IDOT contract 62T84 bid tabulation
Section FAU. Let by Illinois DOT on July 31, 2026, Cook, District 01. 3 bids received; low bid $1,552,966 by D. Construction, Inc..
- Owner
- Illinois DOT
- Letting
- 31 JUL 2026
- Pay items
- 96
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | D. Construction, Inc. | $1,552,966 | Low |
| 2 | Lorig Construction Company | $2,149,812 | +38% |
| 3 | M & J Underground Inc. | $2,358,211 | +52% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. D. Construction, Inc. | 2. Lorig Construction Company | 3. M & J Underground Inc. |
|---|---|---|---|---|---|---|
| 1 | T-celtis occid CL 2 (A2002879) | EACH | 3 | $1,100.00 | $390.00 | $1,049.99 |
| 2 | S-viburn lant MO 3' (C2012336) | EACH | 24 | $124.30 | $120.00 | $118.65 |
| 3 | Mowing SPL (X2503110) | ACRE | 0.50 | $5,346.00 | $750.00 | $5,102.96 |
| 4 | Native sodding SPL (X2520704) | SY | 685 | $115.50 | $102.00 | $110.25 |
| 5 | Cofferdam typ 1 IS WW (X5021512) | EACH | 2 | $0.01 | $500.00 | $100,000 |
| 6 | Ornamental railing (X5090850) | LF | 143 | $231.75 | $510.00 | $304.50 |
| 7 | Handrail removal (X5091770) | LF | 28 | $20.00 | $82.00 | $18.00 |
| 8 | Storm sew connection (X5510010) | EACH | 6 | $2,500.00 | $3,000.00 | $6,623.72 |
| 9 | SS cleaned 24 (X5538200) | LF | 135 | $38.50 | $35.00 | $20.81 |
| 10 | Memb WTRPRF sys B STR (X5810103) | SY | 416 | $60.00 | $40.00 | $40.71 |
| 11 | Connect EX manhole (X6020399) | EACH | 1 | $1,500.00 | $2,750.00 | $3,177.35 |
| 12 | Fence removal (X6640104) | LF | 12 | $20.00 | $96.00 | $50.00 |
| 13 | Engrs FLD ofc TY A D1 (X6700407) | CAL MO | 12 | $5,000.00 | $3,500.00 | $3,500.00 |
| 14 | Traf cont & prot SPL (X7010216) | LS | 1 | $61,500 | $113,000 | $15,435 |
| 15 | Temp info signing (X7200061) | SF | 51.40 | $30.00 | $16.00 | $21.00 |
| 16 | Rem repl sign & SPPRT (X7240305) | EACH | 1 | $1,000.00 | $1,000.00 | $1,800.00 |
| 17 | Temp TR signal timing (X8900104) | EACH | 5 | $605.00 | $550.00 | $734.99 |
| 18 | Construction layout (Z0013798) | LS | 1 | $10,000 | $25,000 | $13,545 |
| 19 | Rock fill (Z0054400) | CY | 457 | $60.00 | $125.00 | $105.69 |
| 20 | Temporary fence (20101000) | LF | 285 | $3.74 | $3.00 | $3.57 |
| 21 | Tree trunk protection (20101100) | EACH | 7 | $165.00 | $150.00 | $157.50 |
| 22 | Earth excavation (20200100) | CY | 709.70 | $40.00 | $70.00 | $85.35 |
| 23 | Channel excavation (20300100) | CY | 128.70 | $40.00 | $82.00 | $85.35 |
| 24 | Porous gran embank (20700220) | CY | 508 | $60.00 | $145.00 | $96.18 |
| 25 | Trench backfill (20800150) | CY | 37 | $60.00 | $100.00 | $106.07 |
| 26 | Geotech fab F/GR stab (21001000) | SY | 37 | $10.00 | $5.00 | $19.00 |
| 27 | Topsoil exc & plac (21101505) | CY | 157 | $47.30 | $80.00 | $75.63 |
