IDOT contract 70G29 bid tabulation
Section RA. Let by Illinois DOT on July 31, 2026, Champaign, District 05. 3 bids received; low bid $3,219,237 by Stark Excavating, Inc..
- Owner
- Illinois DOT
- Letting
- 31 JUL 2026
- Pay items
- 85
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Stark Excavating, Inc. | $3,219,237 | Low |
| 2 | Duce Construction Company | $4,494,900 | +40% |
| 3 | A & R Mechanical Service, Inc. | $4,618,805 | +43% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Stark Excavating, Inc. | 2. Duce Construction Company | 3. A & R Mechanical Service, Inc. |
|---|---|---|---|---|---|---|
| 1 | Concrete pad (X0321309) | SY | 33 | $295.00 | $234.00 | $385.17 |
| 2 | Rem exs int PLB loc 1 (X0324605) | LS | 1 | $5,400.00 | $17,367 | $16,786 |
| 3 | Rem exs int PLB loc 2 (X0324606) | LS | 1 | $5,400.00 | $15,856 | $15,326 |
| 4 | WTR ser int PLB loc 1 (X0324607) | LS | 1 | $28,000 | $14,619 | $14,131 |
| 5 | WTR ser int PLB loc 2 (X0324608) | LS | 1 | $28,000 | $15,368 | $14,855 |
| 6 | Rem exs san sep loc 1 (X0324609) | LS | 1 | $86,000 | $191,000 | $191,087 |
| 7 | Rem exs san sep loc 2 (X0324610) | LS | 1 | $82,000 | $191,000 | $182,852 |
| 8 | Rem exs S E S D loc 1 (X0324611) | LS | 1 | $8,000.00 | $14,300 | $8,505.95 |
| 9 | Rem exs S E S D loc 2 (X0324612) | LS | 1 | $8,000.00 | $14,300 | $8,505.95 |
| 10 | San elec S&D loc 1 (X0324613) | LS | 1 | $125,000 | $127,000 | $115,438 |
| 11 | San elec S&D loc 2 (X0324614) | LS | 1 | $155,000 | $166,000 | $144,160 |
| 12 | San sew sep TK loc 1 (X0324615) | LS | 1 | $88,000 | $73,000 | $93,396 |
| 13 | San sew sep TK loc 2 (X0324616) | LS | 1 | $88,000 | $73,000 | $94,916 |
| 14 | PCK SX LFT sta loc 1 (X0324617) | LS | 1 | $52,000 | $54,000 | $65,191 |
| 15 | PCK SX LFT sta loc 2 (X0324618) | LS | 1 | $60,000 | $54,000 | $71,372 |
| 16 | PCK DP LFT sta loc 1 (X0324619) | LS | 1 | $83,000 | $77,000 | $86,042 |
| 17 | PCK DP LFT sta loc 2 (X0324620) | LS | 1 | $83,000 | $78,000 | $86,430 |
| 18 | V. DL aug SCN loc 1 (X0324621) | LS | 1 | $145,000 | $176,000 | $189,765 |
| 19 | V. DL aug SCN loc 2 (X0324622) | LS | 1 | $145,000 | $176,000 | $189,765 |
| 20 | Drain field sys loc 1 (X0324623) | LS | 1 | $143,000 | $310,000 | $254,517 |
| 21 | Drain field sys loc 2 (X0324624) | LS | 1 | $166,600 | $330,000 | $271,103 |
| 22 | San sew PVC 8 (X1200198) | LF | 969 | $72.00 | $76.00 | $103.56 |
| 23 | Pres test & disinfect (X1200230) | LS | 1 | $27,000 | $20,000 | $13,624 |
| 24 | San sew remov 8 (X5510308) | LF | 562 | $20.00 | $36.00 | $24.21 |
| 25 | D I WTR MN fittings (X5610004) | LB | 471 | $30.00 | $36.00 | $26.91 |
| 26 | Flush hydrants (X5610017) | EACH | 3 | $6,100.00 | $6,901.00 | $7,059.50 |
| 27 | Cas pipe bor/JKD 12 (X5610054) | LF | 171 | $700.00 | $1,325.00 | $1,633.93 |
| 28 | WTR serv MTR & vault (X5620004) | LS | 1 | $10,000 | $17,000 | $19,948 |
| 29 | Pipe drains 4 SPL (X6011605) | LF | 1,755 | $46.00 | $83.00 | $36.43 |
| 30 | Man TA san 4D T1F CL (X6022858) | EACH | 8 | $5,600.00 | $12,400 | $14,177 |
| 31 | San man removed (X6026054) | EACH | 4 | $1,100.00 | $1,750.00 | $1,248.20 |
| 32 | Traf cont & prot SPL (X7010216) | LS | 1 | $58,000 | $37,000 | $43,586 |
| 33 | Construction layout (Z0013798) | LS | 1 | $23,000 | $48,000 | $45,214 |
| 34 | SS 1 wat MN 12 (Z0056648) | LF | 40 | $158.00 | $129.00 | $117.17 |
| 35 | Steel casings 10 (Z0067200) | LF | 55 | $123.00 | $290.00 | $155.43 |
| 36 | Earth excavation (20200100) | CY | 3,430 | $15.00 | $68.00 | $177.56 |
| 37 | Trench backfill (20800150) | CY | 300 | $74.00 | $129.00 | $102.48 |
| 38 | Seeding CL 2 (25000200) | ACRE | 6.50 | $1,815.00 | $2,530.00 | $1,887.26 |
| 39 | Seeding CL 5 (25000320) | ACRE | 4 | $3,125.00 | $3,410.00 | $5,805.31 |
