking & Excavating Company | $6,393,210 | $6,525,687 | +2.0% | IDOT |
| 78B60 | Section 104RS-8 | District 09 | 1 | E. T. Simonds Construction Company | $4,132,778 | IDOT | ||
| 46951 | Section KICKAPOO | District 05 | 2 | Feutz Contractors, Inc. | $4,107,350 | $4,958,714 | +21% | IDOT |
| 70G29 | Section RA | District 05 | 3 | Stark Excavating, Inc. | $3,219,237 | $4,494,900 | +40% | IDOT |
| 74829 | Section (2,2Z) | District 07 | 2 | Howell Paving, Inc. | $3,050,707 | $3,316,240 | +9.0% | IDOT |
| 61M40 | Project Number: Vd4X-283 / /, section 20-00288-05-TL | District 01 | 3 | Home Towne Electric, Inc. | $2,996,846 | $3,421,618 | +14% | IDOT |
| 62J64 | Section 2019-122-RS&SW | District 01 | 4 | Peter Baker & Son Co. | $2,925,476 | $3,645,000 | +25% | IDOT |
| 46949 | Section ELDON | District 08 | 4 | McCarthy Improvement Company | $2,907,718 | $3,144,338 | +8.0% | IDOT |
| 61K85 | Rolling Meadows, section 21-00126-00-PV | District 01 | 10 | Plote Construction, Inc. | $2,813,311 | $2,888,000 | +3.0% | IDOT |
| 80C90 | Section (1616-VB-WPGM) | District 01 | 3 | F. H. Paschen, S.N. Nielsen & Associates LLC | $2,448,235 | $2,464,588 | +1.0% | IDOT |
| 80D50 | Section 2026-2188-I | District 01 | 2 | ERA-Valdivia Contractors, Inc. | $2,425,000 | $3,775,000 | +56% | IDOT |
| 66T53 | Section (124)RS-4 | District 03 | 2 | Curran Contracting Company | $2,389,089 | $2,427,144 | +2.0% | IDOT |
| 91669 | Project Number: R9Gf-473 / /, section 22-00137-01-RS | District 05 | 2 | Evergreen Roadworks, LLC | $2,189,996 | $2,294,716 | +5.0% | IDOT |
| 80B44 | Section (1313VB-VC-WPGM) | District 01 | 5 | D. Construction, Inc. | $2,052,202 | $2,383,504 | +16% | IDOT |
| 68K27 | Section 32RS-6;29RS-5;28RS-3 | District 04 | 2 | Advanced Asphalt Company | $1,822,642 | $2,411,426 | +32% | IDOT |
| 62W91 | Section 2024-966-TS | District 01 | 3 | H & H Electric Co. | $1,753,960 | $2,726,629 | +55% | IDOT |
| 61K19 | Elk Grove Village, section 22-00078-00-RS | District 01 | 4 | R. W. Dunteman Company | $1,589,589 | $1,638,000 | +3.0% | IDOT |
| 62T84 | Section FAU | District 01 | 3 | D. Construction, Inc. | $1,552,966 | $2,149,812 | +38% | IDOT |
| 61K67 | Aurora, section 23-00367-00-RS | District 01 | 3 | Builders Paving, LLC | $1,538,538 | $1,561,674 | +2.0% | IDOT |
| 78C21 | Section D9 | District 09 | 2 | Collins & Hermann, Inc. | $1,458,402 | $2,175,000 | +49% | IDOT |
| 80B78 | Section 2025-2036-I | District 01 | 2 | MYS, Incorporated | $1,409,040 | $1,455,555 | +3.0% | IDOT |
| 80B42 | Section 2025-2020-I | District 01 | 4 | D. Construction, Inc. | $1,380,593 | $1,817,673 | +32% | IDOT |
| 70J06 | Section D5 | District 05 | 2 | Collins & Hermann, Inc. | $1,317,046 | $1,900,000 | +44% | IDOT |
| 78935 | Section 113B-2 | District 09 | 2 | E. T. Simonds Construction Company | $1,269,718 | $1,321,450 | +4.0% | IDOT |
| 66P22 | Section (ORCB)BRR-1 | District 03 | 2 | Civil Constructors, Inc. d/b/a/ Helm Civil | $1,257,661 | $1,918,739 | +53% | IDOT |
| 62Y20 | Section 2025-1070-BDR,BJR | District 01 | 5 | Martam Construction Incorporated | $1,236,716 | $1,392,514 | +13% | IDOT |
| 97866 | Columbia, section 21-00053-01-PV | District 08 | 4 | Mayer Landscaping, Inc. | $1,072,824 | $1,140,035 | +6.0% | IDOT |
| 62V45 | Section FAP | District 01 | 4 | D. Construction, Inc. | $1,062,900 | $1,136,281 | +7.0% | IDOT |
| 99769 | Project Number: Mqtu-969 / /, section 23-00111-00-RS | District 09 | 1 | Samron Midwest Contracting, Inc. | $1,054,105 | IDOT | ||
| 93856 | Project Number: Clz9-161 / /, section 24-00109-00-BR | District 06 | 1 | C-Hill Civil Contractors, Inc. | $1,021,148 | IDOT | ||
| 76V11 | Section DIST | District 08 | 3 | Kinney Contractors, Inc. | $951,953 | $999,552 | +5.0% | IDOT |
| 76V22 | Section 28Q | District 08 | 2 | DMS Contracting, Inc. | $899,907 | $940,763 | +5.0% | IDOT |
| 68L01 | Section 2RS-6,PP | District 04 | 1 | R. A. Cullinan and Son, a div of UCM, Inc. | $892,489 | IDOT | ||
| 74E44 | Section D7 | District 07 | 2 | Collins & Hermann, Inc. | $825,162 | $1,650,000 | +100% | IDOT |