| 28 | Grading & shap ditch (21400100) | LF | 233 | $11.55 | $13.00 | $11.02 |
| 29 | Sodding salt tolerant (25200110) | SY | 505 | $14.85 | $20.00 | $14.17 |
| 30 | Supple watering (25200200) | UNIT | 60 | $1.10 | $50.00 | $1.05 |
| 31 | Temp eros contr seed (28000250) | LB | 100 | $7.15 | $4.00 | $6.82 |
| 32 | Temp ditch checks (28000305) | LF | 30 | $18.15 | $4.50 | $17.32 |
| 33 | Perimeter eros bar (28000400) | LF | 641 | $4.18 | $3.00 | $3.99 |
| 34 | Inlet & pipe protect (28000500) | EACH | 7 | $154.00 | $66.00 | $189.53 |
| 35 | Temp eros contr blank (28001100) | SY | 692 | $1.98 | $1.50 | $1.89 |
| 36 | Stone riprap CL A4 (28100107) | SY | 50 | $85.00 | $165.00 | $210.88 |
| 37 | Stone riprap CL A5 (28100109) | SY | 106 | $90.00 | $220.00 | $229.11 |
| 38 | Filter fabric (28200200) | SY | 50 | $10.00 | $4.00 | $35.25 |
| 39 | Agg subgrade impr 12 (30300112) | SY | 168 | $30.00 | $52.00 | $40.18 |
| 40 | Sub gran mat B (31101100) | CY | 27 | $80.00 | $160.00 | $110.44 |
| 41 | HMA base cse 8 (35501316) | SY | 125 | $89.00 | $167.00 | $155.40 |
| 42 | Bit matls tack CT (40600290) | LB | 56 | $0.01 | $0.25 | $0.01 |
| 43 | HMA surf rem butt JT (40600982) | SY | 52 | $27.50 | $75.00 | $0.01 |
| 44 | HMA SC IL-9.5 D N50 (40604060) | TON | 14 | $200.00 | $535.00 | $339.15 |
| 45 | HMA SC IL-9.5 D N70 (40604062) | TON | 2 | $400.00 | $900.00 | $540.75 |
| 46 | PCC PVT 9 jointed (42000401) | SY | 326 | $165.00 | $225.00 | $117.84 |
| 47 | PC conc sidewalk 5 (42400200) | SF | 3,639 | $10.73 | $13.00 | $13.70 |
| 48 | Detectable warnings (42400800) | SF | 55 | $33.00 | $105.00 | $38.68 |
| 49 | Pavement rem (44000100) | SY | 440 | $31.90 | $31.00 | $37.62 |
| 50 | Comb curb gutter rem (44000500) | LF | 304 | $11.00 | $20.00 | $18.19 |
| 51 | Sidewalk rem (44000600) | SF | 1,937 | $2.75 | $2.00 | $3.97 |
| 52 | Rem exist struct N1 (50100300) | EACH | 1 | $20,000 | $100,000 | $80,017 |
| 53 | Rem exist struct N2 (50100400) | EACH | 1 | $20,000 | $8,000.00 | $80,017 |
| 54 | Structure excavation (50200100) | CY | 1,648 | $30.00 | $60.00 | $132.18 |
| 55 | Rem/disp uns matl-STR (50200450) | CY | 457 | $40.00 | $82.00 | $106.14 |
| 56 | Stud shear connectors (50500505) | EACH | 116 | $10.00 | $45.00 | $25.00 |
| 57 | Reinforcement bars (50800105) | LB | 10,190 | $2.50 | $4.20 | $3.25 |
| 58 | Reinf bars, epoxy CTD (50800205) | LB | 900 | $5.00 | $6.00 | $4.49 |
| 59 | Name plates (51500100) | EACH | 1 | $1,500.00 | $800.00 | $1,408.26 |
| 60 | Perm SHT piling (52200015) | SF | 875 | $45.00 | $51.00 | $90.26 |
| 61 | Conc STR retain wall (52200900) | CY | 6.20 | $2,200.00 | $4,300.00 | $5,666.20 |
| 62 | Conc box cul (54003000) | CY | 65.50 | $116.00 | $2,500.00 | $1,899.06 |