| 40 | Nitrogen fert nutr (25000400) | LB | 554 | $2.00 | $2.20 | $1.81 |
| 41 | Phosphorus fert nutr (25000500) | LB | 554 | $2.00 | $2.20 | $1.81 |
| 42 | Potassium fert nutr (25000600) | LB | 554 | $2.00 | $2.20 | $1.81 |
| 43 | Erosion contr blanket (25100630) | SY | 28,474 | $1.25 | $1.45 | $2.02 |
| 44 | Temp eros contr seed (28000250) | LB | 1,228 | $2.50 | $5.50 | $5.32 |
| 45 | Temp ditch checks (28000305) | LF | 42 | $13.00 | $54.00 | $6.58 |
| 46 | Perimeter eros bar (28000400) | LF | 2,463 | $4.50 | $2.50 | $3.27 |
| 47 | Inlet & pipe protect (28000500) | EACH | 8 | $200.00 | $284.00 | $179.63 |
| 48 | Inlet filters (28000510) | EACH | 7 | $250.00 | $328.00 | $181.27 |
| 49 | Temp eros contr blank (28001100) | SY | 28,474 | $1.00 | $1.05 | $2.02 |
| 50 | Agg subgrade improve (30300011) | TON | 380 | $82.00 | $78.00 | $95.80 |
| 51 | Agg surf course TY B (40200800) | TON | 678 | $63.00 | $78.00 | $47.84 |
| 52 | PC conc sidewalk 5 (42400200) | SF | 1,638 | $16.00 | $18.75 | $13.50 |
| 53 | Pavement rem (44000100) | SY | 263 | $50.00 | $54.00 | $66.63 |
| 54 | Comb curb gutter rem (44000500) | LF | 184 | $20.00 | $17.50 | $24.60 |
| 55 | Sidewalk rem (44000600) | SF | 1,638 | $4.25 | $3.50 | $3.78 |
| 56 | Welded wire reinf (44200050) | SY | 215 | $12.00 | $27.00 | $15.67 |
| 57 | CL B patch T4 8 (44200944) | SY | 139 | $175.00 | $176.00 | $135.10 |
| 58 | CL B patch T4 10 (44200976) | SY | 124 | $240.00 | $204.00 | $174.60 |
| 59 | Dowel bars 1 1/4 (44201298) | EACH | 280 | $28.00 | $16.50 | $23.73 |
| 60 | Dowel bars 1 1/2 (44201299) | EACH | 270 | $29.00 | $17.90 | $27.73 |
| 61 | Saw cuts (44213200) | LF | 400 | $6.50 | $7.75 | $3.19 |
| 62 | Tie bars 3/4 (44213204) | EACH | 61 | $27.00 | $17.10 | $21.10 |
| 63 | Pipe culvert remov (50105220) | LF | 6 | $18.00 | $75.00 | $113.51 |
| 64 | P cul CL D 1 eqrs 18 (542D5473) | LF | 43 | $96.00 | $120.00 | $176.79 |
| 65 | PRC flar end sec 15 (54213660) | EACH | 1 | $1,850.00 | $1,991.00 | $2,291.06 |
| 66 | Storm sew CL A 1 15 (550A0070) | LF | 50 | $112.00 | $107.00 | $136.40 |
| 67 | Water main 6 (56100600) | LF | 950 | $74.00 | $97.00 | $66.58 |
| 68 | D I water main 6 (56103000) | LF | 75 | $165.00 | $340.00 | $118.61 |
| 69 | Water valves 6 (56104900) | EACH | 5 | $2,500.00 | $2,850.00 | $3,192.42 |
| 70 | Tap valve & sleeve 6 (56108800) | EACH | 1 | $7,600.00 | $5,800.00 | $6,998.17 |
| 71 | Water serv line 6 (56201160) | LF | 4,872 | $50.00 | $75.50 | $48.33 |
| 72 | Inlets adj new T9F&G (60261100) | EACH | 1 | $1,780.00 | $1,450.00 | $1,514.33 |
| 73 | Comb CC&G TB6.12 (60603800) | LF | 53 | $110.00 | $89.00 | $65.46 |
| 74 | Comb CC&G TY B-6.24 (60605000) | LF | 103 | $115.00 | $95.00 | $61.03 |
| 75 | Comb CC&G TB9.12 (60605900) | LF | 29 | $120.00 | $155.00 | $106.77 |
| 76 | CH LK fence 4 (66400105) | LF | 571 | $48.00 | $51.50 | $49.89 |
| 77 | CH LK gates 4X8 DBL (66405600) | EACH | 2 | $5,700.00 | $6,188.00 | $5,980.75 |
| 78 | Engr field office B (67000500) | CAL MO | 7 | $3,400.00 | $3,800.00 | $2,020.39 |
| 79 | Mobilization (67100100) | LS | 1 | $190,000 | $269,000 | $276,351 |
| 80 | Seal aban water wells (67201000) | EACH | 1 | $12,000 | $9,800.00 | $17,034 |
| 81 | Traf cont-prot 701422 (70100315) | EACH | 2 | $1.00 | $20,000 | $2,708.07 |
| 82 | Traf cont-prot 701201 (70100450) | LS | 1 | $5,500.00 | $5,000.00 | $4,382.20 |
| 83 | Traf cont-prot 701406 (70100700) | LS | 1 | $71,000 | $20,000 | $25,367 |
| 84 | Traf cont-prot 701451 (70100820) | LS | 1 | $21,000 | $8,500.00 | $7,647.99 |
| 85 | TR cont & prot 701801 (70102640) | LS | 1 | $4,000.00 | $4,500.00 | $3,109.59 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of July 31, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way