| 64V41 | Section ((33,40-1)&(115))PP | District 02 | 2 | Valley Construction Co. | $755,266 | $791,482 | +5.0% | IDOT |
| 66T13 | Section (50-8, | District 03 | 1 | Advanced Asphalt Company | $729,412 | IDOT | ||
| 78B80 | Section (101,102,103)TR-1 | District 09 | 2 | Mosley Construction 1, LLC | $717,325 | $805,275 | +12% | IDOT |
| 99775 | Herrin, section 25-00078-00-RS | District 09 | 2 | Samron Midwest Contracting, Inc. | $693,605 | $702,220 | +1.0% | IDOT |
| 66T21 | Section (128)PP | District 03 | 2 | G. M. Sipes Construction, Inc. | $690,200 | $702,750 | +2.0% | IDOT |
| 68L03 | Section 22PP | District 04 | 2 | Brandt Construction Co. | $630,038 | $660,905 | +5.0% | IDOT |
| 76V21 | Section (Q-1)RS-3, | District 08 | 2 | Evergreen Roadworks, LLC | $622,539 | $802,719 | +29% | IDOT |
| 64V30 | Section (L)TR | District 02 | 2 | Clean Cut Tree Service, Inc. | $615,524 | $639,299 | +4.0% | IDOT |
| 66N23 | Section (112)CR-2548 | District 03 | 3 | Riber Construction, Inc. | $615,314 | $643,347 | +5.0% | IDOT |
| 66T22 | Section (19) | District 03 | 2 | G. M. Sipes Construction, Inc. | $610,480 | $681,610 | +12% | IDOT |
| 93860 | Project Number: Numa-444 / /, section 25-00048-00-PP | District 06 | 2 | A. C. Pavement Striping Co. | $586,823 | $670,000 | +14% | IDOT |
| 64T48 | Section (105BR-1)BRR | District 02 | 3 | Martin & Company Excavating | $523,502 | $558,681 | +7.0% | IDOT |
| 66T35 | Section (46-2)HL | District 03 | 3 | Laser Electric, Inc. | $447,135 | $598,992 | +34% | IDOT |
| 64T49 | Section (102BR)BRR | District 02 | 3 | Martin & Company Excavating | $443,472 | $532,329 | +20% | IDOT |
| 97902 | Salem, section 23-00047-04-RS | District 08 | 2 | Howell Paving, Inc. | $436,089 | $557,627 | +28% | IDOT |
| 62V46 | Section FAP | District 01 | 2 | Mosley Construction 1, LLC | $424,498 | $438,081 | +3.0% | IDOT |
| 66T30 | Section (106)SFY | District 03 | 2 | CSD Environmental Services, Inc. | $404,001 | $1,075,580 | +166% | IDOT |
| 62V29 | Section FAP | District 01 | 2 | Denler, Inc. | $334,302 | $669,331 | +100% | IDOT |
| 62X43 | Section 68B-1 | District 01 | 4 | D. Construction, Inc. | $290,657 | $321,880 | +11% | IDOT |
| 80C87 | Section 2025-2119-RS,DR | District 01 | 3 | Gallagher Asphalt Corporation | $288,498 | $316,088 | +10% | IDOT |
| 72E86 | Section D6 | District 06 | 3 | Truman L. Flatt & Sons Co., Inc. | $286,492 | $398,633 | +39% | IDOT |
| 72E81 | Section D6 | District 06 | 1 | Capitol Construction Group, LLC d/b/a Egizii Electric | $279,735 | IDOT | ||
| 68L02 | Section 131PP | District 04 | 2 | Advanced Asphalt Company | $253,825 | $372,818 | +47% | IDOT |
| 66T37 | Section D3 | District 03 | 1 | Ficek Electric & Communication Systems, Inc. | $241,801 | IDOT | ||
| 78C18 | Section (5-3,1-4,1-3,1-2)LS-1 | District 09 | 2 | CSD Environmental Services, Inc. | $241,350 | $288,100 | +19% | IDOT |
| 62V79 | Section FAP | District 01 | 2 | Denler, Inc. | $190,610 | $197,404 | +4.0% | IDOT |
| 72372 | Section D6 | District 06 | 3 | Freehill Asphalt, Inc. | $143,774 | $229,488 | +60% | IDOT |
| 72E85 | Section 83RS-2 | District 06 | 2 | Illinois Valley Paving, a div of UCM, Inc. | $105,717 | $154,788 | +46% | IDOT |
| 72J00 | Section D6 | District 06 | 3 | Freehill Asphalt, Inc. | $92,224 | $113,798 | +23% | IDOT |
| 70J08 | Section D5 | District 05 | 3 | Thor General Contracting LLC | $87,478 | $250,320 | +186% | IDOT |
| 62V64 | Section FAP | District 01 | 2 | Denler, Inc. | $85,435 | $91,284 | +7.0% | IDOT |
| 74E43 | Section D7 | District 07 | 2 | Howell Paving, Inc. | $61,319 | $119,180 | +94% | IDOT |
| 62V80 | Section FAP | District 01 | 2 | Denler, Inc. | $51,792 | $117,765 | +127% | IDOT |
| 64V16 | Section (K-2)CG | District 02 | 5 | Law Excavating, Inc. | $45,940 | $56,921 | +24% | IDOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than IDOT received, the others did not match their published totals and are left out. Each contract number opens its full bid tabulation.