| 63 | PCBC 8X7 (54010807) | LF | 198 | $1,250.00 | $1,050.00 | $1,242.88 |
| 64 | PCBC 12X7 (54011207) | LF | 99 | $2,054.00 | $1,800.00 | $2,041.09 |
| 65 | PRC flar end sec 30 (54213675) | EACH | 1 | $3,000.00 | $5,000.00 | $2,829.24 |
| 66 | Storm sew CL A 1 12 (550A0050) | LF | 8 | $141.00 | $230.00 | $230.83 |
| 67 | Storm sew CL A 1 15 (550A0070) | LF | 10 | $150.00 | $210.00 | $362.33 |
| 68 | Storm sew CL A 1 24 (550A0120) | LF | 28 | $170.00 | $180.00 | $167.18 |
| 69 | Storm sew CL A 1 30 (550A0140) | LF | 130 | $190.00 | $180.00 | $179.84 |
| 70 | Storm sewer rem 15 (55100700) | LF | 30 | $20.00 | $65.00 | $27.91 |
| 71 | Storm sewer rem 24 (55101200) | LF | 29 | $30.00 | $70.00 | $55.47 |
| 72 | Storm sewer rem 30 (55101400) | LF | 135 | $40.00 | $65.00 | $32.35 |
| 73 | Geocomposite wall DR (59100100) | SY | 416 | $35.00 | $42.00 | $34.68 |
| 74 | Man TA 4 dia T24F&G (60219540) | EACH | 1 | $4,200.00 | $6,000.00 | $3,811.85 |
| 75 | Inlets TA T1F OL (60234200) | EACH | 1 | $2,500.00 | $2,400.00 | $2,503.99 |
| 76 | Inlets TA T24F&G (60237470) | EACH | 2 | $2,500.00 | $2,500.00 | $1,538.36 |
| 77 | Lids T1 CL (60403800) | EACH | 1 | $600.00 | $260.00 | $610.58 |
| 78 | Remov inlets (60500060) | EACH | 2 | $750.00 | $535.00 | $853.09 |
| 79 | Conc curb TB (60600605) | LF | 35 | $49.50 | $135.00 | $99.26 |
| 80 | Comb CC&G TB6.12 (60603800) | LF | 98 | $49.50 | $100.00 | $65.74 |
| 81 | Comb CC&G TY B-6.24 (60605000) | LF | 337 | $53.63 | $105.00 | $72.00 |
| 82 | Guardrail remov (63200310) | LF | 130 | $20.00 | $18.00 | $30.77 |
| 83 | Non SPL waste disposl (66900200) | CY | 890 | $85.00 | $90.00 | $104.85 |
| 84 | Soil disposal analy (66900530) | EACH | 3 | $1,750.00 | $1,450.00 | $839.99 |
| 85 | Reg sub P-const plan (66901001) | LS | 1 | $2,500.00 | $3,100.00 | $4,724.96 |
| 86 | Reg sub F con report (66901003) | LS | 1 | $2,500.00 | $2,100.00 | $525.00 |
| 87 | Reg sub mon (66901006) | CAL DAY | 30 | $950.00 | $1,400.00 | $750.74 |
| 88 | Mobilization (67100100) | LS | 1 | $92,500 | $110,000 | $91,000 |
| 89 | Changeable message SN (70107025) | CAL DAY | 30 | $100.00 | $35.00 | $31.50 |
| 90 | Temp conc barrier (70400100) | LF | 100 | $40.00 | $40.00 | $80.85 |
| 91 | Pin temp conc barrier (70400125) | EACH | 48 | $20.00 | $26.00 | $25.20 |
| 92 | THPL PVT MK line 4 (78000200) | LF | 618 | $4.13 | $5.50 | $3.94 |
| 93 | THPL PVT MK line 6 (78000400) | LF | 55 | $6.05 | $31.00 | $5.77 |
| 94 | THPL PVT MK line 12 (78000600) | LF | 30 | $12.10 | $46.00 | $11.55 |
| 95 | Raised refl pavt MKR (78100100) | EACH | 28 | $137.50 | $140.00 | $131.25 |
| 96 | Raised ref PVT MK rem (78300200) | EACH | 28 | $20.00 | $15.00 | $15.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of July 31, 2026. Compiled by Mirage Metrics.